Pack of 3 Word Letter Templates: Contractor's Duty to Notify (Art. 25 SIA 118) & Notice of Defects

Complete 7-page guide (PDF) and Word template. The contractor's duty to notify (devoir d'avis) before installation, the client's notice of defects (avis de défauts) after delivery, deadlines before and after 1 January 2026, the client's rights and four letters.

Interactive tool: legal reservation paragraph ready to copy and paste

Loading the tool…

📄 The « Brut de chantier » pack to download (free)

DOCXPDF

Notice of Defects & Duty to Notify Templates (Art. 25 SIA 118)

Complete 7-page guide (PDF) and Word template. The contractor's duty to notify (devoir d'avis) before installation, the client's notice of defects (avis de défauts) after delivery, deadlines before and after 1 January 2026, the client's rights and four letters.

  • Legal basis, what changed on 1 January 2026 and notice periods
  • Procedure for the contractor and for the client, content of a valid notice of defects
  • Four letters to adapt, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted

Editable Word template (.docx) · Printable PDF document

1. Detail of the 3 legal letter templates included in the downloadable pack

Three letters to adapt, to be sent by registered mail or by e-mail with acknowledgement of receipt. Keep a dated copy of each.

1.1 Letter no. 1 — Duty to notify and formal reservation on an unsuitable existing substrate or a risky instruction (Art. 25 SIA 118 / Art. 365 para. 3 CO)

A contractor who finds that a substrate, a prescribed material or an instruction jeopardises the work must inform the client immediately (Art. 365 para. 3 CO). The letter describes the finding, suspends execution of the part concerned, attaches a quotation for restoring the level and asks for a written decision within 5 working days.

1.2 Letter no. 2 — Formal notice of defects and demand (mise en demeure) to remedy addressed to a defaulting subcontractor

The letter describes the defects found, with photos in support, sets a period of 10 days to repair them and, failing that, announces execution by a third party at the subcontractor's expense, subject to the price reduction and damages.

1.3 Letter no. 3 — Formal notice to provide security (Art. 83 CO) and quotation for restoring the substrate (levelling, sanding, drying)

Third letter of the pack: when objective elements jeopardise payment, the contractor suspends its performance and demands security within a reasonable period (Art. 83 CO), failing which it withdraws from the contract. The quotation for restoring the substrate, with the price of the change order, is attached to letter no. 1: the pack promises nothing more than these three letters.

2. Why an oral remark at a site meeting never protects you before a Swiss court

The duty to notify is a duty of information: it is proved by dated writings, not by memories of meetings.

2.1 The constant case law of the Federal Supreme Court: the contractor is « the one who knows » vis-à-vis the client and even vis-à-vis the architect

The contractor is presumed to know the rules of the trade and must warn the client of the risks it perceives, even when the architect drafted the bill of quantities. The greater the contractor's competence, the wider its duty to notify. An oral notice, without a trace, is very difficult to prove.

2.2 How to turn a notice of reservation about a defective substrate into additional works paid as daywork

Once the notice has been sent, two legitimate outcomes exist: the client corrects the substrate at its own expense, or instructs you to do so against payment. In the second case, have the change order signed before acting or, in an emergency, invoice as daywork with a signed-off slip.

3. Frequently asked questions about the contractor's duty to notify (FAQ)

3.1 What should I do if the architect orders me in writing to lay despite my letter of reservation (Art. 25 SIA 118)?

Carry out the work on written order, provided you have stated your reservation: the text of letter no. 1 provides that you continue at the client's risk for the consequences of the defect reported. Keep the written order with your notice: together, they delimit the responsibilities.

3.2 Should you send your notice of reservation by registered mail or is an e-mail enough?

An e-mail with a read receipt may suffice as proof, but registered mail remains the safest route. The best is to combine both: an immediate e-mail for speed, registered mail for proof, with a copy to the site management.

3.3 Does the duty to notify automatically suspend my contractual execution periods (Art. 96 SIA 118)?

No, not automatically: you must request the extension of the periods in the same letter. Art. 96 SIA 118 (to be checked in the applicable edition) allows an obstacle not attributable to the firm to be invoked; the letter of reservation must therefore also reserve the extension of the period.

Keywords covered: duty to notify letter template SIA 118 art 25 · letter of reservation non-compliant substrate Swiss site word · article 365 para 3 CO contractor liability · notice of defects letter template subcontractor Switzerland · formal notice to provide security site · releasing craftsman liability architect instruction.

General information based on Swiss law in force — does not replace personalised legal advice.

The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.