Complete 6-page guide (PDF) and Word template. Bidding together as two without paying alone for the other's mistakes: full internal agreement, liability towards the client, default, exits, letters and end-of-lot report.
Interactive tool: maximum financial exposure under a consortium, subcontracting or separate lots
Loading the tool…
📄 The « Brut de chantier » pack to download (free)
PDFDOCX⚖️ 'Pure Law' File
Secure Consortium Agreement (simple partnership) & Minutes (PV) of the Condition at End of Lot
Complete 6-page guide (PDF) and Word template. Bidding together as two without paying alone for the other's mistakes: full internal agreement, liability towards the client, default, exits, letters and end-of-lot report.
Simple partnership (Art. 530 to 551 CO): legal basis, liability towards the client
Internal consortium agreement and minutes (PV) of the condition at end of lot
Three letters, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted
Printable PDF document · Editable Word template (.docx)
1. The legal trap of the « simple partnership » (Art. 530 to 551 CO) when two SMEs bid together
Two companies that respond together to a call for tenders do not create a new limited-liability company: by default they form a simple partnership, with all its consequences for their assets.
1.1 Article 544 para. 3 of the Code of Obligations: why you answer with 100% of your assets for the debts, delays and defects of your partner
The partners are jointly and severally liable for the commitments they have assumed towards third parties by acting jointly or through a representative; contrary agreements are valid only between themselves (Art. 544 para. 3 CO). The client may therefore turn to a single partner for the whole.
1.2 Why the internal split « 50/50 » or by lots cannot be invoked against the client if external joint liability is not excluded
The division of lots is valid only between partners: it changes nothing about what the client can claim. Only a clause expressly accepted by the client can exclude external joint liability. For the rest, the internal agreement sets the right of recourse.
Consequences by party involved
Party involved
What the law says for them
Partner contractor
Is jointly and severally liable for 100% of the consortium's commitments (CO 544 para. 3); internal recourse according to the agreement.
Subcontractor
Is bound only to his own principal; does not commit the consortium.
Client
May claim the whole from a single partner; is not affected by the internal split.
2. Co-activity on site (Art. 30 SIA 118): handling the delay or breakage caused by the preceding trade
On a shared site, your delays or damage also depend on the other trades. Two documents are enough to protect you.
2.1 How to notify at the same time the delay of the preceding lot (Art. 96 SIA 118) and reservations about its work (Art. 25 SIA 118)
Send a single letter that notifies the delay (extension of deadlines, Art. 96 SIA 118) and states reservations about the substrate left by the preceding lot (duty to warn, Art. 25 SIA 118 and Art. 365 para. 3 CO). The articles are to be checked in the applicable edition.
2.2 Having an « end-of-lot condition report (PV) » signed, with time-stamped photos, as soon as you leave a room
As soon as you leave a room, have a condition report (PV) signed: zone, condition observed, dated photos, reservations. In the event of later damage, it proves that your lot was finished and clean. Our pack contains the form.
3. Frequently asked questions about consortiums in the building sector in Switzerland (FAQ)
3.1 Is it better to bid as a consortium or as a main contractor with a subcontractor on Simap.ch?
With a main contractor, a single contract binds the successful company, which answers for its subcontractors. The consortium shares visibility and capacity, but increases the joint-liability risk. Read the tender conditions: some limit or regulate consortiums.
3.2 Which internal clauses should be required in a consortium agreement (cross-guarantee, lead company, joint account)?
At a minimum: allocation of lots by CFC, internal responsibility of each partner for his lots, full recourse, own guarantees and RC for each, right to take over the lot of a defaulting partner, decision rules by unanimity. Our pack provides these key clauses.
3.3 Can a consortium partner bind the simple partnership by ordering equipment without my signature?
If the agreement appoints an agent to deal with third parties, he may bind the partnership within the limits of his mandate. Without a written limit, a partner acting in good faith may bind you. Cap by agreement the orders without double signature.
Keywords covered: consortium construction company Switzerland liability · simple partnership art 530 544 para 3 CO joint liability · difference consortium and subcontracting public procurement · template consortium agreement building Switzerland word · damage caused by another craftsman on site SIA 118 art 30 · PV end-of-lot condition report site.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.