Calculator for Soil Bulking, Truck Trips & Excavation Slopes
Calculator for soil bulking, truck tonnages & slopes/shoring from 1.5 m.
Interactive tool
Quantities are paid in place. The in-place volume is the billable volume according to SIA 118 and CAN 211 (specification reminder); the bulked volume is only used to size the trucks and the tip. Densities, bulking and compaction factors are editable.
A The excavation and the ground
1 Excavation input
B Trucks, excavator and slope
Volumes, trucks and slope
- Billable volume in place (SIA 118 / CAN 211)
- Bulked volume to be hauled
- Total mass to be removed
- Exact number of trips
- Trucks in continuous rotation
- Excavator loading time
- Volume to be returned as compacted backfill
- Footprint of the slope overwidth
Formulas: bulked volume = volume in place × bulking; mass = volume in place × density; trips = the greater of mass / payload and bulked volume / body volume, rounded up to the next whole number; trucks = cycle / loading time of one truck. Payloads, densities and bulking factors: specification values.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.03"] in the content of a page on the site.
📄 Files and templates linked to this tool (free)
- PDFDOCX ⚖️ Pure Law Geotechnical Reserve & Excavation Contingencies Pack Complete 5-page guide (PDF) and Word template. Rock, water, polluted materials, obstacles: who bears the ground risk, reservation clauses, immediate notice, written confirmation and three letters. See the file, its mini-tool and the pack →
- XLSXPDF Geotechnical Table: Soil Bulking, Tonnages & Truck Cycles From volume in place to tonnage and the number of trucks. See the file, its mini-tool and the pack →
- PDFDOCX Excavation Safety Protocol & Underground Network Plans (SIA 405) The checklist for opening an excavation near buried utility lines. See the file, its mini-tool and the pack →
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
Reference table of soil bulking factors and densities in Switzerland (Topsoil, Gravel, Molasse, Rock)
An excavated soil takes up more volume than in place: this is bulking. The bulking factor soil gravel earthworks Switzerland varies from 1.18 for natural gravel to 1.55 for blasted rock, and the density topsoil gravel rock t/m3 from 1.45 to 2.50 t/m³. Reference values of the tool, all editable in the calculator:
| Ground type | In-situ density (t/m³) | Bulking | Compaction | 350 m³ in situ become |
|---|---|---|---|---|
| Topsoil / humus (Horizon A) | 1,45 | 1,25 (+25 %) | 0,90 | 438 m³ bulked, 508 t |
| Silt / clay / loam (Horizon B) | 1,75 | 1,30 (+30 %) | 0,92 | 455 m³ bulked, 613 t |
| Sand and natural gravel / moraine | 1,95 | 1,18 (+18 %) | 0,95 | 413 m³ bulked, 683 t |
| Soft rock / crushed molasse | 2,20 | 1,40 (+40 %) | 1,10 | 490 m³ bulked, 770 t |
| Hard compact rock (Limestone / blasted granite or broken with a rock breaker) | 2,50 | 1,55 (+55 %) | 1,20 | 543 m³ bulked, 875 t |
Note on the text of the standard. These densities, bulking factors and compaction coefficients are those of the tool's specification: they are usual values, not verified in a standard. A geotechnical engineer's tests or the values of your quarry and your tip take priority.
Why the contractor invoices in “m3 in place” (CAN 211) but pays for trucks and the tip in “bulked m3” or by the tonne
The measurement rule earthworks volume in place SIA 118 recalled by the specification is simple: measurement is paid on the theoretical volume in place, never on the volume bulked in the trucks (CAN 211, Earthworks). For 350 m³ of silt in place, the company therefore invoices 350 m³, but pays for the transport of 455 m³ bulked, i.e. 613 tonnes at the tip. The difference is a cost borne by the company: it must be recovered in the unit price of the m³ in place.
Note on the text of the standard. The “in place” method of measurement is that of the specification and of CAN 211 practice; the text of CAN 211 and that of SIA 118 on this point were not consulted. The contract or the tender item may provide for another method of measurement: check it before pricing.
Sizing a truck rotation of 4-axle (32 tonnes) and 5-axle (40 tonnes) trucks without downtime for the excavator
The calculation number of 4-axle trucks spoil removal starts from two limits: the payload in tonnes and the body volume in m³. The more restrictive of the two sets the load of a trip. For the excavation in the example (350 m³ of silt, bulking 1.30, density 1.75 t/m³), an excavator that loads 35 m³ in place per hour and a round-trip cycle of 50 minutes:
| Truck | Trips | Limit | Load of one truck | Trucks in rotation |
|---|---|---|---|---|
| 3-axle truck 26t (payload ~14.5 t / ~9 m³) | 51 | Body volume | 11,8 min | 5 |
| 4-axle truck 32t (payload ~18.5 t / ~11.5 m³) | 40 | Body volume | 15,0 min | 4 |
| Articulated lorry / semi 40t (payload ~25.0 t / ~16 m³) | 29 | Body volume | 20,7 min | 3 |
| Site dumper 6t (payload ~5.5 t / ~3.2 m³) | 143 | Body volume | 4,2 min | 12 |
The number of trucks in rotation is the cycle time divided by the loading time of one truck, rounded up to the next whole number: with one truck fewer, the excavator waits; with one truck more, a truck waits. Excavator loading time: 10.0 h for 350 m³. ⚡ Price your earthworks in Soumission
Payloads and body volumes (~18.5 t / ~11.5 m³ for a 32 t 4-axle truck): specification values. The 40 t semi corresponds to the “Articulated lorry / semi 40t” line.
Safety of excavations and trenches (OTConst Art. 68 to 79 and SIA 267 standard): 1:1 slope, shoring and 50 cm free strip
The excavation slope gradient OTConst SIA 267 depends on the strength of the ground (Art. 75 OTConst). Art. 68 para. 2 requires, for excavations, shafts and earthworks more than 1.50 m deep that are not braced or shored, that they be sloped in accordance with Art. 75 or secured by other adequate measures. For the excavation in the example (depth of 2.80 m), the extra slope width per side is:
| Slope gradient | Angle | Overwidth per side | With the 1,00 m free strip |
|---|---|---|---|
| 1:1 (45°): medium loose ground | 45,0° | 2,80 m | 3,80 m |
| 2:1 (~63°): very cohesive consolidated ground | 63,4° | 1,40 m | 2,40 m |
| 3:1 (~72°): sound rock | 71,6° | 0,93 m | 1,93 m |
- Free strip at the top of the excavation (Art. 71): at least 50 cm when the excavation is braced or the wall is secured by sheet piles, pile walls, diaphragm walls or soil-nailed walls; at least 1 m when the wall is sloped.
- Engineer's or geotechnician's verification (Art. 76): if the slope exceeds 4 m, if it is steeper than 2:1 (1:1 in collapsing ground), if it carries loads or where water inflows are present.
- Shoring and bracing (Art. 77 and 78): designed for the foreseeable loads, with an unbraced lower part of at most 80 cm and an overhang of 15 cm above the edge.
- Working width: at least 60 cm in earthworks (Art. 70).
Note on the text of the standard. The specification cites the OTConst “Art. 72 to 75” and a 50 cm free strip for any excavation. According to the text of the ordinance (as at 1 January 2024), sloping falls under Art. 68 para. 2, 75 and 76 (Art. 72 deals with stockpiles, Art. 73 with stairs and ladders, Art. 74 with prevention of crossings) and the free strip is 50 cm for a braced excavation but 1 m for a sloped wall (Art. 71): the tool applies these articles. The 3:1 slope of sound rock exceeds the 2:1 of Art. 76 para. 1 let. b: it therefore also requires an engineer's verification. The content of the SIA 267 standard (geotechnics) was not consulted. For the full list of site measures, see the OTConst safety plan generator.
Frequently Asked Questions on Bulking, Trucks and Excavations (FAQ)
1. What is the bulking factor of soil and gravel?
Bulking is the swelling of a soil once excavated. The specification values, editable in the tool, are: topsoil 1.25, silt and clay 1.30, natural sand and gravel 1.18, soft rock 1.40 and compact rock 1.55. They are paired with densities in place of 1.45 to 2.50 t/m³ and with compaction coefficients of 0.90 to 1.20.
These are usual values, not verified in a standard: replace them with the results of your geotechnical engineer when you have them. For 350 m³ of silt in place, the volume to be transported is 455 m³ and the mass 613 tonnes.
2. How many m³ of soil in a 32-tonne 4-axle truck?
The 32 t 4-axle truck used by the specification carries about 18.5 tonnes of payload for a body of about 11.5 m³. The more restrictive of the two criteria limits the load. For a silt of 1.75 t/m³ in place bulked to 1.30: the payload would allow 10.6 m³ in place, the body only 8.8 m³ in place. So it is the body that limits, to about 8.8 m³ in place per trip.
For 350 m³, 40 trips are needed; with a 50-minute cycle and an excavator loading 35 m³/h, 4 trucks in rotation keep the excavator from waiting. Payloads and volumes are those of the specification.
3. Is earthworks measurement under SIA 118 done in place or bulked?
The specification recalls that measurement is paid on the theoretical volume in place, never on the volume bulked in the trucks (CAN 211, Earthworks). Bulking only comes into play in logistics: number of trips, body capacity, tip cost. The company therefore invoices 350 m³ in place, but pays for the transport of 455 m³ bulked.
The contract may provide for another method of measurement: check the tender item and the text of CAN 211 for your quote. For backfill, the volume to be placed is that of the compacted soil (322 m³ for 350 m³ of silt with the 0.92 coefficient).
Indicative information drawn up from the OTConst and the tool's specification; it replaces neither a geotechnical engineer's study nor the safety verification of the slopes.