NPK Concrete Selector (SN EN 206), B500B Reinforcement Calculator & SIA 414 Tolerances
Concrete class selector (XC/XD/XF), steel ratios kg/m³ & tolerances.
Interactive tool
Official table of concrete types. The selector applies the table of concrete types from standard SN EN 206 (NPK annex of the CRB), which differs from the tool's specifications for types A, B and C: the official text prevails. The nominal covers are those of the specifications, not verified in SIA 262. The SIA 414/2 tolerance scale in part C is the one you supplied: it has not been verified in the standard (paid, not consulted) and remains editable.
A NPK concrete type selector (SN EN 206 / SIA 262)
NPK concrete type, exposure class and cover
- Nominal cover cnom of the reinforcement
B Concrete volume, formwork and tonnage of B500B steel
3 Entering the dimensions
5 Cross-section of the column or beam
cm × cmConcrete, steel and formwork
- Theoretical concrete volume
- Concrete volume to order
- Weight of B500B steel to fabricate
- Formwork area
Steel = volume × quantity (in kg/m³). Formwork: slab = area (soffit); shear wall = 2 × the developed area (two faces); raft foundation = edge formwork of a square raft (4 × √area × thickness); column or beam = perimeter of the section × length. Estimate by element: the formwork take-off depends on the real geometry.
C Dimensional tolerance checker (SIA 414/2)
10 Requirement
Tolerance verdict
Table supplied by the user (not verified in SIA 414/2): rough flatness under a 1, 2, 4 or 10 m straightedge, finished flatness under a 1, 2 or 4 m straightedge, verticality up to 3 or 6 m in height, in normal or enhanced requirement. For another case (dimensional deviation, height over 6 m), enter the tolerance of your contract or of the standard.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.06"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
Understanding the Swiss concrete types NPK A, B, C, D, E, F and G (SN EN 206 and SIA 262 standards)
In Switzerland, concrete is ordered by NPK type, which groups the strength class, the exposure classes, the maximum aggregate diameter, the chloride content and the consistence. The exposure class Swiss concrete XC4 XF4 NPK A B C is chosen according to the environment of the structure: dry interior (XC1), moderate humidity (XC3), carbonation by wet / dry cycling (XC4), frost (XF1 to XF4), chlorides (XD1 to XD3). Table of the concrete types of SN EN 206 (maximum aggregate diameter 32 mm, chloride content class Cl 0.10, consistence C3):
| Type | Strength | Exposure classes | W/C max. | Cement min. (kg/m³) | Use |
|---|---|---|---|---|---|
| Type 0 | C12/15 | X0 | — | — | Unreinforced concrete (blinding) |
| Type A | C20/25 | XC1, XC2 | 0,65 | 280 | Building construction: interior or buried concrete, wet rarely dry |
| Type B | C25/30 | XC3 | 0,60 | 280 | Building construction: exterior concrete sheltered from rain, damp room |
| Type C | C30/37 | XC4, XF1 | 0,50 | 300 | Building construction: exterior concrete exposed to weather, frost without salt |
| Type D (T1) | C25/30 | XC4, XD1, XF2, XF3, XD2a | 0,50 | 300 | Civil engineering: atmospheric chlorides (XD1), frost with de-icing salt at moderate saturation (XF2) or frost without salt at high saturation (XF3) |
| Type E (T2) | C25/30 | XC4, XD1, XF4, XD2a | 0,50 | 300 | Civil engineering: chlorides (XD1), frost with de-icing salt at high saturation (XF4) |
| Type F (T3) | C30/37 | XC4, XD3, XF2, XD2b | 0,45 | 320 | Civil engineering: wet / dry cycling with chlorides (XD3), frost with salt at moderate saturation (XF2) |
| Type G (T4) | C30/37 | XC4, XD3, XF4, XD2b | 0,45 | 320 | Civil engineering: chlorides (XD3) and frost with salt at high saturation (XF4) |
To choose the type for an ordinary structure, the tool's selector proposes:
| Work | Type | Cover cnom |
|---|---|---|
| Unreinforced blinding concrete under a raft foundation (5–10 cm) | Type 0 (C12/15, X0) | Not applicable (unreinforced) |
| Interior slabs, walls and columns in dry conditions | Type A (C20/25, XC1, XC2) | c_nom = 25 mm |
| Buried basement walls, foundations and raft foundations (against soil) | Type A (C20/25, XC1, XC2) or Type C (C30/37, XC4, XF1) | c_nom = 35 mm (40 to 50 mm if cast directly against soil) |
| Exterior elements sheltered from rain (open shed, damp room) | Type B (C25/30, XC3) | c_nom = 35 mm |
| Exterior facades exposed to frost, balconies, parapets (without de-icing salt) | Type C (C30/37, XC4, XF1) | c_nom = 35 to 40 mm |
| Road retaining walls, garage ramps and elements exposed to salt spray | Type D (T1) (C25/30, XC4, XD1, XF2, XF3, XD2a) or Type E (T2) (C25/30, XC4, XD1, XF4, XD2a) | c_nom = 45 mm |
| Underground car park slabs, garage raft foundations (salts carried by tyres in winter) | Type F (T3) (C30/37, XC4, XD3, XF2, XD2b) or Type G (T4) (C30/37, XC4, XD3, XF4, XD2b) | c_nom = 50 to 55 mm (surface protection OS8 or OS11 recommended) |
Note on the text of the standard. The table of concrete types above is the official table of SN EN 206 + A2:2021 (NPK annex of the CRB, read in the Holcim brochure of 2023). It differs from the tool's specification: type A is a C20/25 (not a C25/30), type B a C25/30 in class XC3 (not XC4-XF1), type C covers XC4 and XF1 (not XF3), types D and E are C25/30 (not C30/37) and types F and G C30/37 (not "C30/37 or C35/45"). The official text prevails. Consequence for buried walls, which the specification assigns to type B: a wall against soil is in class XC2 (wet, rarely dry), therefore type A, and type C if it is exposed to frost. The nominal covers of the specification were not verified in SIA 262, whose table was not consulted.
Why an underground car park slab requires XD3 concrete (NPK F/G) and a 50 mm cover
In winter, cars carry salt water on their tyres: the car park concrete undergoes wetting and drying cycles laden with chlorides, and chlorides that reach the reinforcement make it rust. This is exposure class XD3, which requires types F or G: a water/cement ratio of 0.45 at most, at least 320 kg of cement per m³ and a C30/37 concrete. The specification adds a nominal reinforcement cover of 50 to 55 mm, i.e. clearly more than the 25 mm of an interior slab in a dry environment: the SIA 262 standard reinforcement cover concrete sets the thickness of concrete that protects the steel according to exposure. It also recommends a surface protection of type OS8 or OS11.
Note on the text of the standard. The covers of 25, 35, 40, 45 and 50 to 55 mm and the OS8 / OS11 surface protection are those of the specification; SIA 262 was not consulted. The engineer's design sets the cover of each element. For the other structural requirements (snow, fire), see the fire protection and snow load calculator.
B500B reinforcement quantity per m3 of concrete in Switzerland: average values for a raft foundation, a slab, a shear wall and a seismic zone
The steel quantity reinforced concrete kg/m3 slab raft wall serves to estimate the reinforcement tonnage before the reinforcement drawing exists. The tool's specification gives three levels, which apply to a raft foundation, a slab or a shear wall according to the stresses:
| Reinforcement level | Ratio | Steel for 28.8 m³ (120 m² × 24 cm) |
|---|---|---|
| Low: 75 kg/m³ | 75 kg/m³ | 2,16 t |
| Standard: 100 to 115 kg/m³ | 100 to 115 kg/m³ | 2,88 to 3,31 t |
| Seismic zone Z3 / heavily stressed: 140–160 kg/m³ | 140 to 160 kg/m³ | 4,03 to 4,61 t |
With 3% loss in pumping and casting, the example slab requires 29.7 m³ of concrete and 120 m² of formwork (soffit). The formwork of a raft foundation, a shear wall or a column is calculated differently: see the tool's notes. ⚡ Price your structural work in Soumission
Note on the text of the standard. The specification gives no quantity per element (raft foundation, slab, shear wall): only three levels (75, 100–115 and 140–160 kg/m³), which the user chooses. These values are unverified preliminary-design averages: the engineer's reinforcement drawing gives the exact tonnage. B500B steel is the reinforcement grade stated in the specification.
SIA 414/2 standard: what flatness and verticality tolerances are permitted for structural concrete work and masonry?
The dimensional tolerances masonry concrete SIA 414 standard set the deviations permitted between the work as built and the drawing: on a dimension, on the verticality of a wall or column, and on the flatness deflection measured under a straightedge, in normal or enhanced requirement. The tool's checker (part C) compares the deviation measured on site with the tolerance in the built-in table and indicates the margin or the excess. The exposed concrete surface category SIA 118/262 is another subject: it concerns the appearance of the face and is agreed in the contract, in addition to the geometric tolerances. Built-in table (maximum deflection in mm, measured under the straightedge):
| Case | Straightedge or height | Normal requirement | Increased requirement |
|---|---|---|---|
| Raw flatness | under the 1,0 m straightedge | 5 mm | 3 mm |
| Raw flatness | under the 2,0 m straightedge | 8 mm | 5 mm |
| Raw flatness | under the 4,0 m straightedge | 12 mm | 8 mm |
| Raw flatness | under the 10,0 m straightedge | 20 mm | 15 mm |
| Finished flatness | under the 1,0 m straightedge | 3 mm | 2 mm |
| Finished flatness | under the 2,0 m straightedge | 5 mm | 3 mm |
| Finished flatness | under the 4,0 m straightedge | 8 mm | 5 mm |
| Plumb of a wall or column | up to h = 3,0 m | ± 8 mm | ± 5 mm |
| Plumb of a wall or column | up to h = 6,0 m | ± 12 mm | ± 8 mm |
Note on the text of the standard. This table was supplied by the user of the tool (step 7B): it was not verified in SIA 414/2 (2016, which replaces V414/10), a paid standard that was not consulted. It does not cover dimensional deviation or verticality above 6 m: the tool then asks for the tolerance to be entered. "Rough flatness" designates rough slabs, rough screeds and unplastered walls; "finished flatness" plastered walls, smooth exposed concrete and finished screeds. The same applies to the content of SIA 118/262 on exposed-concrete surface categories, which are not covered.
Frequently asked questions on reinforced concrete, NPK types and tolerances (FAQ)
1. What is the difference between NPK concrete A, B and C?
According to the official table of concrete types (SN EN 206, NPK annex of the CRB), type A is a C20/25 concrete for exposure classes XC1 and XC2 (interior, dry or wet rarely dry), type B a C25/30 for XC3 (moderate humidity, exterior sheltered from rain) and type C a C30/37 for XC4 and XF1 (exterior exposed to weather and frost without salt). The maximum water/cement ratio falls from 0.65 to 0.60 then 0.50 and the minimum cement content rises from 280 to 300 kg/m³. The maximum aggregate diameter is 32 mm, the chloride content Cl 0.10, the consistence C3.
The tool's specification describes these types slightly differently (A in C25/30, B in XC4-XF1): the official table applies. The cement content requirements are to be checked in the standard and in the project specification.
2. How many kg of steel per m³ of reinforced concrete?
The specification quantities are 75 kg/m³ for a lightly reinforced element, 100–115 kg/m³ for a standard case (slab, raft foundation, shear wall) and 140–160 kg/m³ in seismic zone Z3 or for a heavily stressed element. For a 120 m² slab of 24 cm (28.8 m³), the standard quantity gives 2.88 to 3.31 tonnes of B500B steel, and 29.7 m³ of concrete are to be ordered with 3% loss.
These are preliminary-design averages: only the engineer's reinforcement drawing gives the exact tonnage.
3. What flatness tolerance for a rough concrete slab according to SIA 414?
The SIA 414/2 standard (dimensional tolerances in construction, which replaces V414/10 of 2016) sets permitted deviations for dimensions, verticality and flatness, in normal or enhanced requirement. The tool integrates the table you supplied, not verified in the standard (paid, not consulted). For rough flatness (rough slabs, rough screeds, unplastered walls), the maximum deflection under the straightedge is 8 mm (normal) or 5 mm (enhanced) under a 2.00 m straightedge, and 12 mm or 8 mm under 4.00 m; for finished flatness, 5 mm or 3 mm under 2.00 m.
The checker compares the measured deviation with this tolerance and indicates the margin or the excess. For a case outside the table (dimensional deviation, verticality above 6 m), enter the tolerance of your contract or of the standard.
Indicative information prepared on the basis of the SN EN 206 concrete types table and the tool's specification; it replaces neither the SIA 262 and SIA 414/2 standards nor the engineer's design.