Unit times Tool 3.11 Online

Database of Installation Rates (Hours/m²) & Materials Margin Calculator

Look up installation rates in hours per m² and calculate your margin on materials.

Interactive tool

A Planning of hours and site duration

h
CHF/hPre-filled with the 2026 ACIP daywork rate for the trade (tool 2.1). Calculate your real production cost.

Hours, duration and labour budget

Total labour hours required
Number of working days on site for the crew (8.25 h per day basis)
Total labour budget

B Multiplier coefficient and real margin on materials

CHF
%
%
%

Your real selling price

Production cost = purchase price × (1 + waste) × (1 + handling). Selling price = production cost ÷ (1 − margin on selling price). Coefficient = selling price ÷ purchase price.

Cost price of the installed material
Selling price of the material
Overall multiplier coefficient
Installation labour (unit time × hourly rate)
Complete unit price "supplied and installed"

⚡ Find the 35 chapters already calculated in our Soumission ACIP module

Why divide by (1 − margin)? A 20% margin is calculated on the selling price, not on the cost: multiplying the cost by 1.20 gives only a real margin of 16.7%. Unit times are averages for a skilled worker: adjust them to access, height and complexity.

Embed this calculator on a website page

Paste this code into the page, or write [outil code="3.11"] in the content of a page on the site.

📄 File linked to this tool (free)

Move from calculation to full management

Keep your references at hand, then automate them in your quotes, bids and final statements.

⚡ Automate this calculation in our ERP / Soumission software (Trial)

Technical reference guide

Swiss reference system of unit execution times by category of work (ratios of productive hours per m², m³ or lm)

The average laying time per m2 Swiss construction of a work item is the number of productive hours a skilled worker needs to carry out one unit under normal conditions. This unit times table construction serves two purposes: estimating the duration of a site (quantity × unit time, divided by the number of workers and by 8.25 hours per day) and calculating the price of labour (hours × hourly rate). Ten work items take over the table in the tool's specification; the others are editorial indicative values (flagged), to be validated against your own records. These are productive hours: to find your real hourly production cost, use the worker cost simulator.

1. Structural work, formwork, reinforcement and brick masonry

For structural work, the reference laying rate tiles painting masonry plasterboard m2 hour is about 8.5–11 m² per day for 15 cm brick masonry, 10–12.5 m² per day for wall formwork and 280–370 kg per day for reinforcement. Add waste and overlaps to your quantities.

Unit times and installation rates
WorkUnitAverage unit time (hours per unit)Daily output (1 journeyman, 8,25 h)Waste rate / material loss
Clay brick masonry, 15 cm thickm²0,75 to 0,95 h / m²~8,5 to 11 m² / day5 % (bricks) / 10 % (mortar)
Formwork for concrete walls (panel formwork) / slabsm²0,65 to 0,85 h / m²~10 to 12,5 m² / day5 % (timber / consumables)
Reinforcement fixing / placing of B500B barskg0,022 to 0,030 h / kg~280 to 370 kg / day8 % to 12 % (overlaps / offcuts)
Poured and vibrated concrete (slab or wall, pump on site) (indicative value)m³0,90 to 1,40 h / m³~6 to 9 m³ / day3 % (over-consumption)
Outdoor paving (concrete pavers on a sand bed) (indicative value)m²0,90 to 1,30 h / m²~6,5 to 9 m² / day5 % to 8 % (cuts)

2. Finishing work — Plastering-painting, external thermal insulation (ITE), tiles, parquet and joinery

In finishing work, times vary greatly with the quality of finish and access: a drywall partition at Q2 finish takes 0.65–0.85 h/m², a Q3/Q4 skim 0.25–0.40 h/m², interior painting 0.22–0.32 h/m² and 60×60 tiling 0.85–1.15 h/m². The waste rate tile cutting parquet rises to 10% for straight laying and to 15% for diagonal laying.

Unit times and installation rates
WorkUnitAverage unit time (hours per unit)Daily output (1 journeyman, 8,25 h)Waste rate / material loss
Rendered external façade insulation (ITE), completem²1,10 to 1,40 h / m²~6 to 7,5 m² / day7 % (EPS / mineral wool boards)
Drywall partition with plasterboard (1+1 on studs + insulation)m²0,65 to 0,85 h / m²~10 to 12,5 m² / day8 % (boards and profiles)
Suspended ceiling (boards on framework) (indicative value)m²0,55 to 0,80 h / m²~10,5 to 15 m² / day7 % (boards and framework)
Full-skim plastering Q3 / Q4 on walls and ceilingsm²0,25 to 0,40 h / m²~20 to 33 m² / day10 % (plaster)
Interior painting (primer + 2 coats of emulsion)m²0,22 to 0,32 h / m²~26 to 37 m² / day5 % to 8 %
Floor tile laying (60×60 cm format, double-buttering)m²0,85 to 1,15 h / m²~7 to 9,5 m² / day10 % (straight laying) / 15 % (diagonal)
Wall tiles (adhesive-fixed, joints included) (indicative value)m²1,10 to 1,50 h / m²~5,5 to 7,5 m² / day10 % to 15 % (cuts)
Fully bonded parquet installation (planks)m²0,60 to 0,80 h / m²~10 to 13,5 m² / day7 % to 10 % (cuts)
Floating cement screed (6 cm, over insulation) (indicative value)m²0,30 to 0,45 h / m²~18,5 to 27,5 m² / day5 % (mortar)
Bituminous flat roof waterproofing (2 layers) (indicative value)m²0,45 to 0,65 h / m²~12,5 to 18,5 m² / day8 % to 12 % (overlaps)
Skirting boards installation (indicative value)ml0,12 to 0,20 h / lin. m~41 to 69 lin. m / day8 % (corner cuts)
Installation of a standard window (removal of the old one not included) (indicative value)pcs2,50 to 4,00 h / pcs~2,1 to 3,3 pcs / day0 % (single piece)

3. Building services — Electrical, underfloor heating and plumbing

For building services, one worker lays 18 to 27 m² of underfloor heating pipes per day on studded insulation board. Times for electrical and plumbing installations depend heavily on the number of points and the length of runs: use the indicative values as a starting point and replace them with your own records.

Unit times and installation rates
WorkUnitAverage unit time (hours per unit)Daily output (1 journeyman, 8,25 h)Waste rate / material loss
Laying underfloor heating pipes (on studded insulation board)m²0,30 to 0,45 h / m²~18 to 27 m² / day5 % (PE-Xa / multilayer pipes)
Pulling electrical conduits and cables (indicative value)ml0,080 to 0,15 h / lin. m~55 to 103 lin. m / day8 % (cable offcuts)
Installation of flush-mounted sockets and switches (indicative value)pcs0,35 to 0,60 h / pcs~14 to 23,5 pcs / day0 % (single piece)
Multilayer sanitary piping (installation and fittings) (indicative value)ml0,30 to 0,50 h / lin. m~16,5 to 27,5 lin. m / day5 % (offcuts)

How to calculate your real selling price on supplies and materials (cutting waste, transport, overheads and profit)?

The calculation multiplier coefficient margin materials tradesman follows three steps: production cost of the installed material = net purchase price × (1 + waste rate) × (1 + handling costs); selling price = production cost ÷ (1 − margin on selling price); multiplier coefficient = selling price ÷ purchase price. Example: a material bought at CHF 38.00/m², with 10% waste and 5% handling, costs CHF 43.89/m²; for a 20% margin on the sale, it is sold at CHF 54.86/m², i.e. an overall coefficient of 1.4437. Add the laying labour to obtain the complete unit price "supplied and installed".

1. Why adding +15% to the supplier's purchase price makes you lose money (the difference between margin on selling price and markup on cost + a loss/waste rate of 5% to 15%)

A +15% surcharge on the purchase price covers neither cutting waste (5% to 15% depending on the material), nor transport, nor overheads. In the example above, +15% gives CHF 43.70/m², while the production cost is already CHF 43.89/m²: every square metre sold costs you money. The trap is twofold: confusing markup (calculated on cost: price = cost × 1.20) and margin on selling price (calculated on the selling price: price = cost ÷ 0.80). Multiplying by 1.20 gives only a real margin of 16.7%; to reach 20% you must divide by 0.80, i.e. multiply by 1.25. Always start from the full production cost.

Real margin according to the calculation method (material at CHF 38, 10% waste, 5% handling)
MethodSelling price per m²Real margin on the sale
+15 % on the purchase price43.70 CHF-0,4 %
Cost price × 1,20 (margin rate)52.67 CHF16,7 %
Production cost ÷ 0.80 (20% margin on selling price)54.86 CHF20,0 %

⚡ Find the 35 chapters already calculated in our Soumission ACIP module

Frequently asked questions on calculating laying times and margins (FAQ)

1. How do you use unit times to calculate the duration and cost of a site?

Multiply the quantity by the unit time: this gives the total hours. Divide this total by the number of workers and by 8.25 hours per day to get the duration in days. Example: 120 m² of tiles at 1.00 h per m², i.e. 120 h; with 2 workers, 7.27 days on site.

Then multiply the hours by the hourly rate: at CHF 96 per hour (average ACIP daywork rate for finishing trades), the labour budget is CHF 11'520. To get your real production cost, go through the worker cost simulator (tool 2.1).

2. What is the difference between margin on selling price and markup on cost, and why is multiplying by 1 + margin a mistake?

The margin on selling price is calculated on the selling price: selling price = production cost / (1 − margin on selling price). The markup is calculated on the cost: price = cost × (1 + rate). To aim for a 20% margin on the sale, you must divide by 0.80, i.e. multiply by 1.25, and not by 1.20.

Example: a material bought at CHF 38 per m², with 10% waste and 5% handling, costs CHF 43.89. Multiplied by 1.20, it would be sold at CHF 52.67: your real margin is only 16.7%. Divided by 0.80, it is sold at CHF 54.86, i.e. CHF 2.19 more per m².

3. Why does a +15% surcharge on the purchase price lose money?

Because +15% covers neither cutting waste nor handling: on a material at CHF 38 with 10% waste and 5% handling, the production cost is CHF 43.89, and a selling price at +15% on the purchase (CHF 43.70) is below that cost. Every square metre installed costs you money before overheads are even counted.

Always calculate the full production cost, then divide by (1 − margin on selling price). The overall multiplier coefficient in the example is 1.4437 on the purchase price.

4. Where do the tool's unit times and waste rates come from?

Ten work items (brick masonry, formwork, reinforcement, external thermal insulation, drywall partition, skim coat, painting, tiling, glued parquet, underfloor heating) take over the table in the tool's specification. The other work items are editorial indicative values, flagged as such in the tool: validate them against your own site records.

These are averages for a skilled worker under normal conditions (8.25 hours per day, excluding preparation and travel): adjust the unit time to access, height, complexity and crew.

Unit times are indicative averages: validate them against your own site records before using them in a quotation.