1. What does the Excel workbook for managing daywork and change orders contain?
Two sheets for two moments: the report that the foreman fills in the same day, and the dashboard that the site manager consults every week so that no daywork is left without sign-off.
1.1 Sheet 1 — The daywork report sheet ready to print or fill in (qualifications, hours, materials, machinery, weather and DT sign-off)
The sheet records the date, the site, the request of the site management (DT), the workers by qualification, the hours, the materials supplied, the machinery used and the weather conditions. A sign-off line allows the DT to sign on site, which turns work requested « verbally » into a priced document.
1.2 Sheet 2 — The monthly dashboard of daywork awaiting signature with an alert on the 7-day return deadline (Art. 47 SIA 118)
The table lists each report submitted, the submission date and the return date of the signed-off report. According to SIA 118 (to be checked in the applicable edition), the report is returned within 7 days and discrepancies are notified within one month: the workbook colours in red the daywork whose deadline has passed.
2. The strict legal procedure of articles 44 to 57 of the SIA 118 standard
SIA 118 regulates daywork and the remuneration of additional services in a series of articles, which the workbook summarises. Their exact numbering must be checked in the edition of the standard attached to your contract.
2.1 Why the signature of the site manager amounts to irrevocable acknowledgement of the hours and materials used
A report signed off without reservation is the best proof that the hours and materials were ordered and consumed. If the DT disputes it, it must do so within the deadline provided: after that, it is very difficult to challenge quantities that it signed itself. So have each report signed off by the next day at the latest.
2.2 The 3 legal surcharges that 70% of craftsmen forget to enter on their daywork slips (tools, transport, coordination)
The daywork rate includes salary and contributions, but ordinary tools, transport and coordination or supervision are the subject of surcharges or separate lines depending on the contract and the SIA scales. Our fact sheet lists these three items so that they appear on every slip.
3. Frequently asked questions about daywork slips in construction in Switzerland (FAQ)
3.1 What should you do if the site manager refuses to sign or does not return the daywork report within 7 days?
Send the report by e-mail with acknowledgement of receipt and a written reminder: « without a reply within 7 days, we consider the quantities to be correct ». Photograph the work before it is covered over. Silence is not agreement, but it weakens the DT's late challenge.
3.2 Does the global discount granted on the main quote apply automatically to daywork?
Not automatically: it all depends on the contract. The discount agreed on the offer applies in principle to the unit prices of the offer, whereas daywork is invoiced at the agreed daywork rate. State in the offer whether the discount also covers daywork.
3.3 What is the difference between a daywork report (Art. 47 SIA 118) and a change order (Art. 86 SIA 118)?
Daywork remunerates work by the hour on instruction, without a price agreed in advance. The change order fixes the price of a change before it is carried out; Art. 86 SIA 118 also allows unit prices to be adjusted when quantities vary by more than 20%. An agreed price is safer than a contestable daywork.
Keywords covered: daywork report template Switzerland excel · daywork slip construction site free pdf · tracking additional works SIA 118 art 47 · deadline signing daywork slip 7 days site management · contesting daywork invoice 30 days · invoicing tools and machinery as daywork.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.