Special Foundations Calculator: Bored Piles, Nailed Walls & Soldier-Pile Walls (SIA 267)
Preliminary sizing tool for micropiles, soldier-pile walls & anchors.
Interactive tool
Preliminary sizing. The concrete overconsumption (+15 % or +25 %), the shotcrete rebound (+25 %), the reinforcement ratio and the nail grid are those of the specifications, not verified in any standard: the geotechnical engineer designs the structure (SIA 267).
A Calculation mode
1 Type of structure
Bored pile quantities
- Total linear drilling length
- Theoretical concrete volume
- Actual volume to order (C25/30 or C30/37 concrete)
- Reinforcing steel B500B
- Pile heads to be cut off
Theoretical volume = N × π × (D/2)² × L; actual volume = theoretical volume × (1 + overconsumption); steel = theoretical volume × ratio.
Soil-nailed wall quantities
- Supported wall area
- Passive anchor nails
- Theoretical shotcrete
- Actual shotcrete including rebound
- Welded mesh
Nails = area / (horizontal spacing × vertical spacing), rounded up to the next whole number; drilling and GEWI bars = number of nails × length of one nail; actual concrete = theoretical concrete × (1 + rebound); mesh = area × 1.15.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="6.05"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
SIA 267 standard (Geotechnics): choosing between a soil-nailed wall, a soldier-pile (Berlin) wall, a sheet pile wall and a diaphragm wall
Special foundations piles soil-nailed wall SIA 267 cover structures that a simple excavation is not enough to build: deep foundations on piles, retention of a deep excavation, underpinning. The SIA 267 standard (geotechnics) is the reference for design; the choice of system is up to the geotechnical engineer. The soldier-pile wall vs soil-nailed wall shotcrete comparison is the first question for an urban excavation:
| System | Principle | Points to watch |
|---|---|---|
| Soil-nailed wall | Excavation in descending stages, passive nails grouted into the ground, shotcrete reinforced with a mesh. | Ground that stands vertically for a moment; nails that sometimes leave the plot; poorly suited below the water table. |
| Soldier-pile wall | Steel sections driven before excavation, lagging (timber or shotcrete) placed between them, anchors or struts. | Quick to build; anchors need permission from the neighbour; not watertight. |
| Sheet pile wall | Interlocking sections driven or vibrated, tiebacks or struts. | Largely watertight; vibration and noise during installation. |
| Diaphragm wall | Reinforced concrete diaphragm cast in a trench under slurry, anchors or struts. | Very rigid and watertight; expensive, reserved for great depths and sensitive neighbouring buildings. |
Note on the text of the standard. The content of the SIA 267 standard was not consulted (paid standard): the comparison above gives general characteristics of the trade, not criteria from the standard. The tool quantifies the soil-nailed wall and the bored piles; the soldier-pile wall, sheet piles and diaphragm wall are not priced.
In which cases does an urban or sloping excavation require special retention (party wall, water table, height > 4 m)?
Three situations almost always call for an engineer's study. The party wall: a neighbouring building nearby rules out a simple slope. The water table: water inflows destabilise the walls. The height: the OTConst requires a safety verification drawn up by a specialist engineer or geotechnician for a slope of more than 4 m, for a slope steeper than 2:1 (1:1 in collapsing ground), for a slope that carries loads or where water inflows are present (Art. 76). Ground consolidation by injection, shotcreting or freezing is allowed only on presentation of a safety and stability verification (Art. 79), and the edge of a soil-nailed, pile or diaphragm wall remains free for at least 50 cm (Art. 71 let. a). For the safety measures of the excavation itself, see the bulking, trucks and slopes calculator and the OTConst safety plan.
Pricing bored piles (CAN 141) and a soil-nailed wall: the trap of concrete overconsumption and shotcrete rebound
The CAN 141 code special works geotechnics is the one the specification uses for special foundation works (the specification also cites CAN 141 to 153); the exact code to use is that of the architect's bill of quantities. The calculation of bored pile concrete volume overconsumption starts from the theoretical cylinder N × π × (D/2)² × L, then adds the ground overconsumption. For 16 piles of 600 mm and 12 m:
| Assumption | Concrete to order | Deviation from the theoretical |
|---|---|---|
| Theoretical volume | 54,3 m³ | — |
| Oscillating casing (+15 %) | 62,4 m³ | +8,1 m³ |
| Under slurry or in loose ground (+25 %) | 67,9 m³ | +13,6 m³ |
Cage reinforcement at 95 kg/m³: 5'157 kg of B500B steel. For the soil-nailed wall, the trap is rebound: part of the shotcrete falls to the ground. For 40 m of excavation of 5.5 m (220 m² of wall), 15 cm of shotcrete and 25% rebound, the theoretical concrete of 33.0 m³ becomes 41.3 m³ to order, with 253 m² of welded mesh (15% overlap). ⚡ Price your special works in Soumission
Note on the text of the standard. The concrete overconsumption (+15% or +25%), the +25% rebound, the reinforcement ratio of 95 kg/m³ and the 15% mesh overlap are those of the specification and were not verified in a standard. Tighter casing, known ground or wet-process shotcrete lower them.
Anchor tests (SIA 267), inclinometer monitoring and underground easements on the neighbour's land for the anchors
The nail grid anchors prestressed SIA 267 determines the number of nails: wall area divided by the horizontal spacing and by the vertical spacing, rounded up to the next whole number. For the wall in the example:
| Grid | Nails | Drilling and bars (4,5 m per nail) |
|---|---|---|
| 1,00 m × 1,00 m | 220 | 990,0 ml |
| 1,50 m × 1,50 m | 98 | 441,0 ml |
| 2,00 m × 2,00 m | 55 | 247,5 ml |
Anchors are proof-tested by pull-out tests before they are put into service, and the deformations of the wall are tracked by inclinometer measurements during excavation. When the nails or anchors leave the plot, they encroach on the neighbour's land: ownership of the ground extends in depth to the extent useful (Art. 667 CC) and the agreement is settled by a contract and an easement entered in the land register (Art. 730 ff. CC), often with compensation.
Note on the text of the standard. The anchor test protocols, the acceptance criteria and the monitoring thresholds of the SIA 267 standard are not in the specification and were not consulted: the tool does not calculate them. The articles of the Civil Code are quoted for information; the agreement with the neighbour is made with a notary. Nail length: the specification suggests 0.7 to 0.8 times the height; the tool's default value (4.5 m for 5.5 m) is an editable assumption.
Frequently Asked Questions on Piles, Soil-Nailed Walls and Anchors (FAQ)
1. What is the difference between a soil-nailed wall and a soldier-pile wall?
The soil-nailed wall reinforces the ground itself: you excavate in descending stages, drive passive anchor nails into the ground, then spray concrete reinforced with a mesh onto the face. It suits excavations whose ground stands vertically for a moment. The soldier-pile (Berlin) wall, on the other hand, rests on vertical steel sections driven before excavation, between which lagging (timber or shotcrete) is placed, with anchors or struts if the height requires it.
For 40 m of excavation of 5.5 m, the tool counts 220 m² of soil-nailed wall and 98 nails on a 1.50 × 1.50 m grid. The choice between the two is up to the geotechnical engineer (SIA 267), who takes account of the ground, the water table and the neighbouring buildings.
2. Why allow 15 to 25% more concrete in a bored pile?
The concrete fills the real cavity of the borehole, which is always a little larger than the theoretical cylinder: oscillating casing, ground irregularities and loose zones make it consume more than π × (D/2)² × L. The specification suggests +15% with oscillating casing and +25% under slurry or in loose ground. For 16 piles of 600 mm and 12 m, the theoretical volume is 54.3 m³; 62.4 m³ must be ordered at +15% and 67.9 m³ at +25%.
These percentages, like the reinforcement ratio of 95 kg/m³ (i.e. 5'157 kg of B500B steel), are those of the specification, not verified in a standard. Tighter casing or known ground lowers them.
3. Is the neighbour's agreement needed to place nails or anchors under their land?
Yes. Ownership of the ground extends in depth to the extent that the owner has an interest in exercising it (Art. 667 CC): anchors or nails that go beyond the boundary of the plot encroach on the neighbouring land. The neighbour's agreement is therefore needed, in practice a written agreement and an easement entered in the land register (Art. 730 ff. CC), often with compensation and a clause on the fate of the anchors after the work (deactivation or removal).
Of the 98 nails in the example, 4.5 m each, those that leave the plot are concerned. Have the agreement checked by a notary or a lawyer: the tool does not give legal advice.
Indicative information drawn up from the OTConst and the tool's specification; it replaces neither the design by the geotechnical engineer (SIA 267) nor legal advice.
