Upstands and special details: the execution baseline

Intended for CFC 226 team leaders, foremen, and site managers, this guide covers special details where waterproofing terminates or is interrupted. From the geometry of parapet upstands to technical penetrations, terrace thresholds, and expansion joints, it gathers the execution rules to guarantee the continuity of water barriers according to standard SIA 271.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

Norme SIA 271

150 mm

Standard minimum height of the waterproofing upstand above the level of protection or wearing course

Norme SIA 271

120 mm

Reduced minimum upstand height when special drainage measures are implemented

Norme SIA 271

500 mm

Minimum clear distance between two adjacent technical penetrations or a corner

Norme SIA 271

100 mm

Minimum downstand of the metal drip edge protecting the facade along an open edge

Technical scope and operational limits

Upstands and junctions constitute the most heavily stressed areas of a flat roof. Water infiltration almost systematically stems from a lack of adhesion at the heel, a poorly resolved thermal bridge, or unsuitable mechanical fixing at the top of the upstand. This section strictly defines the operating procedures applicable to flat roofs, balconies, terraces, and underground car park slabs executed by the waterproofer.

  • Included: bituminous, synthetic, and liquid waterproofing membrane (SEL) upstands against vertical walls and protrusions.
  • Included: treatment of flat and raised expansion joints with elastomeric waterproofing strips.
  • Included: sleeves, cable transit plates, gooseneck ducts, and post embedments.
  • Excluded: flashings and metal aprons for pitched roofs, included in the tinsmith's scope of work.
  • Excluded: internal tanking and drainage of buried walls, which fall under masonry work.
  • Excluded: thin-bed waterproofing under bathroom tiling, executed by the tiler.

Compliance with recognized good practice protects operatives and supervisors. In the event of a deliberate failure to comply with recognized technical rules that endangers the physical integrity of others, the penal sanctions of art. 229 CP apply without reservation on the construction site.

Methodical reading order for site management

To master the preparation of a waterproofing construction site, the study of execution details must follow the chronology of the structure's physical stresses, starting from the external perimeter and moving down to the complex details.

  1. 1. Roof perimeter: parapets and eavesBegin by mastering regulatory heights (G3-01), then the mechanical fixing of upstand terminations beneath termination bars and copings (G3-02), before addressing free edge trims and drip profiles (G3-10). This provides the basic framework against peeling caused by wind uplift forces.
  2. 2. Passages and access points: thresholds and terracesNext, analyse the frequent conflicts between upstand requirements and step-free access for pedestrian traffic (G3-03). This minimum thickness logic also applies to balconies and railing anchorages (G3-09).
  3. 3. Plan layout singularities: corners and existing wallsContinue with the mandatory geometric reinforcements at internal and external corners (G3-06). Then address junctions against existing facades using raglets and profiles adapted to differential settlement (G3-08).
  4. 4. Penetrations and structural movementsFinish with the most critical elements for the service life of the waterproofing system: technical services penetrations sealed with welded sleeves (G3-04), bases for lightweight or air conditioning installations (G3-07), and expansion joints with bellows capable of absorbing structural shrinkage (G3-05).

📘 Chapters in this section 10

Upstands and special detailing

Upstand height: dimension above finished level and reduction cases

Master height tolerances to prevent any refusal of acceptance during waterproofing inspections.

Upstands and special detailing

Parapet upstand: top fixing, clamping strip and coping

Secure the mechanical termination at the top to eliminate risks of wind uplift tear-off.

Upstands and special detailing

French window threshold: reconciling accessibility and upstand height

Ensure step-free access compliant with standards without compromising the watertightness of glazed doors.

Upstands and special detailing

Penetrations: sleeve, welded flange and distance between two penetrations

Successfully execute the welded flange to ensure perfect watertightness for every penetrating duct or pipe.

Upstands and special detailing

Expansion joint: upstand kerb, expansion bellows and waterproofing continuity

Install a continuous waterproofing bellow capable of absorbing structural movement without cracking.

Upstands and special detailing

Internal and external corners: prefabricated angle pieces and corner reinforcements

Fit preformed corner pieces to prevent excessive stresses in corners.

Upstands and special detailing

Securing equipment to a waterproofed roof: ballasted blocks or sealed penetrations

Select between a ballasted, unbonded pedestal or a metal bracket anchored directly into the concrete slab.

Upstands and special detailing

Upstand against an existing wall: chase, clamping profile and differential movement

Fasten raglet profiles to prevent water ingress resulting from movements in existing walls.

Upstands and special detailing

Balcony: railing anchoring, threshold and upstand in low thickness

Drain balcony run-off water and anchor railing posts without puncturing the waterproofing layer.

Upstands and special detailing

Free edge: edge trim, drip edge and façade protection

Detail drip edges and metal profiles to ensure water is shed effectively clear of the facade.