AEAI Fire-Resistance Checker (REI 30/60/90) & Snow Load Calculator by Altitude

Check the AEAI fire-resistance requirements (REI 30/60/90) and calculate the snow load by altitude.

Interactive tool

A Snow load on the roof (SIA 261 standard)

m
m
°

Snow load

Equivalent altitude h_eq = h0 + Δh
Characteristic ground snow load sk
Roof shape coefficient μ1
Snow load on the roof qk = μ1 × Ce × Ct × sk

sk = max(0.90 ; (1 + (h_eq / 350)²) × 0.40) in kN/m² (floor value of 0.90 kN/m², about 90 kg/m²). Formula and coefficients from the specification, based on the SIA 261 standard: confirm them in the standard before sizing the roof structure.

B Fire protection requirements (AEAI directives)

6 Building height category

Instant AEAI requirements

Fire resistance and reaction-to-fire requirements by building height
ItemRequirement

R: mechanical strength; E: integrity against flames and gases; I: thermal insulation; the duration is in minutes. Height thresholds (11 m and 30 m), durations and classes from the specification, not verified in the 2015 AEAI standard: the fire protection concept and the cantonal insurance institution prevail.

Embed this calculator on a website page

Paste this code into the page, or write [outil code="5.9"] in the content of a page on the site.

📄 File linked to this tool (free)

Move from calculation to full management

Keep your references at hand, then automate them in your quotes, bids and final statements.

⚡ Automate this calculation in our ERP / Soumission software (Trial)

Technical reference guide

AEAI Fire Protection Directives in Switzerland: understanding the R, E, I codes and the RF1, RF2, RF3 classes

The fire protection requirements AEAI EI30 REI60 RF1 are read with three letters followed by a duration in minutes: R for the mechanical strength of a load-bearing element, E for integrity against flames and hot gases, I for the thermal insulation of the unexposed face. REI 60 therefore designates a load-bearing and separating element that holds for one hour; EI 30, a non-load-bearing element (apartment door, partition) that remains tight and insulating for half an hour. The materials reaction to fire RF1 RF2 RF3 are classified according to their contribution to the fire: RF1 is non-combustible (concrete, brick, steel, plaster), RF2 contributes slightly, RF3 to an acceptable degree (solid timber generally falls into this class).

REI 30 / REI 60 / EI 30 requirements by building height (thresholds of 11 metres and 30 metres)

The building height category 11m 30m AEAI is the first criterion: the taller the building, the harder evacuation and fire brigade intervention become, and the longer the structure must resist fire. The requirements in the tool's specification are as follows.

Fire resistance requirements by building height category
Height categoryLoad-bearing structureApartment entrance doorsStairwellVertical escape routes
1. Low-rise building (h ≤ 11 m — house, small block (R+2))R 30 (or no requirement for a detached house of 11 m at most)EI 30per the AEAI directive (small building)RF1
2. Medium-rise building (11 m < h ≤ 30 m — standard block R+3 to R+8)REI 60EI 30REI 60RF1
3. High-rise building / tower (h > 30 m)REI 90EI 30REI 60RF1

Clarification on the text of the standard. The height thresholds of 11 m and 30 m, the resistance durations and the RF1 class are those of the tool's specification, based on the AEAI fire protection directives; they were not found in the text of the 2015 standard. For an underground car park, a hotel, a hospital, a school or an industrial premises, additional or use-specific requirements may apply: the tool flags this without detailing them. The project's fire protection concept and the cantonal insurance institution prevail.

SIA 261 standard: how to calculate the snow load per m2 on a roof according to altitude (sk and qk)

The snow load calculation roof altitude SIA 261 is done in two steps. First the characteristic snow load sk on the Swiss ground is determined, which depends only on the equivalent altitude h_eq = h0 + Δh (h0 is the site altitude and Δh a regional correction from −200 m to +400 m depending on the climatic region): sk = max(0.90 ; (1 + (h_eq / 350)²) × 0.40) in kN/m². It is then converted into a load on the roof: qk = μ1 × Ce × Ct × sk, with μ1 the roof shape coefficient, Ce the wind exposure coefficient (1.0 normal, 0.8 windswept, 1.2 sheltered) and Ct the thermal coefficient (1.0).

Example from the tool: at 600 m, sk = 1.58 kN/m² (about 161 kg/m²). On a roof at 25° without a snow guard, μ1 = 0.80 and qk = 1.26 kN/m², that is about 128 kg/m². The floor of 0.90 kN/m² (about 90 kg/m²) applies at low altitude, below about 391 m, where the formula alone would give less.

The official Swiss formula as a function of altitude and the trap of snow guard bars (coefficient μ1 = 0.8)

Without a snow guard, snow slides off steep roofs: μ1 equals 0.80 from 0° to 30°, decreases linearly according to μ1 = 0.8 × (60 − α) / 30 between 30° and 60°, and falls to zero from 60°. With a snow guard or snow fence that prevents sliding, the snow stays on the roof: μ1 stays at 0.80 whatever the pitch. This is the classic trap: a roof at 45° sized without a snow guard receives 0.63 kN/m² in the calculation, but if snow guard bars are then fitted, the real load is 1.26 kN/m².

Shape coefficient μ1 and load on the roof at 600 m according to pitch
Pitch αμ1 without snow guardqk without snow guardμ1 with snow guardqk with snow guard
20°0,8001,26 kN/m²0,8001,26 kN/m²
30°0,8001,26 kN/m²0,8001,26 kN/m²
40°0,5330,84 kN/m²0,8001,26 kN/m²
45°0,4000,63 kN/m²0,8001,26 kN/m²
50°0,2670,42 kN/m²0,8001,26 kN/m²
60°0,0000,00 kN/m²0,8001,26 kN/m²
70°0,0000,00 kN/m²0,8001,26 kN/m²

The formula for sk, the floor of 0.90 kN/m² and the coefficients μ1, Ce and Ct are those of the tool's specification, based on the SIA 261 standard: check them in the standard before sizing the roof structure. Local accumulations (valleys, lower areas, penthouses) and fresh snow on a flat roof require a specific calculation.

Table of reference snow loads in the lowlands (400 m), in the mid-mountains (800 m) and in an alpine resort (1500 m)

The table applies the tool's formula to three typical altitudes, for a roof at 25° without a snow guard (μ1 = 0.80), with Ce = 1.0 and Ct = 1.0 and without regional correction:

Reference snow loads by altitude
SituationAltitudesk on the groundqk on the roofqk in kg/m²
Lowlands400 m0,92 kN/m²0,74 kN/m²≈ 75 kg/m²
Mid-altitude mountains800 m2,49 kN/m²1,99 kN/m²≈ 203 kg/m²
Alpine resort1'500 m7,75 kN/m²6,20 kN/m²≈ 632 kg/m²

The load grows rapidly with altitude: it is multiplied by 8.4 between the lowlands and a resort at 1 500 m, which changes the section of the purlins, rafters and fixings. For a roof in a seismic zone, see also the SIA 261 seismic zone checker.

⚡ Cost your roof structure and roofing in Soumission

Frequently Asked Questions on AEAI Fire Protection and Snow Load (FAQ)

1. What is the difference between EI 30 and REI 60 in the AEAI directives?

The letters describe what the element must retain during the fire: R for mechanical strength (load-bearing capacity), E for integrity against flames and hot gases, I for the thermal insulation of the unexposed face, followed by the duration in minutes. REI 60 applies to a load-bearing and separating element (slab, load-bearing wall, stairwell) that holds for 60 minutes; EI 30 to a non-load-bearing element (apartment door, partition) that provides integrity and insulation for 30 minutes. According to the specification, a medium-rise building requires REI 60 for the structure, EI 30 for apartment doors and REI 60 for the stairwell.

The thresholds by height (11 m and 30 m) and by use are those of the specification and were not verified in the 2015 AEAI standard: the fire protection concept and the cantonal insurance institution prevail.

2. Which formula gives the snow load on a roof according to altitude (SIA 261)?

According to the tool's specification, the ground snow load is sk = max(0.90 ; (1 + (h/350)²) × 0.40) in kN/m², with h the equivalent altitude (reference altitude plus the regional correction). The load on the roof is qk = μ1 × Ce × Ct × sk. At 600 m, sk = 1.58 kN/m² and, for a roof at 25° (μ1 = 0.80), qk = 1.26 kN/m², that is about 128 kg/m². At 45° without a snow guard, the snow partly slides off (μ1 = 0.40, qk = 0.63 kN/m²); with a snow guard, μ1 stays at 0.80 (qk = 1.26 kN/m²).

A snow guard holds the snow on the roof: forgetting it in the calculation undersizes the roof structure and the fixings. The formula and the coefficients μ1, Ce and Ct are those of the specification; check them in the SIA 261 standard before sizing.

3. Which materials are allowed in a stairwell requiring RF1?

RF1 designates non-combustible materials, which do not contribute to the fire: concrete, brick, natural stone, steel, glass, plaster. The specification requires this class for vertical escape routes (stairwell). RF2 materials contribute slightly to the fire, RF3 to an acceptable degree and RF4 to an unacceptable degree: solid timber generally falls into RF3 and is therefore not suitable where RF1 is required.

Coverings, insulation, cables and joinery also count: the class is justified by the product's certificate. Possible derogations (small buildings) are checked in the AEAI directive and in the fire protection concept; these classes were not checked in the standard.

Indicative information based on the AEAI fire protection directives and the SIA 261 standard; it does not replace the fire protection concept or the calculation of a civil engineer.