Skip to content
Website
🧱 CFC 226Drainage and hydraulic safetyChapter 4 of 10 in the section

Connecting an outlet: flange, welded sleeve and surrounding insulation

This chapter details trade best practice for installing and connecting a rainwater outlet on a flat roof. You will learn how to recess the thermal insulation without creating backfalls, mechanically fasten the flange, and fully bond the waterproofing sleeve by welding to guarantee drainage without ponding water or risk of water ingress.

Key takeaways

  • The outlet constitutes the critical low point requiring systematic waterproofing reinforcement.
  • The rebate in the thermal insulation offsets the thickness of the flange without weakening the substrate.
  • The local slope shaped towards the spigot prevents any ponding around the collar.
  • The connection using a welded sleeve ensures hydraulic continuity with the multi-layer system.

Preparing the recess in the insulation and shaping the local depression

On an insulated flat roof, rainwater drainage requires strict geometry. The outlet represents the lowest point of the roof, concentrating all run-off water flows and thermomechanical stresses. The most frequent mistake on a construction site consists in laying the metal flange directly on flat insulation boards: the combined thickness of the metal, mechanical fixings and bridging strips creates an excess thickness of 5 to 8 millimetres. This excess thickness forms a permanent annular dam that blocks water and creates a standing retention zone conducive to premature ageing of the bituminous or synthetic system.

Rainwater outlets must be positioned and connected so as to ensure free flow without water ponding, incorporating a localised depression relative to the general level of the waterproofing.

norme SIA 271

To comply with the requirements of standard SIA 271, the waterproofing contractor must form a precise recess in the thermal insulation. This counterbore, cut using a handsaw or hot wire depending on the nature of the insulation (polyurethane, mineral wool or expanded polystyrene), must measure at least 50 centimetres by 50 centimetres, centred over the penetration in the slab. The depth of this recess must correspond exactly to the thickness of the outlet flange plus its reinforcements, generally between 15 and 20 millimetres at the zero point.

Recessing parameters according to thermal insulation type
Insulation materialRebating techniqueSlope of the rebateFire protection provision
Polyurethane (PIR)Thermal cutter or raspMinimum 5% towards the orificeNot applicable
EPS / XPSCalibrated hot wireMinimum 5% towards the orificeNon-combustible collar if specified
High-density rock woolCircular saw with dust extractionFactory-chamfered boardNaturally non-combustible A1

The transition between the general plane of the insulation and the bottom of the recess must be made with an even chamfer presenting a minimum local slope of 5%, thereby preventing any 90-degree angular break. If the roof features an overall designed fall of 1.5% to 2%, this local accentuation guarantees an acceleration of the water sheet towards the drainage spigot, preventing the deposition of silt and fine particles that eventually clog leaf guards.

Fastening the flange and welding the waterproofing sleeve

The body of the rainwater outlet must form a non-deformable bond with the structural deck while absorbing the differential expansion of the internal drainage pipework. The flange, whether made of copper, stainless steel, lead, or provided with a preformed collar compatible with synthetic membranes (FPO or PVC), must have a minimum bearing width of 120 to 150 millimetres all around the spigot. This dimension guarantees sufficient overlap and bonding area to absorb transverse tensile stresses.

  1. Mechanical fastening of the flangePosition the spigot into the sleeve penetrating the slab, checking the vertical alignment. Anchor the metal flange to the rigid substrate using hammer-in fixings or concrete screws distributed around the perimeter, using at least six fixings, buried beneath the future connection.
  2. Metal adhesion treatmentThoroughly degrease the metal surface with a suitable solvent. Apply a quick-drying bituminous primer to both sides of the flange if connecting a bituminous waterproofing system, in order to ensure heat-welded adhesion.
  3. Welding the reinforcing sleeveFabricate a collar from an elastomeric (SBS) or plastomeric (APP) bituminous waterproofing sheet reinforced with a polyester fleece. Torch-weld this sleeve fully bonded to the pre-primed metal flange and extend it by at least 150 millimetres onto the first main waterproofing layer.
  4. Integration of the upper waterproofing layerUnroll the cap sheet, centring the roll over the orifice. Cut a circular opening with a diameter 20 millimetres smaller than that of the spigot, chamfer the edges, and weld whilst observing a continuous bleed-out of bitumen around the entire perimeter without local overheating.

For single-ply synthetic waterproofing, the connection requires a factory-prefabricated sleeve or one fabricated from an unreinforced membrane facilitating thermoforming. Hot-air welding is carried out using a 20 or 40-millimetre flat nozzle, paying attention to the welding temperature recommended by the manufacturer and applying constant pressure with a silicone pressure roller. A systematic seam test with a blunt probe around the welded perimeter verifies the homogeneity of the joint before installing the leaf guard.

Integrating the sleeve into the main waterproofing and managing build-up thickness

Connecting an outlet collar to the main area membrane constitutes a critical zone exposed to temporary water ponding. According to standard SIA 271, the outlet forms the absolute lowest point of the gravity drainage system and must ensure continuous watertightness under the thermomechanical stresses of the roof. When the rigid flange made of SBS elastomeric bitumen or synthetic material is mechanically fastened to the substrate, the connection piece or welded sleeve must be inserted between the waterproofing layers with a strict overlap to prevent any backflow or residual ponding.

To eliminate this build-up around the drain, waterproofers systematically pare down the overlap edges over a minimum width of 100 mm using a gentle flame or hot-air gun. The prefabricated sleeve, of a diameter suited to the drainage sleeve, is first fully welded to the metal or bituminous flange. In the case of an insulated roof executed as a two-layer system, the first base layer covers the collar right up to the edge of the downward throat, before laying the top layer which seals the entire assembly with a longitudinal joint stagger of at least 150 mm.

Sleeve integration methods according to the waterproofing type
System typeSleeve arrangementMinimum overlapJoint finish
Two-layer elastomeric bitumenInterleaved between the first and second waterproofing layers150 mm around the perimeter of the flangeEven 5 mm bitumen bead extruded by flame
Single-ply synthetic membraneWelded directly on the surface onto the pre-sleeved flashing120 mm beyond the line of mechanical fixingsCheck with blunt probe and liquid seam sealant bead
Inverted roof systemLaid directly on the substrate beneath the thermal insulation150 mm with joint bridged and reinforced by waterproofing stripContinuous connection without interfering relief beneath the XPS boards

Perimeter thermal connection and installation of protective elements

The thermal insulation surrounding the outlet must neither obstruct the passage of water nor create a conductive thermal bridge through the roof slab. The formation of condensation under the metal flange constitutes one of the most frequent defects on a warm roof. In accordance with accepted technical rules, the body of the outlet must be thermally insulated or housed in a preformed rigid polyurethane or cellular glass insulating sleeve. This supplementary thermal protection guarantees continuity of thermal resistance without interrupting the local fall converging towards the orifice.

  1. Accurate cutting of insulation boardsChamfer the thermal insulation boards over a radius of 500 mm around the drainage hole to maintain the 10 to 20 mm depression, ensuring that no gap wider than 5 mm remains with the outlet shell.
  2. Installing the anti-condensation collarInsert the expanded insulating sleeve around the metal or cast iron spigot to eliminate any point thermal bridge penetrating the concrete slab or profiled steel deck.
  3. Weld inspection and water flow testCheck the thermal bonding of the sleeve-to-waterproofing seam with a blunt probe before carrying out a targeted flow test to confirm the absence of standing water ponding around the flange.
  4. Installing the leaf guard or gravel grateLock the leaf guard basket or perforated strainer into the top of the outlet to prevent floating debris and pea gravel from entering the rainwater downpipe.

The contractor remains responsible for the conformity of the completed works with the waterproofing and durability requirements of standard SIA 271. Pursuant to art. 364 CO, the contractor executes the works in person or under his personal direction. On the waterproofing construction site, this obligation entails constant monitoring of heat-welding temperatures and meticulous adjustment of the insulation to prevent the local slope from being reversed by differential settlement under future loads.

Diagnosis of connection defects and corrective actions

On a flat roof, the outlet constitutes the lowest point of water collection and concentrates mechanical and thermal stresses. When the drainage malfunctions, the defect almost systematically stems from improper recessing or defective welding of the sleeve. A flange laid directly onto the thermal board without a prior recess creates an excess thickness of 4 to 8 mm. This obstacle forms a stop threshold, transforming the drainage area into permanent ponding. According to standard SIA 271, rainwater must flow freely towards the orifice without pronounced residual standing water.

  1. Inspection and exposing the connectionRemove the leaf guard or gravel grate. Cut away the cap sheet and the welded sleeve until sound metal flange is exposed. If any circumstance compromises the regular or prompt execution of the work, the contractor notifies the client in accordance with art. 365 CO.
  2. Remediation of the bedding and chamfering the insulationRemove compressed or deformed insulation. Form a local depression at least 15 mm deep over a square area of 500 mm per side. Chamfer the edges of the insulation layer at 45 degrees to soften the transition and eliminate any reverse sump effect.
  3. Refitting the flange and reinforcement bridgingMechanically fasten the rigid collar to the bottom of the rebate. Fully weld a new bituminous or synthetic sleeve compatible with the main roofing sheet. The overlap onto the existing waterproofing must measure at least 150 mm, systematically verified using a blunt probe.

If the body of the rainwater outlet is misaligned with the internal downpipe, no forced bending of the pipework shall be tolerated. An elastomeric expansion sleeve with a stainless steel clamping band guarantees alignment without putting tension on the welded membrane.

Frequently asked questions

How can the step created by the metal flange on the insulation board be avoided?

The flange must sit in a rebate cut with a hot tool or routed into the thermal insulation board. Its upper surface must be perfectly flush with the plane of the insulation or sit slightly below it. In the absence of this recess, the rigid collar creates an excess thickness blocking water run-off, which causes permanent ponding contrary to the installation rules of standard SIA 271.

What minimum local fall must be observed in the immediate vicinity of the outlet?

Even on a flat roof deemed to be zero-pitched or with minimal fall, the convergence area surrounding the rainwater outlet must feature a local fall of at least 1.5 to 2% over a radius of 50 centimetres. This profiling is achieved using preformed tapered boards or careful shaping of the insulation, guiding the flow of water directly towards the orifice without the risk of residual puddles forming.

Why does the waterproofing sleeve sometimes debond from the metal spigot of the outlet?

This defect results from a lack of adhesion primer on the metal or chemical incompatibility between the collar and the roofing membrane. The surface of the flange must be degreased, abraded if necessary, then coated with an appropriate cold primer before torch- or hot-air welding. Without this preparation, thermal expansion movements quickly cause the sleeve to debond from its substrate.

Can the main roofing membrane be connected directly to the outlet without an intermediate sleeve?

No, this method is prohibited by Swiss trade practice. Connecting a continuous main sheet creates creases under tension and waterproofing bridges when navigating the right angle of the spigot. It is mandatory to insert a connection piece or prefabricated sleeve welded to the flange, and then to cover the latter with the chamfered and circularly cut main waterproofing layer.

Texts and standards cited

  • SIA 271Swiss standard for the waterproofing of flat roofs
  • CO art. 365Immediate notice to the client if a circumstance compromises execution of the works

In the same section