Cost Overrun on Works Quotes in Switzerland: Legal Rules (Art. 373 & 375 CO vs SIA 118) & Change Order Templates

Complete 5-page guide (PDF) and Word template. Lump-sum price, approximate quote or unit prices: who pays for the overrun, how to report it in time, notice, request for adjustment, the client's reply and a change-order form.

Interactive tool: share of the overrun that is payable depending on the contract regime

Loading the tool…

📄 The « Brut de chantier » pack to download (free)

PDFDOCX ⚖️ 'Pure Law' File

Cost Overrun on a Quote Pack (lump sum, estimate, SIA 118)

Complete 5-page guide (PDF) and Word template. Lump-sum price, approximate quote or unit prices: who pays for the overrun, how to report it in time, notice, request for adjustment, the client's reply and a change-order form.

  • The three price regimes (Art. 373 to 375 CO, SIA 118) at a glance
  • Procedure for the contractor and for the client
  • Letters, change order form to have signed before execution, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted

Printable PDF document · Editable Word template (.docx)

1. The 3 price regimes in Swiss construction law (and why a single word changes everything)

« Lump sum », « estimate » and « unit prices » are not synonyms: each word triggers a different regime when the final cost exceeds the starting figure.

1.1 The lump-sum or global-price contract (Art. 373 CO / Art. 41 SIA 118): ban on invoicing a supplement without a change of order

With a lump-sum price, the contractor can in principle claim no increase, even if the work required more effort than planned (Art. 373 para. 1 CO). Only extraordinary circumstances that could not be foreseen can justify an increase or termination (para. 2); a supplement requires a change of order.

1.2 The approximate or indicative estimate (Art. 375 CO): the case-law rule of the +10% tolerance and the sharing of the surplus

If the approximate estimate is exceeded to an excessive extent through no fault of the client, the latter may withdraw from the contract; for a building on its own land, it may ask for a reasonable reduction of the price (Art. 375 CO). Case law adopts a benchmark of the order of 10%: this is not a figure in the law.

1.3 The unit-price contract on measurement (Art. 39 and 86 SIA 118): invoicing of actual quantities and price revision beyond ±20%

With unit prices, the invoice follows the quantities actually executed. According to our SIA 118 fact sheets (Art. 86), each party may ask for unit prices to be adjusted when quantities vary by more than 20% up or down: check the article in your edition.

Consequences by party involved

Party involvedWhat the law says for them
ContractorLump sum: claims nothing without a change of order (CO 373); approximate estimate: risks reduction beyond the 10% benchmark (CO 375); unit prices: follows the measurements.
SubcontractorPasses on the same regime as that of its own contract; warns without delay and has the change order signed.
ClientMay withdraw or ask for a reduction if the overrun is excessive through no fault of its own; must be warned before execution.

2. The mandatory duty to warn the client « without delay » and the architect's liability

The law does not penalise the overrun itself, but the silence. Whoever sees the overrun coming must say so before carrying it out.

2.1 Why waiting for the final invoice to announce an overrun makes you lose the right to payment before the court

A client who learns of the overrun in the final statement can no longer choose: reduce the project, change the services, give up. The courts penalise this loss of choice by reducing the invoice or refusing the supplement. Send a written notice as soon as the gap looms.

2.2 The architect's personal liability in the event of an overall estimation error above 10% (case law ATF 122 III 61)

An architect or site management that delivers a markedly exceeded estimate without reservation may incur liability. Federal case law mentions a benchmark close to 10%, but the decision cited must be checked before being invoked in a dispute: consult a lawyer.

3. Frequently asked questions about quote overruns in Switzerland (FAQ)

3.1 Does the client have the right to demand a discount if the actual measured quantities are more than 20% below the quote?

With SIA 118 (Art. 86, to be checked in the applicable edition), a variation of more than 20 allows each party, and so the client too, to ask for the unit prices to be adjusted. Without SIA 118, everything depends on the contractual clause on quantities.

3.2 What is the legal tolerance of an architect's quote in the preliminary-design phase vs the project design phase under SIA 102?

SIA 102 deals with fees and service phases, not with a single legal tolerance. The expected accuracy of an estimate increases as the project progresses: a preliminary design is less accurate than a detailed quote. The usual tolerances vary according to the phases: read the standard.

3.3 How do you word a change order on site so that it is incontestable?

State the site, the precise subject, the price (lump sum or unit price HT), the impact on deadlines, and have the client or its representative sign before execution. Date and number the change order and attach it to the next progress statement.

Keywords covered: cost overrun quote works Switzerland law · 10% tolerance construction quote art 375 CO · difference lump-sum price and unit price on measurement art 373 CO · architect liability budget overrun ATF 122 III 61 · duty to warn client without delay quote overrun · change order template quote overrun Switzerland.

General information based on Swiss law in force — does not replace personalised legal advice.

The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.