Key takeaways
- Prohibit unrestricted access by immediately marking out a walkway protected by rigid boards.
- Systematically place distribution pads beneath every scaffolding standard resting on the waterproofing build-up.
- Draw up a joint inspection record with dated photographs before opening access to other trades.
- Backcharge every puncture or tear to the identified at-fault third party after verification by site management.
Organising the walkway and protecting waterproofing beneath scaffolding
As soon as a bituminous or synthetic membrane is welded, the surface becomes the temporary working platform for other trades: window fitters, renderers, tinsmiths or photovoltaic panel installers. Leaving unprotected waterproofing accessible without control guarantees its perforation by trodden-on rubble, falling sharp tools, or ladder indentation. The flat roofer must channel these traffic flows in close coordination with site management to prohibit uncontrolled foot traffic across the build-up.
The mandatory walkway is the priority technical measure. It connects the access opening or construction site staircase to future work areas, without straying across the rest of the roof. This corridor must not rely merely on a light felt that tears underfoot or shifts with the wind. The protection must combine a cushioning layer and a rigid shield capable of distributing the dynamic loads of workers and their wheelbarrows.
| Type of traffic | Lower resilient layer | Upper distribution layer | Fixing / Jointing |
|---|---|---|---|
| Regular pedestrian traffic | Heavy non-woven geotextile (min. 300 g/m²) | Fluted polypropylene protection boards | Continuous reinforced cloth tape over joints |
| Trolley and wheelbarrow rolling loads | Recycled granular rubber mat (thickness 8 to 10 mm) | Wood-based panels, OSB 3 type (thickness 15 to 18 mm) | Tongue-and-groove jointing and perimeter ballasting |
| Scaffolding standards and shoring towers | Vulcanised rubber granule slabs (thickness 20 mm) | Timber baulks or planks, cross-section 50 x 200 mm | Mechanical bracing without puncturing the waterproofing |
Erecting standing scaffolding on a flat roof requires extreme care. Metal uprights concentrate very high point loads that can shear the membrane and crush the underlying thermal insulation. It is strictly forbidden to rest a metal screw jack or base plate directly on the waterproofing membrane, even if fitted with its original protection fleece.
The flat roofer must also eliminate unauthorised storage areas. Mortar pallets, sheet metal flashings or heavy toolboxes must not sit on the roof without a dedicated distribution platform approved by the structural engineers regarding slab load limits.
Securing the initial joint inspection record and backcharging site repairs
Before packing up equipment and removing torches or hot-air welders, the flat roofer must formalise the completion of pure waterproofing works. This step marks the legal boundary between the waterproofing contractor's liability and that of subsequent trades. If this formal milestone is neglected, any hole discovered during flood testing or after water ingress will be presumed attributable to the flat roofer at final handover under standard SIA 118.
The contractor convenes site management to draw up a joint inspection record of current conditions. This document certifies that the membrane is free from punctures, upstands on kerbs and parapets are continuously welded, and rainwater outlets are fitted with their temporary strainers. The visual inspection is supplemented by a systematic check of welds with a blunt flat screwdriver or a vacuum box.
- Prior cleaning of the surfaceCarefully sweep the entire build-up to clear rubble, metal offcuts, or leftover self-drilling screws that could conceal tears.
- Joint walk-through with site managementWalk the surface with the site manager and the client's representative to validate visible conformity and test the watertightness of joints.
- Drafting the transfer-of-custody reportRecord in writing the handover of the watertight structure with an inventory of installed temporary protections, accompanied by a complete timestamped photo record.
- Written notification of traffic rulesFormally issue to site management the ban on walking outside the demarcated route and the obligation to protect all point load supports.
Art. 365 CO para. 3 requires the contractor to inform the client immediately if any circumstance jeopardises the proper or timely execution of the works. The uncontrolled intrusion of other trades onto freshly laid waterproofing is a typical critical circumstance. Formal notice releases the contractor from liability in the event of third-party damage.
Repairs cannot be improvised with a simple bead of mastic: a tear or puncture requires the application of a welded waterproofing patch extending at least 100 to 150 mm beyond the damaged area, onto a cleaned and reactivated substrate. The cost of these remedial works, including travel, potential removal of temporary protection, and vacuum box testing, represents a substantial amount that must be fully compensated by the party responsible for the damage.
Temporary protection systems: mandatory walkways and scaffolding base pads
As soon as the waterproofing layer on a flat roof or roof terrace is completed, the membrane is exposed to mechanical damage from secondary trades. Repeated foot traffic, heavily loaded wheelbarrows, the stacking of metal profiles, or dropped sharp tools cause punctures that are often undetectable to the naked eye. The flat roofer must refuse to demobilise from the build-up without having established a robust physical protection barrier resilient to construction site conditions. The basic technical rule requires channelling worker traffic along a single, marked, and reinforced route, strictly prohibiting direct foot traffic over bare elastomeric bitumen or synthetic surfaces.
The mandatory walkway starts from the roof access point (stair opening, scaffolding ladder, or balcony door) and leads to the working areas of facade installers, blind fitters, or metalworkers. Over the bare membrane, the installation consists of a slip and heavy-duty protection layer: a high-density non-woven synthetic geotextile fleece, overlaid with rigid load-spreading boards. Moisture-resistant particle boards such as OSB 3 (minimum thickness 18 mm to 22 mm) or high-density polyethylene sheets create a continuous running surface. Board ends are joined with reinforced cloth tape to prevent grit or concrete debris from slipping under the panels.
| Nature of traffic/loading | Recommended protection system | Key site checkpoints |
|---|---|---|
| Pedestrian traffic and light tool handling | Thick non-woven geotextile (≥ 300 g/m²) + 6 to 8 mm thick recycled rubber matting strips. | Keep sheets tightly butted with no gaps; ballast against wind uplift. |
| Heavy rolling loads (wheelbarrows, manual pallet trucks) | Uncoupling mat + rigid OSB 3 boards (22 mm) or chequered steel/aluminium plates. | Chamfer leading edges to prevent mechanical snagging and secure end joints. |
| Base of standing scaffolding standards | Dense 10 mm elastomer pad + solid timber baulk (min. cross-section 50 x 200 mm) at least 50 cm long. | Check for trapped gravel beneath the rubber pad; prohibit direct metal contact. |
| Storage of facade materials or sharp tools | Triple-layer cushioning build-up: non-woven fleece, rigid timber boards, and watertight protective tarpaulin. | Immediately clear fallen screws, nails, and wire mesh scraps before they are crushed. |
Erecting scaffolding standards on a flat roof is the most frequent cause of through-punctures. A square metal base plate concentrates point loads that exceed the dynamic and static puncture resistance of the underlying thermal insulation and waterproofing. The flat roofer must demand packing beneath every standard: a sheet of pure vulcanised rubber or polyurethane-bound rubber granules of at least 10 mm thickness is inserted between the membrane and a timber distribution baulk measuring at least 500 mm in length. This assembly spreads the load over an acceptable surface and absorbs vibrations from scaffolding erection without shearing the bituminous or thermoplastic membrane.
Condition report before demobilisation and backcharging damage
Before removing equipment and demobilising their teams, the waterproofing site foreman must formalise the handover of the work to site management. As long as this departure is not recorded in a formal condition report, the contractor remains presumed liable for any damage occurring to the waterproofing envelope. This departure inspection establishes joint proof of surface conditions, upstand compliance, proper drainage towards rainwater outlets, and the overall integrity of the waterproofing system.
- Thorough cleaning and visual inspection of weldsMeticulously sweep the entire waterproofed surface, clear bitumen runs, plastic scraps, or stray screws, then check every manual and machine weld with a blunt dry probe to verify absence of delamination.
- Flood testing or smoke / tracer gas testingAccording to the specifications, carry out a 48-hour flood test or perform non-destructive testing using a vacuum box or smoke testing beneath the waterproofing.
- Joint inspection on the roofConvene site management, the main site manager, and the foremen of subsequent trades (facade fitters, tinsmiths, landscapers, edge protection installers) for a comprehensive visual examination.
- Signing the joint inspection recordDraw up a specific report recording the provisional handover of the waterproofing, the total absence of damage, and the transfer of custody of the work, supported by an exhaustive, dated, and geotagged photographic survey.
When the joint inspection record certifies that a waterproofing system was delivered free of all defects, any subsequent cuts, grinding burns, or punctures caused by a third-party trade trigger an immediate contractual process. Under art. 365 CO para. 3, if materials supplied by the client or ground designated by them are defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must immediately inform the client, on pain of bearing the consequences. As soon as damage caused by third parties is identified, the flat roofer issues a formal notice to site management with close-up photographs and marked drawings.
Remedying waterproofing damaged by third parties never falls under the flat roofer's warranty. The work requires a dedicated daywork sheet or an addendum submitted for prior approval to site management before cutting into the build-up. Curative works (cutting out the contaminated or sliced section, drying the insulation if water has entered, welding a properly dimensioned patch extending 150 mm beyond the cut, sealing laps and testing seams) are backcharged directly to site management, which will then debit the site shared cost account or the account of the contractor responsible for the damage.
Dispute management: recorded damage and backcharging remedial works
Once the flat roofer leaves the flat roof, work by secondary trades creates major puncture hazards. If damage occurs despite the presence of temporary protections, handling the defect demands a strict contractual process. The departure inspection is your only shield: without this condition report countersigned by site management, any tear discovered later will be presumed to be your workmanship defect.
- Immediate reporting of damageAs soon as damage to the waterproofing build-up is discovered (puncture by fixings, crushing beneath scaffolding standards, or tearing by a wheelbarrow), halt access to the area. Notify site management in writing within 24 hours, attaching timestamped photographs and precise marked-up drawings.
- Joint inspection of defectsDemand an on-site visit with site management and the at-fault contractor (facade fitter, tinsmith, or scaffolder). Draw up a joint inspection record detailing the nature of the damage, the missing base pads, or traffic outside the protected walkway.
- Repair and backchargingThe appointed flat roofer alone carries out the technical repair: cutting out the damaged sheet, drying out insulation where necessary, and heat-welding a waterproofing patch. Issue a specific daywork sheet or quote; remedial work is backcharged to the designated responsible party or debited directly by site management from the at-fault party's shared site cost account.
If the responsible party refuses to sign the report, formally submit your reservations to site management with reference to standard SIA 118. The waterproofing cannot be guaranteed if third-party trades walk outside the designated walkway without your written consent.
Frequently asked questions
Who bears the financial cost of installing the temporary walkway?
The supply and installation of a protected walkway must be specified in the tender description. If site management orders additional protective measures after your contractual work has finished to allow access for facade or blind fitters, this work is covered by an addendum or daywork sheets charged to the client before other trades enter the worksite.
How should one react if scaffolding standards are erected on the bare membrane?
Immediately halt work around the area and issue a written notice to site management. Insist on prompt packing using timber distribution pads at least 50 mm thick over a thick rubber protective mat. Record any onset of indentation in a joint inspection record before permitting the resumption of scaffolding erection.
What should be done if site management refuses to sign the joint inspection record before departure?
Send your full condition report that same day by registered post and secure email, including high-resolution photo sheets of each flat roof section. State that without written objection within forty-eight hours, the waterproofing is deemed delivered free of visual defects, releasing your liability regarding subsequent mechanical damage caused by other trades.
How can the repair rate for third-party punctures be justified?
Repairing waterproofing involves more than sticking on a patch: it requires moisture testing beneath the membrane, potential drying of the thermal insulation, and welding in accordance with manufacturer guidelines. Price travel, skilled labour, and materials based on your approved contractual unit prices, submitting the invoice to site management for immediate backcharging to the responsible third party.
Texts and standards cited
- CO art. 97Non-performance of obligation: the debtor is liable to make good the damage unless they prove that no fault is attributable to them.
- norme SIA 118General conditions for construction work