Aller au contenu
Website
CFC 0 to 9 Tool 5.3 Online

Overall Construction Budget Simulator (CFC 0 to CFC 9) & Hidden Costs CFC 5

Estimate the overall budget of a project (CFC 0 to 9) and the secondary costs of CFC 5.

Interactive tool

A Your project

CHF
CHF
CHF
CHF
rooms
%
months
Starting percentages and amounts (editable: values from the specification, to be replaced with those of your municipality)
%
% of the land
% of CFC 2
% of CFC 2
CHF / room
% of CFC 2
% of CFC 2
% of the capital
% of CFC 2

Overall project budget

Total project cost incl. TVA (TTC)
Incidental costs CFC 5 (excluding reserve)
Actual ancillary costs (CFC 5 and reserve) relative to CFC 2
Share of the building (CFC 2) in the budget excluding land
Breakdown of the project budget by CFC code
Line itemAmount (CHF)

VAT (TVA) is calculated on the works under CFC 1, 2 and 4; the other items generally do not carry VAT or carry it under other rules. Land financing is not included.

Embed this calculator on a website page

Paste this code into the page, or write [outil code="5.3"] in the content of a page on the site.

📄 File linked to this tool (free)

Move from calculation to full management

Keep your references at hand, then automate them in your quotes, bids and final statements.

⚡ Automate this calculation in our ERP / Soumission software (Trial)

Technical reference guide

The complete structure of the Building Cost Code (CFC 0 to CFC 9) of the CRB in Switzerland

The CFC 0 to 9 list Swiss construction of the Swiss Centre for Construction Rationalisation (CRB) classifies all the costs of a property project into numbered groups. A complete overall budget property development Switzerland adds them all up, not just the building. In the tool's example (land of 500'000 CHF, building of 950'000 CHF), the total cost of the project is 1'781'444 CHF incl. VAT (TTC).

The groups of the Building Cost Code and their amount in the tool's example
CodeGroupExample (CHF)Content
CFC 0Land522'500land price and acquisition costs
CFC 1Preparatory works35'000demolition, special earthworks, temporary connections
CFC 2Building950'000structural work, finishing work, building services
CFC 3Operating equipment—not priced by the tool (depending on use)
CFC 4Landscaping & External Works65'000garden, access, fencing
CFC 5Incidental costs76'394permits, models, insurance, financing
CFC 58Contingency reserve47'500classed under "CFC 9" in the specification
CFC 9Furnishings and decoration—not priced by the tool

Why the building cost (CFC 2) is only 75 % to 82 % of the total budget excluding land

The price of the CFC 2 works is the figure that gets quoted, but it is not the budget. In the example, the CFC 2 of 950'000 CHF weighs 80.9 % of the budget excluding land of 1'173'894 CHF: the rest is divided between preparatory works, outdoor works, the secondary costs of CFC 5 and the contingency reserve. The ancillary costs (CFC 5 and reserve) represent 13.0 % of CFC 2. A budget that stops at CFC 2 is therefore underestimated by 18 % to 25 % before even buying the land. For the areas and volume on which this cost is based, see the SIA 416 areas calculator.

Clarification on the text of the standard. The contingency reserve comes under CFC 58 (secondary costs) in the CRB code; the tool's specification files it under "CFC 9", which designates furnishing and decoration. The tool counts it as a reserve, with the ancillary costs.

X-ray of CFC 5 (Secondary costs): the 5 items that make construction budgets slip

The calculation CFC 5 secondary costs connection fees permit adds up five items that are often forgotten. In the example, CFC 5 reaches 76'394 CHF and the reserve 47'500 CHF:

The CFC 5 items at default values
Line itemCalculation basisAmount
CFC 51: permits and feespermit 0.80 % + connections 3.50 % of CFC 2 + civil-defence shelter (PC)47'175 CHF
CFC 52: samples, models, copies0,30 % of CFC 22'850 CHF
CFC 53: client's insurance (ATC and RC)0,45 % of CFC 24'275 CHF
CFC 54: financing (interim interest and commissions)capital × drawdown × rate × duration / 12 + 0.50 %22'094 CHF
Contingency reserve (CFC 58)5,0 % of CFC 247'500 CHF

Municipal connection fees (water, sewage treatment, electricity grid) and civil-defence shelter (PC) fee

The connection fees for the water, sewer and electricity networks, and the building permit fee, are set by the municipality and the network operator. The tool uses 0.80 % of CFC 2 for the permit (7'600 CHF) and 3.50 % for the connections (33'250 CHF). The cost fee civil-defence shelter PC Swiss civil protection replaces the construction of a shelter: the tool counts 1'150 CHF per habitable room (the specification quotes 800 to 1'500 CHF), that is 6'325 CHF for 5.5 rooms. These values are benchmarks from the specification: ask for the fee schedule of your municipality and your canton.

Calculating the interim interest on the construction loan and the ATC/RC MO insurance

The interim interest construction loan calculation follows the progressive drawdown of the loan: capital of the works × average drawdown × rate × duration / 12, plus bank commissions. With 1'050'000 CHF of works (CFC 1, 2 and 4), 50 % average drawdown, a rate of 2.75 % and 14 months, the interest is 16'844 CHF, plus 5'250 CHF of commissions: 22'094 CHF of CFC 54. The client's insurance (construction works insurance ATC and the client's liability RC MO) costs 4'275 CHF at 0.45 % of CFC 2; it is separate from the liability insurance of each contractor, as the liability and ATC diagnosis explains.

Summary table of the CFC 1, CFC 4 and CFC 5 ratios for a villa or a small apartment building

These ratios, calculated with the tool's parameters, give an order of magnitude for comparing your budget with a typical project. The fees of the appointed professionals, which are not included in the tool's secondary costs, are priced with the fee simulator by phase.

CFC 1, CFC 4 and CFC 5 ratios relative to CFC 2
Ratio to CFC 2Villa (CFC 2: 950'000 CHF)Small apartment building (CFC 2: 6'000'000 CHF)
CFC 1, preparatory works3,7 %3,0 %
CFC 4, landscaping and external works6,8 %5,3 %
CFC 5, incidental costs8,0 %8,8 %
Ancillary costs (CFC 5 and reserve)13,0 %13,8 %
CFC 2 in the budget excluding land80,9 %81,9 %
Total project cost incl. TVA (TTC)1'781'444 CHF10'469'458 CHF

The small apartment buildings in the example use land of 2'500'000 CHF, preparatory works of 180'000 CHF, outdoor works of 320'000 CHF, 40 rooms and 20 months on site. All the percentages are those of the specification, to be replaced with the values of your municipality and your canton.

⚡ Track the actual cost of your site in Soumission

Frequently Asked Questions on the Overall Construction Budget and CFC 5 (FAQ)

1. What do CFC 0 to 9 of the Building Cost Code cover?

The CRB's CFC classifies the costs of a project: CFC 0 land, CFC 1 preparatory works, CFC 2 building, CFC 3 operating equipment, CFC 4 outdoor works, CFC 5 secondary costs (permits and fees, samples and models, insurance, financing, reserves) and CFC 9 furnishing and decoration. In the tool's example, the CFC 2 of 950'000 CHF weighs 80.9 % of the budget excluding land, within the range of 75 % to 82 % in the specification.

The contingency reserve is classed by the CRB under CFC 58 (secondary costs); the tool's specification files it under "CFC 9". The tool calls it a reserve and counts it with the ancillary costs.

2. What are the hidden costs of CFC 5 that make a budget slip?

In the example (CFC 2 of 950'000 CHF), CFC 5 reaches 76'394 CHF: permits and fees 47'175 CHF (permit 7'600, connections 33'250, civil-defence shelter PC 6'325), models and copies 2'850 CHF, client's insurance 4'275 CHF and financing 22'094 CHF. With the reserve of 47'500 CHF, the ancillary costs represent 13.0 % of CFC 2.

These percentages (0.8 %, 3.5 %, 0.3 %, 0.45 %) and the shelter fee of 1'150 CHF per room are values from the specification: permit fees, connection fees and the shelter replacement contribution depend on the municipality and the canton.

3. How is the interim interest on the construction loan calculated?

During the works, the loan is drawn down as payments are made: the tool uses an average drawdown of 50 % of the capital of the works (CFC 1, 2 and 4) over the duration of the works. Interest = capital × average drawdown × rate × duration / 12. With 1'050'000 CHF, 2.75 % and 14 months: 16'843.75 CHF, to which 5'250 CHF of bank commissions are added (0.5 %), that is 22'093.75 CHF of CFC 54.

Land financing and the interest for the period before the works are not included. For a long project or a rapid drawdown (large advance payments at the start), increase the average drawdown.

Indicative information based on the CRB Building Cost Code; it does not replace a budget drawn up by a professional or the fee schedules of your municipality.

📥 Ready-to-use pack · free

Download the document

The file is displayed on screen right away and we also send it to you by e-mail.

Your address is used to send you this file. See our privacy policy.