1. When are the pollutant diagnosis and the waste disposal plan (Art. 16 OLED) mandatory?
Two federal triggers that a craftsman must know before demolishing, chiselling or drilling an old building.
1.1 The two federal triggers: building constructed before 1 January 1991 (asbestos / PCB before 1990) or waste volume above 200 m³
A pollutant diagnosis is required before works on a building constructed before 1991 for asbestos and around 1990 for PCB. The waste disposal plan is mandatory from 200 m³ of construction waste (Art. 16 OLED). The reference points in our sheets must be confirmed in the texts in force.
1.2 Stricter cantonal specificities (Vaud LATC Art. 103a, Geneva, Valais) and the client's responsibility
Several cantons impose stricter rules than the Confederation (diagnosis, notification, inspection). We have not re-read these cantonal articles, including Art. 103a LATC of Vaud: check them with the authority of your canton. The client remains responsible for providing the diagnosis.
2. How to use the OLED Excel form and the OMOD code table to price your skips
A badly sorted skip costs more than one sorted at source: the disposal route depends on the material.
2.1 Distinction between Type A landfill (clean excavation), Type B (mineral inert materials), Type E (reactive materials) and OMOD special waste
The type of landfill depends on the quality of the materials: unpolluted excavation, mineral inert materials, reactive materials, special waste subject to the OMOD. Rates per tonne vary by landfill; those in the workbook are indicative and must be confirmed with your landfill.
2.2 CFST 6503 work categories (Green, Orange, Red): what a craftsman is entitled to remove himself vs a SUVA-recognised asbestos removal company
The green, orange, red classification in our sheets distinguishes bonded and intact materials, small-scale interventions and friable materials: the last level falls under a specialised remediation site with notification to the authority. The precise rules are set by Suva: consult them before any intervention.
3. Frequently asked questions about asbestos and OLED construction waste (FAQ)
3.1 Who must pay for the asbestos diagnosis before works and the OLED disposal plan?
The diagnosis is in principle the responsibility of the client, owner of the building, who must provide it before the works. The disposal plan is drawn up for the site: state in the quote who provides it and invoice it if you are asked for it.
3.2 Why should you never mix plaster (calcium sulphate) in a skip of inert mineral rubble (Type B)?
Plaster is a waste that does not meet the criteria for Type B inert materials: a mixture downgrades the whole skip to a more expensive route, at your expense if you caused the mixture. Sort plaster at source.
3.3 Which asbestos reservation clause should be inserted in every quote for renovating a building from before 1991?
State that the price assumes the absence of pollutants, that the client provides the diagnosis before the works begin, and that any discovery stops the site and gives rise to a change order (avenant). No intervention on a suspect material without a report.
Keywords covered: waste disposal plan site OLED art 16 excel · 200 m3 threshold construction waste Switzerland · asbestos diagnosis mandatory before 1991 PCB 1990 · CFST 6503 guideline categories green orange red · site waste code list OMOD Switzerland · landfill rate type B type E rubble tonne.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.