1. Summary tables of flatness tolerances under the 2-metre straightedge (SIA Standards 414, 242, 248 and 251)
The memo fits on one page and brings together the reference values to check before laying: flatness, finished level, residual moisture. Always confirm with the standard in force and the technical data sheet of the product.
1.1 What the tiler, the parquet layer and the painter are entitled to demand from the mason and the screed layer before laying
The trade that lays must be able to rely on a compliant substrate. The SIA 414/2 scale that we use gives, for a finished surface, a normal flatness of 3 mm under the 1 m straightedge, 5 mm under 2 m and 8 mm under 4 m (increased: 2, 3 and 5 mm). Beyond that, the substrate must be reworked before laying, or the deviation reserved in writing.
1.2 Maximum residual moisture limits CM (carbide bomb) in a cement screed (2.0% / 1.5%) and anhydrite screed (0.5% / 0.3%)
For a cement screed, the usual values are 2.0% for tiling (1.8% if the screed is heated) and 1.8% for parquet and resilient floors (1.5% if heated); for an anhydrite screed, 0.5% (0.3% if heated). These benchmarks are taken from the SIA 251 standard and from our fact sheets: read the manufacturer's data sheet before laying.
2. Visual inspection of painted surfaces (SIA 257) and glazing (SIGaB 006 Guideline): the viewing rules
A surface is judged under normal viewing conditions, not with a magnifying glass. This is the rule that protects the painter and the glazier alike.
2.1 Why inspection with a floodlight in raking light at 20 cm from the wall is formally excluded (unless a Q4 finish was ordered and paid for in the quote)
Appearance defects in paintwork are checked with the naked eye, in diffuse light, from a normal distance; raking light from a few centimetres reveals irregularities that no one sees in use. It is justified only if a more expensive Q4 finish was ordered and paid for.
2.2 Regulatory viewing distances with the naked eye (1 m to 3 m under diffuse daylight)
The inspection distances range from 1 to 3 metres depending on the surface and the applicable standard, under diffuse daylight. Note them in the acceptance report (PV): they prevent a scratch invisible at two metres from blocking a payment.
3. Frequently asked questions about construction tolerances in Switzerland (FAQ)
3.1 What is the difference between plaster quality levels Q2 (standard) and Q3/Q4 in the SIA 242 standard?
Q2 is the normal level when nothing else is ordered. Q3 corresponds to a careful smoothing, Q4 to a complete skim coat of the surface, designed to withstand raking light. The higher the level, the higher the price: the architect must specify it in the bill of quantities.
3.2 What should you do if the substrate delivered by the previous trade exceeds the SIA flatness tolerances?
Measure, photograph with the straightedge, then send a letter of reservation to the site management before laying (duty to notify, Art. 25 SIA 118 and Art. 365 para. 3 CO), with a quotation for restoring the level. Our file on duty-to-notify letters provides the template.
3.3 From what minimum distance is a scratch on triple glazing judged under the Swiss SIGaB guideline?
The SIGaB guidelines provide for a visual inspection at a standardised distance and under standardised lighting, without a magnifying glass or raking light. The exact distance depends on the guideline in force: check it in the SIGaB text before disputing a glazing unit.
Keywords covered: flatness tolerance wall screed standard SIA 414 pdf · paint tolerance SIA 257 raking light · moisture content anhydrite cement screed before laying tiles parquet · SIGaB 006 guideline visual inspection glazing distance · plastering finish levels Q1 Q2 Q3 Q4 SIA 242 · permissible deflection under 2-metre straightedge.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.