1. The golden rule of Swiss quantity measurement (SIA 118 / CAN 211): you price « in place », you transport « bulked » and you pay « per tonne »
The same cubic metre of soil changes volume and weight depending on the stage: in place in the ground, bulked in the skip, weighed at the landfill. Mixing these three measures is costly.
1.1 Complete table of bulking coefficients (1.15 to 1.60) and densities (t/m³) for 25 types of ground in Switzerland
Our workbook covers 25 materials, from topsoil (1.25) to compact rock (1.60), with their in-place density (0.5 to 2.7 t/m³): for example silt 1.80 t/m³ and 1.25, molasse 2.30 t/m³ and 1.40, demolished reinforced concrete 2.50 t/m³ and 1.60. These are orders of magnitude to be confirmed by a test or by your weighbridge tickets.
1.2 Real payloads permitted in Switzerland for site trucks (26 tonnes, 32 tonnes and 40 tonnes)
Permitted gross weights of 26 t (3 axles), 32 t (4 axles) and 40 t (articulated combination) give payloads of about 15, 20 and 26 tonnes once the tare is deducted. The exact load is read on the vehicle registration document: never exceed the permitted gross weight.
2. How to use the Excel weighbridge ticket tracking book to avoid any loss on the transport/landfill item
Checking weighbridge tickets is the only way to know whether the site is removing more tonnes than planned.
2.1 Checking in real time the gap between the engineer's theoretical volume and the tonnes actually invoiced by the gravel pit/landfill
The book lists each weighbridge ticket (date, material, truck, tonnes, rate) and totals tonnes and amount. By comparing it with the theoretical volume converted into tonnes, you immediately spot a density or quantity discrepancy.
3. Frequently asked questions about bulking and soil transport in Switzerland (FAQ)
3.1 Is an architect entitled to apply a bulking coefficient to the quantities in the CAN 211 bill of quantities?
Earthworks are measured in place: the bill of quantities measures the geometric volume, without bulking. A coefficient applied to the quantities of the bill contradicts the measurement rule; bulking goes into the transport price, not into the quantity.
3.2 How many m³ in place and how many tonnes does a 4-axle truck (32 tonnes gross weight) actually carry?
With a payload of about 20 tonnes, it carries about 11 m³ of body volume and, depending on the density of the material, between 8 m³ of compact rock and 12 m³ of soil in place. It is mass, not volume, that is the limit for dense materials.
3.3 What is the bulking coefficient and the weight per m³ of a demolished reinforced concrete slab?
Our table takes 1.60 for demolished reinforced concrete and 2.50 t/m³ in place. These values are orders of magnitude; your weighbridge tickets confirm the real weight.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.