1. The strict obligations of the SIA 405 standard and of SUVA directive 1417 before the first bucketful
A pulled-out pipe costs a network outage, a site stoppage and sometimes a life. Before opening an excavation, you must know what is in the ground and at what distance. The precise distances and deadlines are set by each operator: ask for them in writing.
1.1 Why a 6-month-old architect's plan is worthless: the obligation to hold SIA 405 extracts less than 30 days old on site
A site plan handed over at the tender stage is not an up-to-date utility plan. Our protocol takes as a reference point that a plan more than a year old or undated is out of date, and recommends requesting the plans just before opening. The exact period of validity (for example 30 days) is set by the operator: ask for it.
1.2 Marking on the ground, prior detection and 50 cm protection zone (manual excavation or suction excavator truck)
Locate the pipes with a detector before opening, mark them on the ground, and replace the mechanical digger with hand-dug trial pits or a suction excavator in the safety zone set by the operator (a reference of 50 cm is often cited). This distance is to be confirmed in writing with the operator.
2. How to invoice the idling of the excavator and the manual excavation in the case of an unlisted pipe
A pipe that is not on the plan is an unforeseen event: it is documented and invoiced.
2.1 Pipe missing from the SIA 405 plan or offset by more than 50 cm: document the discrepancy with a tape measure and have a daywork slip signed immediately
Measure the discrepancy with a tape measure, photograph with a date, stop the digger and have a daywork slip signed by the site management. The cadastre is never guaranteed to the centimetre: this discrepancy is a risk that the quote must provide for or reserve.
3. Frequently asked questions about SIA 405 plans and damage to pipes (FAQ)
3.1 Who must order the SIA 405 underground utility plans: the architect or the civil engineering contractor?
It depends on the contract: the client or the architect must in principle supply the plans at the tender stage. The company that opens the excavation must, for its part, make sure the plans are up to date before excavating. If plans are missing or out of date, write to the client: our pack contains the reservation letter.
3.2 What should you do immediately if the digger bucket catches a warning tape or the duct of an electric or gas cable?
Stop the machine, do not touch the pipe, move people away, cordon off, then alert the operator and 118 for gas or electricity. Photograph, note the time and confirm in writing to the operator, the site management and your liability insurer (RC).
3.3 What is the legal tolerance for the positional accuracy of an old pipe on an SIA 405 plan?
There is no single legal tolerance: accuracy depends on the survey method and the age of the network, and the cadastre is never guaranteed to the centimetre. That is why a hand-dug trial pit is necessary near a pipe.
Keywords covered: standard SIA 405 underground utility plans site Switzerland · SUVA rule 1417 excavation near electric gas pipes · underground cadastre portal SITG ASIT-VD SITValais SITN · 30-day validity extract utility plan excavation · mandatory hand-dug trial pit 50 cm buried pipe · bucket strike cable optical fibre liability RC.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.