SIA 118 / OTConst Tool 6.01 Online

Site Set-Up, Logistics & SUVA Safety Calculator (Chapter 01)

Calculator for site set-up, fences, cranes & sheet-metal workers' bridges.

Interactive tool

Editable example prices. The specifications provide no unit price and ACIP chapter 01 is not available: the tool's rates are examples to be replaced with your own prices (“Unit prices” section). The sanitary ratios are those of the specifications, not verified.

A The site

months
workers
m
CHF
Unit prices (editable examples)
Unit prices of site facilities in three items
Line item1. Set-up (CHF per unit)2. Operation (CHF per unit per month)3. Dismantling (CHF per unit)
Heras-type fencing (per m)
Site accommodation container (per container)
Chemical or connected WC (per WC)
Site electrical board (lump sum)
Lifting (none)Follows the lifting equipment chosen in point 5 (crane, transport and erection).

Sanitary provision and welfare facilities

Chemical or connected WCs
Heated and lit changing room and canteen
Drinking water and hand basins

The ratios of WCs and floor area per person are those of the specifications. Sanitary facilities fall under Ordinance 3 to the Labour Act (OLT 3, art. 29 to 33), not under the OTConst: check the figures in the ordinance.

Analytical pricing in 3 items (CAN 113 structure)

Costing of site facilities in set-up, operation and removal
Line item1. Set-up2. Operation3. Dismantling
Total site installations

    Electrical cabinet: sockets up to 32 A for mobile appliances are protected by a residual-current device (DDR) of 30 mA at most (art. 31 para. 2 OTConst). The benchmark of 4% to 8% of the structural work is that of the specifications.

    Embed this calculator on a website page

    Paste this code into the page, or write [outil code="6.01"] in the content of a page on the site.

    📄 Files and templates linked to this tool (free)

    Move from calculation to full management

    Keep your references at hand, then automate them in your quotes, bids and final statements.

    ⚡ Automate this calculation in our ERP / Soumission software (Trial)

    Technical reference guide

    How to cost the "Site facilities" item (CAN 113 / ACIP Chapter 01) without losing your margin

    Site facilities group everything that makes the site possible without being part of the works: fences, site accommodation, WCs, connections, lifting equipment. The costing site facilities CAN 113 CFC 211 is done item by item, never in one go, because each line behaves differently over time: some are paid once (the erection), others every month (the hire), others at the end (the dismantling). On the tool's example site (building of 8 months, 8 workers, 80 m of fencing, structural work of CHF 450'000), the facilities reach CHF 20'280 excl. VAT (HT) without a crane and CHF 77'280 excl. VAT (HT) with a quick-erect crane.

    Note on the text of the standard. The title of the specifications cites CFC 211.1; in the hub's register, CFC 211.1 designates façade scaffolding, whereas general site facilities fall under CFC 113 and 211.0 (ACIP chapter 01). The text of CAN 113 was not consulted and ACIP chapter 01 is not available: the tool's unit prices are examples, which you replace with your own prices.

    The mandatory split into 3 items: Set-up (lump sum), Operation (per month) and Removal

    The CAN 113 structure used by the tool distinguishes the set-up (outward erection, transport, lump sum), the operation (hire and consumption, multiplied by the number of months) and the removal (dismantling, clearing away, making good). Mixing the three loses money as soon as the site lasts longer than planned: only the operation item rises with duration. Costing of the example, without lifting equipment:

    Costing of the example in three items, without lifting equipment
    Line item1. Set-up2. Operation (8 months)3. Dismantling
    Heras-type site fencing960.00 CHF2'560.00 CHF480.00 CHF
    Accommodation: changing-room and canteen containers1'200.00 CHF7'200.00 CHF800.00 CHF
    Chemical or connected WCs80.00 CHF1'440.00 CHF60.00 CHF
    Site electrical cabinet with DDR 30 mA, water and electricity consumed800.00 CHF4'400.00 CHF300.00 CHF
    Total3'040.00 CHF15'600.00 CHF1'640.00 CHF

    Example unit prices of the tool, editable: they come neither from the specifications nor from a standard.

    Why a site delay not attributable to the company entitles it to paid extension of the facilities (SIA 118)

    Each month of delay costs the company the operation item: with the example rates, one more month of quick-erect crane and site accommodation adds CHF 6'450 excl. VAT (HT). The SIA 118 standard protects the company when the delay is not attributable to it: the time limit is extended, provided the delay is notified immediately and in writing to the site management (art. 96). Acceleration measures ordered by the client are at the client's expense (art. 95 para. 3) and extraordinary circumstances give a right to payment of the additional expenses (art. 59).

    Note on the text of the standard. The title of the specifications speaks of "paid extension of the facilities". According to the SIA 118 commentaries consulted, art. 96 grants an extension of the time limit without a delay penalty, but does not by itself guarantee payment of the additional operating months: that depends on the cause of the delay (art. 59 for extraordinary circumstances, art. 95 para. 3 for acceleration) and on the contract (firm price, art. 38). Title kept as it is; notify the delay in writing, then cost the extra months.

    SUVA and OTConst legal obligations for site accommodation: heated changing rooms, canteen, WCs and DDR 30 mA cabinet

    The site facilities standard SUVA SIA 118 does not exist as a single text: the safety of the installation falls under the Construction Work Ordinance (OTConst) and the Suva guidelines, while the contract and the price fall under SIA 118. The tool's specifications set four requirements for site accommodation:

    • WC obligation heated changing room site OTConst: at least 1 WC for 15 workers (1 for 10 in comfort), less than 100 m from the workstations;
    • a heated and lit changing room and canteen of 1.5 to 2.0 m² per worker present, i.e. 12 to 16 m² for 8 workers (2 containers of 15 m²);
    • drinking water and a hand basin close to the WCs and the canteen;
    • a site electrical board DDR 30 mA: sockets up to 32 A for mobile appliances are protected by a residual-current device of 30 mA at most (art. 31 para. 2 OTConst).

    Note on the text of the standard. The specifications attach the WCs and the rooms to the OTConst. According to the texts consulted, sanitary facilities and welfare rooms fall under Ordinance 3 to the Labour Act (OLT 3, art. 29 to 33) and under art. 6 of the Labour Act; only the 30 mA residual-current device is verified in the OTConst. The numerical ratios (1 WC for 10 to 15 workers, 1.5 to 2.0 m² per person) are those of the specifications and were not found in the ordinance: check them with the cantonal labour inspectorate. For the site's other safety measures, see the OTConst safety plan generator.

    Average ratio of site facility cost in Switzerland (4% to 8% of the structural work depending on the crane and access)

    The percentage site facilities on structural work serves as a plausibility check: the usual benchmark in the specifications is 4% to 8% of the structural work package. A crane kept for the whole site, difficult access or an occupied site push the ratio up; a villa without lifting equipment keeps it low. On the example (structural work of CHF 450'000, 8 months):

    Ratio of site facilities to structural work depending on the lifting equipment
    ScenarioInstallations excl. TVA (HT)Share of the structural workReading
    Without lifting equipment20'280 CHF4,5 %Within the benchmark
    Quick-erecting crane GMR77'280 CHF17,2 %Above the benchmark
    Tower crane GME136'280 CHF30,3 %Above the benchmark

    A ratio outside the benchmark is not an error: it signals a particular site, to be justified. For sites in town, add the public-space occupation fees with the public-space occupation tariff calculator. ⚡ Price your site setups in Soumission

    The benchmark of 4% to 8% is that of the specifications; it has not been checked in a publication. The tool's example prices are not market rates.

    Frequently Asked Questions about Site Facilities, Site Accommodation and the Crane (FAQ)

    1. What does the "site facilities" lump sum include in an offer under SIA 118?

    The lump sum groups the resources common to the whole site that are not attached to any specific work: fences, site accommodation (changing rooms, canteen, WCs), electrical cabinet with water and electricity consumed, lifting equipment with its transport and erection. The tool breaks it down into three items, like the CAN 113 structure: set-up (outward erection), operation (hire and consumption × number of months) and removal (dismantling and making good). With the default values (building, 8 months, 8 workers, 80 m of fencing, no crane), it gets CHF 20'280 excl. VAT (HT), i.e. 4.5% of structural work of CHF 450'000, within the benchmark of 4 to 8%.

    The tool's unit prices are editable examples: ACIP chapter 01 is not available and the specifications provide none. On a firm price (art. 38 SIA 118), the lump sum does not move, except for an extension of the time limit not attributable to the company (art. 96) or extraordinary circumstances (art. 59); replace the examples with your prices.

    2. What are the obligations for the WCs and the rest room on a site?

    Sanitary facilities and welfare rooms are not in the OTConst: they fall under Ordinance 3 to the Labour Act (OLT 3, art. 29 to 33: changing rooms, toilets, canteens) and under art. 6 of the Labour Act. The tool's figures are those of the specifications, not checked in the ordinance: at least 1 WC for 15 workers (1 for 10 in comfort), less than 100 m from the workstations, and 1.5 to 2.0 m² of heated and lit changing room and canteen per person. For 8 workers: at least 1 WC, 12 to 16 m², i.e. 2 containers of 15 m².

    On the OTConst side, sockets up to 32 A for mobile appliances are protected by a residual-current device of 30 mA at most (art. 31 para. 2). Check the exact requirements in OLT 3 and with the cantonal labour inspectorate.

    3. How to invoice the extra months of crane?

    The "operation" item is invoiced monthly: one more month therefore costs the monthly hire of the crane and the site accommodation. With the tool's example rates, going from 8 to 9 months with a quick-erect crane adds CHF 6'450 excl. VAT (HT) to the whole of the facilities, of which CHF 4'500 for the crane. The total goes from CHF 77'280 to CHF 83'730 excl. VAT (HT).

    The right to be paid for these months is not automatic. Under SIA 118, a delay not attributable to the company gives a right to an extension of the time limit (art. 96) provided it is notified immediately and in writing to the site management; payment of additional expenses is provided for extraordinary circumstances (art. 59), and acceleration measures ordered by the client are at the client's expense (art. 95 para. 3). Notify the delay in writing, then cost the extra months.

    Indicative information prepared from the tool's specifications, the OTConst and SIA 118; it replaces neither reading the texts nor the advice of the site management.