Dry Partition Calculator (Boards, CW/UW Profiles) & Q1 to Q4 Qualities (SIA 242)
Calculator for board/track quantities, finish levels Q1–Q4 & measurement rules.
Interactive tool
Ratios from the specifications, SIA 242 not consulted. Material ratios (0,80 ml/m² of UW tracks, 2,0 ml/m² of CW studs, 7 % waste, filler of 0,3 / 0,5 / 1,1 / 2,2 kg/m² according to Q1 to Q4) and non-deduction threshold for openings (0,50 to 2,50 m²): specifications, not verified. Assumptions of the tool: joint tape of 1,3 ml per m² of board, 15 screws per m² of board, CW studs proportional to 62,5 / spacing, non-deduction threshold of 0,50 m² by default (editable). The Q1 to Q4 scale comes from a German plaster-industry leaflet; the CRB's NPK 671 adopts Q2 as the standard quality.
A Dry-lining materials and finish quality Q1 to Q4
Quantities to order (with 7 % waste)
- Gross and net wall area
- Wall thickness
- Plasterboard
- Horizontal UW tracks
- Vertical CW studs
- Acoustic mineral wool
- Joint tape and resilient strip
- Phosphated screws
- Joint and skim-coat filler
Boards of 2,00 × 1,25 m (2,50 m²). UW tracks: 0,80 lm/m²; CW studs: 2,0 lm/m² at 62,5 cm centres. The jointing compound is counted on the visible faces. Measurement rule SIA 118 / 242 (CAN 642 / 341): the non-deduction threshold in the specifications is not verified.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.22"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
Standard SIA 242 and ASIPG guideline: understanding the 4 surface quality levels (Q1, Q2, Q3 and Q4)
The finish quality Q1 Q2 Q3 Q4 plasterwork and painting standard SIA 242 describes the care given to the surface of a plasterboard wall before painting or wallpapering. Standard SIA 242 «Plasterwork, rendering, dry construction» sets the tolerances; the higher the level, the more compound and work are needed:
| Level | Use | Joint and skim-coat filler |
|---|---|---|
| Q1: basic finish | Surface intended for a thick covering or tiling: joints and screws covered, with no requirement for appearance. | approx. 0,3 kg/m² |
| Q2: standard | Standard quality, with matt paint or coarse-textured wallpaper. | approx. 0,5 kg/m² |
| Q3: careful smoothing | Careful smoothing of the joints and the surface, for fine paint or smooth wallpaper. | approx. 1,1 kg/m² |
| Q4: full skim coat, raking light | Complete skim coat of the surface, for raking light or a glossy finish. | approx. 2,2 kg/m² |
Note on the text of the standard. SIA 242 (paid) was not consulted, and its tolerances are not reproduced. The title of this section cites an «ASIPG guideline» that I could not find: the Q1 to Q4 scale is that of information sheet 2 of the Bundesverband der Gipsindustrie (Germany), and the CRB catalogue (NPK 671, Plasterwork) refers to SIA 242 for the tolerances. The uses in the table come from plaster industry guides, and the compound consumptions (0,3 / 0,5 / 1,1 / 2,2 kg/m²) are those of the specifications.
Why level Q2 is the default standard (if nothing is stated in the quote) and when to require Q3 or Q4 (raking light)
The CRB catalogue (NPK 671) takes Q2 as the standard quality and Q4 as the highest level: if the quote states nothing, Q2 applies. A wall lit by raking light (large window, raking lighting in a corridor) reveals the slightest joint defect: the full skim coat Q3 Q4 under raking light is then necessary, as it is for gloss paint or smooth wallpaper. Level Q4 consumes about 2,2 kg of compound per m², against 0,5 kg in Q2: for a wall of 27,4 m² net on two faces, 121 kg against 27 kg, not counting the extra labour.
Material ratios per m2 of drywall partition in Switzerland (12,5 mm boards, CW/UW 75 profiles, mineral wool, screws and compound)
The calculation of quantities of plasterboard, UW tracks and CW studs per m2 is based on ratios per square metre of wall, increased by 7 % waste. For 1 m² of partition (two faces) in single layer, then in double layer:
| Material | Single skin | Double skin |
|---|---|---|
| 12,5 mm plasterboard | 2,14 m² | 4,28 m² |
| Horizontal UW tracks | 0,90 ml | 0,90 ml |
| Vertical CW studs (62,5 cm spacing) | 2,10 ml | 2,10 ml |
| Mineral wool in the frame | 1,07 m² | 1,07 m² |
| Joint tape | 2,80 ml | 2,80 ml |
| Phosphated screws | 32 | 64 |
| Filler in Q2 | 1,00 kg | 1,00 kg |
| Wall thickness (75 mm sections) | 100,0 mm | 125,0 mm |
The acoustic double-layer drywall partition EI30 doubles the boards on each side to improve sound insulation and fire resistance. The class EI30 to EI60 depends, however, on the complete tested system (boards, profiles, wool, fixings): it appears in the manufacturer's test report, not in the number of boards alone. For the fire protection of buildings, see the fire resistance tool AEAI (VKF).
Note on the values. The ratios of 0,80 lm/m² of UW tracks and 2,0 lm/m² of CW studs (at 62,5 cm centres), the 7 % waste and the board of 2,00 × 1,25 m are those of the specifications, not verified. Assumptions of the tool (the specifications give none): CW studs proportional to 62,5 / centres for centres of 41,7 and 50 cm; joint tape of 1,3 lm per m² of board (perimeter of a board divided by 2 and by its area); 15 screws per m² of board. For a suspended ceiling, the tool applies the same ratios to the perimeter profiles and the CD 60/27 profiles, for lack of a value in the specifications.
Measurement rules SIA 118 / CAN in plasterwork: deduction of doors and windows and charging of corner profiles
The deduction of openings in plasterwork measurement SIA 118/242 follows a measurement rule: openings below a threshold are not deducted from the area, to compensate for the work on reveals and lintels. The specifications cite a typical threshold of 0,50 to 2,50 m² depending on the CAN item (CAN 642 / 341). For a partition of 12 m by 2,60 m with 2 doors of 0,90 × 2,10 m (1,89 m² each):
| Threshold | Doors deducted? | Deducted area | Net area |
|---|---|---|---|
| 0,50 m² (default value) | yes, 1,89 m² exceeds the threshold | 3,78 m² | 27,42 m² |
| 2,50 m² | no, 1,89 m² stays below the threshold | 0,00 m² | 31,20 m² |
Corner profiles (angle beads) and other accessories are charged separately according to the CAN items; the specifications give no numerical rule for them, and the tool does not count them. To compare the measurement and liability rules of standard SIA 118 with the Code of Obligations, see the SIA 118 and CO comparator.
Note on the text of the standard. The non-deduction threshold (0,50 m² by default, editable) and the exact rule of SIA 118 and SIA 242, as well as the CAN 642 and 341 items cited by the specifications, were not verified: the quote states the applicable measurement rule. ⚡ Price your partitions in Soumission
Frequently Asked Questions about Drywall Partitions, Q1 to Q4 Qualities and Measurement (FAQ)
1. What do the surface quality levels Q1, Q2, Q3 and Q4 mean in plasterwork?
Q1 is the basic finish (joints and screws covered, no requirement for appearance, for example under tiling), Q2 the standard quality, Q3 a careful smoothing and Q4 the complete skim coat of the surface, for raking light. The jointing and skimming compound increases with the level: about 0,3 kg/m² in Q1, 0,5 in Q2, 1,1 in Q3 and 2,2 in Q4 (skim coat of 1 to 2 mm). Level Q2 is the standard quality of the CRB's NPK 671, and Q4 the highest; if the quote states nothing, Q2 applies.
The tolerances of each level are in standard SIA 242 (paid, not consulted). The Q1 to Q4 scale is that of information sheet 2 of the Bundesverband der Gipsindustrie (Germany): the «ASIPG guideline» cited by the specifications could not be found.
2. How many boards, profiles and screws for a partition 12 m long and 2,60 m high?
With 2 doors of 0,90 × 2,10 m deducted, the net area is 27,42 m². For a single-layer partition on two faces, with 7 % waste: 58,68 m² of 12,5 mm boards, i.e. 24 boards of 2,00 × 1,25 m; 23,5 lm of UW tracks and 58,7 lm of CW studs at 62,5 cm centres; 29,34 m² of mineral wool; 76,3 lm of joint tape; 1 box of 1'000 screws; 27,4 kg of compound in Q2. In double layer, the board area rises to 117,36 m².
The ratios (0,80 lm/m² of UW tracks, 2,0 lm/m² of CW studs, 7 % waste) are those of the specifications. The joint tape (1,3 lm per m² of board), the 15 screws per m² and the adaptation of the studs to centres of 41,7 and 50 cm are assumptions of the tool.
3. Should doors and windows be deducted in plasterwork measurement?
Openings below a threshold are not deducted, to compensate for the work on reveals and lintels. The specifications cite a typical threshold of 0,50 to 2,50 m² depending on the CAN item. With the threshold of 0,50 m² adopted by default, the two doors of 1,89 m² are deducted (3,78 m², net area of 27,42 m²); with a threshold of 2,50 m², they are not and the net area stays at 31,20 m².
The exact rule, according to SIA 118 and SIA 242 and the CAN 642 and 341 items cited by the specifications, was not verified: the threshold is editable in the tool and the quote states the applicable measurement rule.
Indicative information prepared from the tool's specifications; it replaces neither standard SIA 242, nor SIA 118, nor the data sheets of the board manufacturer.