Key takeaways
- The as-built drawing records the exact layout of hidden sheets, upstands and penetrations.
- The technical data sheets certify the chemical and mechanical compatibility of the membranes with their substrate thermal insulation.
- An identified membrane coupon enables comparative laboratory tests in the event of deferred damage.
- Test records from water testing or tracer gas attest to compliance before backfilling.
Documenting invisible layers using the as-built drawing and technical data sheets
As soon as the protective gravel, green roof substrate or slab pavers on pedestal supports are in place, the waterproofing build-up becomes completely invisible. Ten or fifteen years after execution, when water ingress occurs or additional technical equipment is installed, the building operator and contractors frequently encounter a lack of documentation. Without faithful execution documents, no one knows the nature of the membrane, the thickness of the vapour barrier or the thermal resistance of the insulation used. Drawing up an as-built drawing of the layers and gathering manufacturers' technical data sheets constitutes the only rigorous method to remove these technical uncertainties without resorting to costly destructive testing.
- Waterproofing as-built drawing
- Contractual graphic document drawn up after the completion of the work, representing the actual and final state of the waterproofing build-up, including modifications made during the construction site, the precise location of rainwater outlets, overflows, expansion joints and parapet upstand details.
- Record the actual geometric layoutTransfer to the roof plan the actual dimensions of the rainwater outlets, the exact position of emergency overflows, the structural work expansion joint lines and the actual slope direction towards the outlets.
- Detail the composition of the build-up using a typical sectionDraw the annotated schematic section from the concrete or timber substrate up to the wear layer: primer, vapour barrier with corner reinforcements, bonded or mechanically fastened insulation boards, base layer and capping sheet.
- Record details and interfacesIndicate the type of fastening for skylight upstands, the minimum height of each parapet upstand, ventilation pipe penetrations, and the waterproofing method under French window thresholds.
- Compile the technical data sheets of the materialsAttach the technical data sheets for each component installed: bituminous or synthetic binder, cold adhesive, bonding primer, vapour barrier and insulation boards, with the exact batch references delivered.
| Element of the build-up | Information to record | Associated supporting document |
|---|---|---|
| Substrate and preparation | Nature of substrate, surface finish, type of bituminous or synthetic primer | Technical data sheet for the primer |
| Vapour barrier | Thickness, reinforcement, installation method (welded, bonded), declared sd value | Manufacturer's declaration of performance |
| Thermal insulation | Type (PIR, EPS, mineral wool), thickness, compressive strength | Technical data sheet and approval certificate |
| Single-layer or two-layer waterproofing | Polymer type (SBS, APP, FPO, EPDM), total thickness, reinforcement, root-resistant treatment | Product technical data sheet and traceability label |
| Protection and ballast | Grain size of round gravel (16/32), layer thickness, type of separating geotextile | Delivery note for aggregates or slabs |
Archiving the control membrane offcut and recording test records
Handing over the file to the client is accompanied by tangible physical elements. Providing a physical sample from the construction site, commonly referred to as the retained membrane offcut, is an essential precaution. In the event of a subsequent dispute or premature ageing observed on the roof, this control coupon, unexposed to weathering and ultraviolet radiation, allows for comparative laboratory analyses. It serves to determine whether degradation stems from an intrinsic defect in the original material or from external aggression linked to building operation.
Test records complete quality assurance before the heavy protective layer is installed. Whether it is a systematic visual inspection of welds using a seam probe, a vacuum bell test on synthetic membranes, a smoke test under the waterproofing or a water test maintained for forty-eight hours, each inspection must be documented in a jointly signed record. Standard SIA 118 governs the procedures for joint verification of the work.
Upon acceptance of the work, the contractor is released from liability, except for defects that could not be detected during the regular verification or that were intentionally concealed.
art. 370 CO
Ten-year diagnosis under ballast: using the as-built drawing and technical data sheets
Ten years after the acceptance of an inaccessible or gravel-ballasted flat roof, active memories of the construction site have completely vanished: installation crews have changed, the general contractor has sometimes ceased trading and successive operators often rely merely on guesswork. When a damp patch penetrates the concrete ceiling slab of a heated room, the property manager faces an area of several hundred square metres covered in round gravel or slabs on pedestal supports. Without an as-built drawing of the layers, leak detection requires repeated destructive testing, haphazard shovelling of dozens of cubic metres of ballast and the permanent risk of puncturing the waterproofing with shovel strikes. The as-built drawing indicates the precise millimetre location of rainwater outlets, the exact position of expansion joints, the thickness and slope of insulation boards, and the roll laying direction.
| Investigated parameter | With complete file | Without technical file | Consequence for the work |
|---|---|---|---|
| System type | Manufacturer's technical data sheet identified (SBS, APP, PVC, FPO) | Total uncertainty, pyrolysis or solvent test required | Chemical incompatibility when welding a repair patch |
| Slope layout | As-built drawing with valley and ridge line levels | Topography hidden under ballast or topsoil | Prolonged water ponding after inaccurate backfilling |
| Insulation type | Type (EPS, PIR, mineral wool) and compressibility recorded | Destructive cutting of the build-up to measure thickness | Thermal crushing or creation of a permanent cold bridge |
| Details | Identification of penetrations and pipes hidden under gravel | Blind searching along upstands and flashings | Damage to a waterproofing upstand caused by clearing equipment |
The product technical data sheet archived in the as-built documentation prevents major defects during subsequent connections. If a building technician needs to install new heat pump pipework or a penetrating ventilation duct, they must know the chemical composition of the binder. Laying a new plasticised PVC sheet directly in contact with an old elastomeric bitumen membrane triggers destructive plasticiser migration, leading to rapid embrittlement and cracking of the synthetic sheet within a few months. Likewise, flexible polyolefin (FPO) membranes require specific hot-air welding temperature ranges and cleaning solvents that only the manufacturer's technical data sheet can specify unambiguously.
Control sample and test records: resolving doubts during expert assessments
In the event of delayed damage, the technical expert appointed by the parties seeks to determine whether the defect arises from an intrinsic material defect, an application error or external environmental aggression. The membrane offcut retained in the waterproofing file represents decisive evidence. It allows initial mechanical characteristics of the virgin material to be measured in a laboratory: cold flexibility, tensile strength of the reinforcement and compound stability. By comparing this preserved sample to a coupon cut from the aged roof, specialists can immediately distinguish degradation caused by micro-organisms, maintenance chemicals or local overheating under gravel from an original manufacturing defect.
- Static water test record: certifies the absolute watertightness of the basin prior to ballast placement, demonstrating that no leak existed upon handover.
- Tracer gas or smoke leak detection: certifies the absence of initial micro-punctures across main surfaces and longitudinal laps.
- Log of non-destructive seam probe checks: proves that every welded overlap was systematically checked to verify weld bead continuity.
- Fastener pull-out test record: records the mechanical resistance of insulation fixings against wind uplift in accordance with recognised standards.
This compilation of tests, appended to the validated as-built drawing, forms the conclusive core of the as-built documentation handed over to the client during acceptance of the work according to standard SIA 118. It durably protects the waterproofing contractor against unjustified claims when third-party trades modify the superstructure, install solar panels without precautions or damage the waterproofing build-up during landscaping work or chimney maintenance.
Late dispute or infiltration: reconstructing waterproofing records in the absence of a complete file
Ten years after acceptance of the work, water ingress beneath a ballasted roof quickly escalates into a technical dispute if the operator has no as-built drawing or technical data sheets. Gravel or green roof layers conceal the exact composition of the build-up: whether synthetic or bituminous sheets were used, presence of a bituminous vapour control layer or PE film, type of thermal insulation in EPS, PIR or rock wool. If the control membrane offcut archived at acceptance cannot be found and weld test records are missing, a joint inspection record is required before any destructive clearing.
- Open a localised trial pitManually clear loose protection over an area of approximately 1 m² directly over or upstream of the leak area. Avoid heavy machinery to prevent puncturing the underlying build-up. Photograph each interface before cutting.
- Take an investigation sampleTake a membrane coupon from the roof for laboratory analysis of chemical composition, residual thickness and reinforcement. Immediately install a watertight temporary seal using a compatible material.
- Record the joint inspection findings of the layersDraw up a record detailing the exact build-up sequence: substrate, vapour barrier, insulation, single-layer or two-layer waterproofing, separating layer. Note any trapped moisture in the insulation.
From a legal perspective, the limitation period for the client's rights regarding defects in an immovable work is governed by art. 371 CO. Outside the statutory or contractual warranty framework according to standard SIA 118, proving the origin of the defect without initial test records requires rigorous expert assessment. Analysis of the extracted coupon allows the original polymer to be identified against current technical data sheets and helps determine whether degradation results from chemical incompatibility beneath the ballast, poor joint workmanship or normal ageing.
Frequently asked questions
Where should the control membrane offcut taken on the construction site be kept?
The control membrane offcut, measuring at least 30 centimetres square, must be labelled with the installation date, factory batch number and exact manufacturer reference. It is kept sheltered from ultraviolet radiation and heat in the as-built documentation handed over to the client, with a duplicate filed in the technical archives of the waterproofing contractor to serve as a baseline for any future diagnostic.
What should be done if the membrane under gravel has become brittle during leak detection?
A synthetic membrane that has become rigid or brittle under gravel often indicates plasticiser migration or chemical aggression from direct contact without a separating fleece. Mechanical handling must cease, a coupon should be extracted for laboratory analysis and open flames must be avoided on an unknown substrate. Remediation requires stripping the area and installing a suitable joint according to the repair manufacturer's recommendations.
Why should weld test records be included in the as-built file?
Test records, whether from seam probe checks, vacuum bell tests, temporary water tests or smoke testing, certify the compliance of execution at handover. Should a leak arise years later, these documents prove that joints were tested according to recognised technical rules before ballast was placed.
What is the technical difference between the working drawing and the as-built drawing for a flat roof?
The working drawing shows the planned layout before the construction site begins, whereas the as-built drawing records the work exactly as built. It includes the actual alignment of expansion joints, the precise location of rainwater outlets, the position of emergency overflows and thermal insulation thickness adjustments validated during installation to compensate for structural work falls.
Texts and standards cited
- CO art. 371limitation period for the client's rights regarding defects: two years from acceptance of the work (para. 1); five years for defects in an immovable work against the contractor, architect or engineer (para. 2) and for defects in a movable work incorporated into an immovable work (para. 1); the five-year period cannot be modified to the detriment of the client (para. 3).
- norme SIA 118General conditions for construction work