Electric Charging Points Configurator in PPE according to SIA 2060 (Levels C1 to D2)
Configurator for the EV charging equipment levels (VE; C1 to D2) in PPE car parks.
Interactive tool
Technical leaflet, not a standard; values from the specifications. SIA 2060 is a non-binding technical leaflet (Merkblatt), not consulted. Levels A (Pipe for power), C1 (Power to garage), C2 (Power to parking) and D (Ready to charge) are described by cantonal and industry sources; levels B, C3 and D1 / D2 from the specifications could not be found. Power per active charger with load management: 1,5 to 2,5 kW according to the specifications (2,0 by default), higher than the average energy requirement.
A Sizing tool for dynamic load management (DLM)
Power demand and verdict
- Active chargers
- Power WITHOUT load management
- Energy requirement per vehicle
- Power WITH dynamic load management
- Charging time
Without management: charging points × nominal power. With management: charging points × allocated power. The amperes are calculated in three-phase 400 V (√3 × 400 V). The verdict compares the power with the switchboard reserve and checks that charging fits within the night-time window.
B Decoder of the equipment levels of the SIA 2060 technical leaflet
Selected level
| Level | Designation | Content |
|---|---|---|
| Level A | Pipe for power | Planning, concept study and empty conduits (specification: "planning"). |
| Level B | Level from the specifications | Pre-equipment of the building service entrance: space reserved at the main switchboard and main cable routes (level in the specification). Not found in the sources consulted. |
| Level C1 | Power to garage | Supply and distribution up to the shared garage; cable routes or ducts up to the parking spaces (specification: mandatory at minimum in new buildings). |
| Level C2 | Power to parking | Collective power cabling (flat ribbon cable or collective distribution) up to the parking spaces, with a communication network and dynamic load management (DLM): recommended pre-equipment in condominiums (PPE). |
| Level C3 | Level from the specifications | Plug-and-charge ready per space: junction box and connection run to the individual space (level in the specification). Not found in the sources consulted. |
| Levels D1 / D2 | Ready to charge | Charging point (wallbox) mounted, connected, checked under the OIBT and ready to charge (D1 / D2: subdivision in the specification). |
Levels B, C3 and D1 / D2 come from the tool's specification and were not found in the sources consulted.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.20"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
SIA 2060 technical leaflet in Switzerland: understanding equipment levels C1, C2, C3, D1 and D2 in shared car parks
The SIA 2060 standard electric car charging point car park PPE is actually a technical leaflet (Merkblatt) from the SIA on charging infrastructure for electric vehicles in buildings: it describes progressive equipment levels, from the simple passage of conduits to the installed charging point. The equipment levels C1 C2 C3 D1 D2 SIA 2060 read as follows, based on the tool's specification and cantonal and industry sources:
| Level | Designation | Content |
|---|---|---|
| Level A | Pipe for power | Planning, concept study and empty conduits (specification: "planning"). |
| Level B | Level from the specifications | Pre-equipment of the building service entrance: space reserved at the main switchboard and main cable routes (level in the specification). Not found in the sources consulted. |
| Level C1 | Power to garage | Supply and distribution up to the shared garage; cable routes or ducts up to the parking spaces (specification: mandatory at minimum in new buildings). |
| Level C2 | Power to parking | Collective power cabling (flat ribbon cable or collective distribution) up to the parking spaces, with a communication network and dynamic load management (DLM): recommended pre-equipment in condominiums (PPE). |
| Level C3 | Level from the specifications | Plug-and-charge ready per space: junction box and connection run to the individual space (level in the specification). Not found in the sources consulted. |
| Levels D1 / D2 | Ready to charge | Charging point (wallbox) mounted, connected, checked under the OIBT and ready to charge (D1 / D2: subdivision in the specification). |
Clarification on the text of the standard. The SIA 2060 document is a technical leaflet, non-binding, and was not consulted: the tool does not reproduce it. Levels A ("Pipe for power"), C1 ("Power to garage"), C2 ("Power to parking") and D ("Ready to charge") are described by cantonal and industry sources; levels B, C3 and the D1 / D2 subdivision in the specification were not found in these sources. A cantonal promotion programme may also require specific levels for its subsidies: enquire with your canton's energy office.
Why level C2 (flat ribbon cable + centralised Load Management) is the only viable solution for a condominium (PPE)
The specification recommends level C2 as pre-equipment in condominiums (PPE): a collective power distribution up to the parking spaces, with a communication network and a load management system. The connection power flat ribbon cable underground car park is then that of the single feeder that supplies the flat ribbon cable (an energy bus running along the spaces); each space is then connected to this cable by a tap, without pulling a cable from the switchboard for each charging point. Since the building's connection is shared, the total power of all charging points must not exceed the available reserve: that is the role of load management.
Clarification on the text of the standard. The title of this subsection, taken from the specification, asserts that level C2 is "the only viable solution" for a condominium (PPE): this assertion was not verified, and the tool does not compare the technical solutions with one another; it only calculates the order of magnitude of the power. An electrician and the network operator choose the solution.
Dynamic load management (DLM): how to charge 20 electric cars at night with only 30 to 40 kW available
The dynamic load management DLM load management parking distributes the available power in real time between the connected vehicles. Without it, the nominal power of each charging point must be counted: with 12 charging points of 11 kW, the arithmetic sum is 132 kW, that is about 191 A in three-phase, well beyond an ordinary building service entrance. With load management, the power drawn is capped by the available reserve. The specification uses 1.5 to 2.5 kW per active charging point, that is 18 to 30 kW for 12 charging points.
A vehicle that travels 45 km per day consumes 9.0 kWh (20 kWh per 100 km). For 20 vehicles charged over 10 hours, the table below shows what 30, 35 or 40 kW shared equally allow:
| Available power | Power per vehicle | Energy per vehicle | Kilometres per night |
|---|---|---|---|
| 30 kW (approx. 43 A) | 1,50 kW | 15,0 kWh | 75 km |
| 35 kW (approx. 51 A) | 1,75 kW | 17,5 kWh | 88 km |
| 40 kW (approx. 58 A) | 2,00 kW | 20,0 kWh | 100 km |
With 30 to 40 kW, each vehicle has 1.5 to 2.0 kW: enough to add 75 to 100 km per night, which amply covers the 45 km per day of the example (0.90 kW on average). According to the specification, load management then avoids reinforcing the service entrance and paying a current-increase fee to the distribution network operator.
Clarification on the values. The factor of 1.5 to 2.5 kW per active charging point is that of the specification: it exceeds the average energy need (0.90 kW for 45 km), and therefore leaves a margin. The amperes are calculated in three-phase 400 V. The specification quotes "about 22 to 30 kW" for 12 charging points: the tool calculates 18 to 30 kW with the same charging points. The network operator sets the permissible connection power.
Vote at the General Meeting of the condominium (PPE) and automatic re-billing of the kWh consumed to each co-owner or tenant
In condominium ownership, equipping the common parts of the garage is decided at the general meeting. The majority required depends on the classification of the works under the Civil Code: necessary (art. 647c), useful (art. 647d) or luxurious (art. 647e), which apply to condominium ownership (PPE) through the reference in article 712g. To simulate these majorities, see the condominium (PPE) works voting tool. The classification of a charging infrastructure is not decided here: have it validated by a lawyer before the vote.
The right to a socket electric charging point tenant PPE Switzerland designates the idea of guaranteeing a tenant or a co-owner access to a charging infrastructure in their building. The tool does not settle this question: it depends on the lease or the condominium (PPE) regulations, and on any cantonal rules that were not verified here; the research carried out for this tool did not find a precise Swiss source on the subject.
Re-billing the kWh consumed relies on a meter per charging point or on a system that records each user's consumption, which load management can automate, and on a statement sent to each co-owner or tenant. The condominium (PPE) administrator sets the billing method with the meeting.
Clarification on the text of the standard. The tool does not calculate the majorities, the re-billing or the right to a socket: these points are given for information. For checking the electrical installation after the works, see the electricity and OIBT inspection tool; to generate the charging points' electricity on site, the photovoltaic simulator. ⚡ Price your charging stations in Soumission
Frequently Asked Questions on Charging Points, Load Management and Condominiums (PPE) (FAQ)
1. What do the equipment levels A, B, C1, C2, C3 and D of SIA 2060 mean?
SIA 2060 is a technical leaflet (Merkblatt) on charging infrastructure in buildings, and not a binding standard. Cantonal and industry sources describe the levels as follows: A "Pipe for power" (empty conduits), C1 "Power to garage" (supply up to the garage), C2 "Power to parking" (power distribution up to the parking spaces, with communication and load management) and D "Ready to charge" (charging point installed and ready to charge). The specification adds a level B (pre-equipment of the service entrance), a level C3 (plug-and-charge ready per space) and the D1 / D2 subdivision.
These last three elements (B, C3, D1 / D2) were not found in the sources consulted: the tool displays them as levels from the specification, which recommends level C2 as pre-equipment in condominiums (PPE).
2. How many kW are needed for 12 charging points, with and without load management?
For 24 spaces and 50 % active charging points, that is 12 charging points, the arithmetic sum of 11 kW charging points is 132 kW (about 191 A in three-phase), and 264 kW with 22 kW charging points. With dynamic load management (DLM), the specification allocates 1.5 to 2.5 kW per active charging point: 24 kW (about 35 A) at 2.0 kW per charging point. A vehicle that travels 45 km per day consumes 9.0 kWh, which requires 0.90 kW on average over 10 hours.
The switchboard reserve of 35 kW (about 51 A) is not enough without load management, but is enough with it. The factor of 1.5 to 2.5 kW per charging point is that of the specification: it exceeds the average energy need (0.90 kW) and therefore leaves a margin. At 1.0 kW per charging point, charging a vehicle would take 9.0 hours, that is within the 10-hour window.
3. Can you demand a charging point in a condominium (PPE) or in a rental, and how do you re-bill the kWh consumed?
The tool does not settle the question of the right to a charging point: it depends on the lease or the condominium (PPE) regulations and on any cantonal rules, which were not verified here. In a condominium (PPE), installing a charging infrastructure on the common parts is voted at the general meeting; the majority required depends on the classification of the works (necessary, useful or luxurious, art. 647c to 647e CC): see the condominium (PPE) works voting tool.
Re-billing the kWh is done with a meter per charging point and a statement to each user, which load management can automate. This function is not calculated by the tool; the condominium (PPE) administrator and a lawyer confirm the billing method.
Indicative information based on the tool's specification and cantonal sources; it does not replace the SIA 2060 technical leaflet, or the opinion of an electrician, the network operator or a lawyer.