Drainage Pipes Calculator (SIA 190 Slopes), Trenches & Bituminous Asphalt Tonnage
Calculator for drainage slopes, bedding and tonnage of bituminous asphalt.
Interactive tool
Values from the specifications. The compacted densities (bituminous mix 2,40 t/m³, i.e. 24 kg/m² per cm, aggregate 2,15 t/m³), the tack coat emulsion of 0,35 kg/m² and the slope range of 1,5 % to 5,0 % are those of the specifications. The minimum slopes per diameter in standard SN 592000 are not included (paid standard).
A Tonnage of bituminous asphalt and gravel foundation
Tonnages to order
- Aggregate 0/45 to order
- Base course ACT 22 N
- Wearing course AC 11 N
- Total bituminous mix
- Tack coat emulsion
Tonnage = area × thickness (m) × density × (1 + loss).
B Pipe laying, slope and trench
Slope, trench and laying volumes
- Level difference and end level
- Flow velocity at full bore
- Minimum trench width
- Bedding
- Pipe surround
- Total laying volume
Trench width: the wider of the OTConst requirement (art. 69 para. 3: at least 60 cm from 1 m depth, or 40 cm more than the outside diameter for a pipe of at most 40 cm inside diameter) and the specifications' rule (60 cm down to 1 m depth, then at least 80 cm or outside diameter + 2 × working space). Velocity: Manning formula with n = 0,011 (assumption of a smooth pipe).
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.04"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
Standard SIA 190 and SN 592000: the golden rules for laying a buried pipe (self-cleansing gradient, bedding and surround)
The standard SIA 190 on laying pipes, minimum gradient rests on three principles: a gradient sufficient for the wastewater to carry deposits away (self-cleansing), a regular bedding of 10 cm under the pipe and a surround that protects the pipe from loads. The standard SN 592000 on drainage of properties complements SIA 190 for the drainage installations of properties. For the section in the example (25 m in DN 150 at 2,0 %), the difference in level is 50 cm. The concrete or gravel bedding thickness of 10 cm is followed by a 20 cm surround above the pipe crown in 4/8 round gravel or lean concrete (the specifications speak of 15 to 30 cm).
What minimum gradient should be observed for a wastewater (EU) and clean water (EC) collector according to the DN diameter?
The tool adopts the specifications' recommended range, 1,5 % to 5,0 %, for the self-cleansing of wastewater: below 1,5 % it flags a risk of deposits, above 5,0 % it invites you to check the velocity. As a guide, the full-bore velocity from the Manning formula (coefficient n = 0,011, assumption of a smooth pipe) gives:
| Nominal diameter | Outside diameter | Slope of 1,5 % | Slope of 2,0 % | Slope of 5,0 % |
|---|---|---|---|---|
| DN 100 | 110 mm | 0,95 m/s | 1,10 m/s | 1,74 m/s |
| DN 125 | 125 mm | 1,10 m/s | 1,28 m/s | 2,02 m/s |
| DN 150 | 160 mm | 1,25 m/s | 1,44 m/s | 2,28 m/s |
| DN 200 | 200 mm | 1,51 m/s | 1,74 m/s | 2,76 m/s |
| DN 250 | 250 mm | 1,75 m/s | 2,02 m/s | 3,20 m/s |
| DN 300 | 315 mm | 1,98 m/s | 2,29 m/s | 3,62 m/s |
Note on the text of the standard. The specifications give neither a minimum gradient per diameter nor a difference between wastewater (EU) and clean water (EC): the tool applies a single range. The minimum gradients of standard SN 592000, which depend on the diameter, are not integrated (paid standard, not consulted). The municipality's general drainage plan (PGEE) and the project engineer prevail. The Manning velocity is a calculation benchmark: the formula assumes a smooth, full pipe.
Minimum trench width and frost-free cover of water pipes in Switzerland (80 cm to 120 cm depending on altitude)
The minimum trench width for a pipe according to SUVA and SIA 190 is first of all a safety rule: where the excavation must be accessible for laying pipes, the OTConst requires a usable width of at least 60 cm as soon as the depth exceeds 1 m and, for a pipe of at most 40 cm inside diameter, at least 40 cm plus the outside diameter (art. 69 para. 3). The specifications add their own rule: 60 cm down to 1 m depth, then at least 80 cm or the outside diameter plus twice the working space. The tool adopts the wider of the two. At 1,60 m depth and with 0,30 m of working space per side:
| Nominal diameter | OTConst requirement | Rule from the specifications | Width used | Laying volume per metre |
|---|---|---|---|---|
| DN 100 | 0,60 m | 0,80 m | 0,80 m | 0,318 m³ |
| DN 125 | 0,60 m | 0,80 m | 0,80 m | 0,328 m³ |
| DN 150 | 0,60 m | 0,80 m | 0,80 m | 0,348 m³ |
| DN 200 | 0,60 m | 0,80 m | 0,80 m | 0,368 m³ |
| DN 250 | 0,65 m | 0,85 m | 0,85 m | 0,418 m³ |
| DN 300 | 0,72 m | 0,92 m | 0,92 m | 0,485 m³ |
Note on the text of the standard. The frost-free cover of 80 to 120 cm depending on altitude is a benchmark from the specifications, not verified: the SSIGE guidelines (water pipes) were not consulted, and the tool does not calculate it. For a depth of one metre at most, the specifications give «60 to 70 cm»: the tool adopts 60 cm, the low value. The content of standard SIA 190 was not consulted. For the safety of the excavation itself (slopes, shoring), see the bulking, trucks and slopes calculator and the OTConst safety plan.
How to calculate the tonnage of bituminous asphalt mix (ACT / AC) with the rule of 24 kg/m2 per centimetre of thickness
The calculation of the tonnage of bituminous asphalt mix per m2 in Switzerland comes down to a rule of three: a compacted mix of 2,40 t/m³ weighs 24 kg per m² per centimetre of thickness. The tonnage to order is the area multiplied by the thickness (in metres), by the density and by (1 + laying loss). Weight per m² according to layer thickness:
| Thickness | Weight per m² | Tonnes per 100 m² |
|---|---|---|
| 3,5 cm | 84 kg/m² | 8,4 t |
| 4,0 cm | 96 kg/m² | 9,6 t |
| 6,0 cm | 144 kg/m² | 14,4 t |
| 8,0 cm | 192 kg/m² | 19,2 t |
| 10,0 cm | 240 kg/m² | 24,0 t |
For the yard in the example (250 m², 40 cm of 0/45 gravel, 6,0 cm of ACT 22 N and 3,5 cm of AC 11 N, 5 % loss): 225,8 t of gravel (density 2,15 t/m³), 37,8 t of ACT, 22,1 t of AC, i.e. 59,9 t of asphalt mix, and 87,5 kg of tack coat emulsion at 0,35 kg/m². ⚡ Price your surfacing in Soumission
Compacted densities, tack coat emulsion and designations ACT 22 N and AC 11 N: values from the specifications, not verified in the VSS standards.
Civil engineering acceptance tests: plate bearing test (ME1 / ME2 VSS), watertightness test and camera inspection of sewers
The acceptance of a civil engineering structure is proven by tests, not by a visual check. The plate bearing test (VSS standards) measures the deformation modulus at the first loading (ME1) and then at the second (ME2): the ratio between the two indicates the compaction of the foundation. Sewers are checked by a watertightness test, with water or air, and by a camera inspection that detects deformations, cracks and back-falls before the trench is finally closed.
Note on the text of the standard. The specifications give no acceptance value (ME moduli, test pressure, duration) and the VSS standards and SIA 190 were not consulted: the tool does not calculate these tests and integrates no threshold for them. The criteria are in the project description and in the applicable standard; ask the site management for them before concreting or backfilling.
Frequently Asked Questions about Pipes, Asphalt Mixes and Gradient (FAQ)
1. How many tonnes of asphalt mix per m² for 4 cm or 8 cm of thickness?
With a compacted density of 2,40 t/m³, i.e. 24 kg/m² per centimetre of thickness, 4 cm of asphalt mix weighs 96 kg/m² (0,096 t/m²) and 8 cm weighs 192 kg/m² (0,192 t/m²). Simply multiply the area by this weight and add the laying loss.
For a yard of 250 m² with 6,0 cm of ACT 22 N and 3,5 cm of AC 11 N, 5 % loss, you need 37,8 t of base course, 22,1 t of wearing course and 225,8 t of 0/45 gravel at 40 cm (density 2,15 t/m³). Densities and tack coat emulsion (0,35 kg/m²): values from the specifications.
2. What is the minimum gradient of a wastewater pipe in DN 150?
The tool adopts the specifications' recommended range, 1,5 % to 5,0 %, so that wastewater is self-cleansing: below 1,5 % it flags a risk of deposits. At 2,0 % over 25 m, the difference in level is 50 cm and the full-bore velocity about 1,44 m/s (Manning formula, smooth pipe).
The minimum gradients per diameter of standard SN 592000 are not integrated: the standard is paid and was not consulted. The municipality's general drainage plan (PGEE) and the project engineer prevail.
3. What frost-free depth for a water pipe?
The specifications give a cover of 80 to 120 cm depending on altitude: frost goes deeper in the mountains. This value is an unverified benchmark: the SSIGE guidelines were not consulted. The tool does not calculate the frost-free cover, but the trench width: 0,80 m for a DN 150 pipe (outside diameter 160 mm) at 1,60 m depth.
The OTConst (art. 69 para. 3) requires a usable width of at least 60 cm from one metre depth and, for a pipe of at most 40 cm inside diameter, 40 cm more than the outside diameter: the tool adopts the wider of this requirement and the specifications' rule.
Indicative information prepared from the OTConst and the tool's specifications; it replaces neither standards SIA 190 and SN 592000 nor the engineer's design.