Membranes: bitumen, synthetic, laying and jointing: execution standard
Aimed at team leaders, site foremen and waterproofing site managers, this section deals exclusively with the installation of the waterproofing layer on flat roofs and terraces. It details the rigorous choice between elastomer bitumen and synthetic, overlap geometry, torch-on or hot-air welding execution, fastening methods, and the systematic inspections required by standard SIA 271.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
80 mm
Minimum longitudinal overlap for welded bituminous membrane
100 mm
Minimum end lap (transverse) for bituminous membrane
50 mm
Minimum overlap for hot-air welded synthetic membrane
80 kg/m²
Minimum surface mass of gravel (16/32 mm) for standard 50 mm ballast
2 m
Fall height requiring fall-protection measures at roof edge
Technical scope and work limits
This section brings together all Swiss codes of practice applicable to the installation of waterproofing membranes on flat roofs, terraces, balconies, and underground car park roofs. It sets out laying techniques for two-ply elastomeric bitumen (SBS) systems, single-ply bitumen, as well as thermoplastic (FPO, PVC) or elastomeric (EPDM) synthetic membranes. Jointing methods by thermal welding, bonding, or mechanical fastening are covered exclusively from the perspective of standard SIA 271 requirements.
The waterproofer's responsibility begins upon handover of the substrate (concrete, profiled steel deck, timber panels, or thermal insulation) and ends with the delivery of a watertight, protected envelope. The application of occupational safety regulations, particularly the prevention of falls from height when working near unguarded edges, is mandatory under art. 41 OTConst as soon as the fall height exceeds 2 metres.
| Membrane family | Main bonding method | Primary area of use | Sheet jointing |
|---|---|---|---|
| Elastomeric bitumen (SBS) | Fully torched or semi-independent | Trafficable terraces, inverted roofs, car parks | Torch-welding or hot bitumen |
| Flexible polyolefin (FPO/TPO) | Mechanical fastening or loose-laid ballasted | Large industrial surfaces, lightweight roofs | Automated or manual hot-air welding |
| Polyvinyl chloride (PVC-P) | Mechanical fastening or bonding | Non-accessible exposed roofs, light refurbishments | Hot-air thermal welding |
| Ethylene propylene diene monomer (EPDM) | Cold bonding or loose-laid ballasted | Green roofs, temporary stormwater retention | Splicing adhesive tape or vulcanisation |
Execution sequence: from preparation to remedial works
To ensure the durability of a waterproofing system, the laying team must approach operations in a rigorous technical order. An assembly error or the wrong choice of system leads to major failures in the thermal insulation and building structure, often undetectable before the first water test.
- Membrane selection and mechanical designDetermine the type of membrane based on roof use, exposure class, and load constraints, then calculate the fastening layout pattern to resist wind uplift.
- Jointing, welding, and destructive or non-destructive testingExecute longitudinal and transverse overlaps. Set heating temperatures, carry out the morning peel test, and inspect every centimetre of the seam using a seam probe.
- Installation of connections and detail waterproofingAdapt the laying method using bonding or ballasting depending on main areas and perimeter edges. Detail complex penetrations and upstands using a reinforced liquid waterproofing system.
- Construction site protection and corrective maintenanceProtect the surface against damage from other trades, control wheeled loads, and execute compliant repairs using bridging strips and welded waterproofing patches.
📘 Chapters in this section 10
Elastomeric bitumen or synthetic membrane: what decides the choice
Select the appropriate system for the building's load, thermal movement, and operational requirements.
Membranes: bitumen, synthetic, laying and jointingMembrane welding: lap width and seam probe inspection
Master overlap widths and the systematic technique for detecting unbonded seams.
Membranes: bitumen, synthetic, laying and jointingHot-air welding: temperature, speed and peel test
Configure the nozzle, travel speed, and verify seam strength with the daily peel test.
Membranes: bitumen, synthetic, laying and jointingMechanically fastened membrane: layout of sheets and wind uplift resistance
Distribute fastenings across perimeters and central zones to counteract wind uplift pressures.
Membranes: bitumen, synthetic, laying and jointingBonded waterproofing: primer, flash-off time and adhesion achieved
Prevent debonding by checking solvent evaporation and proper saturation of bonding primers.
Membranes: bitumen, synthetic, laying and jointingLoose-laid ballasted systems: ballast mass, grading and perimeter zones
Calculate the gravel ballast required to stabilise the system without overloading the structure.
Membranes: bitumen, synthetic, laying and jointingLaying in cold or damp weather: limit temperatures and morning dew
Anticipate the dew point and ensure safe preheating of substrates at sub-zero temperatures.
Membranes: bitumen, synthetic, laying and jointingLiquid waterproofing: reinforcement, thickness and critical detailing points
Seamlessly terminate inaccessible upstands and through-pipes using reinforced resin.
Membranes: bitumen, synthetic, laying and jointingProtecting the membrane from other trades: traffic, scaffolding and tools
Install temporary protection walkways to safeguard the waterproofing against damage by other trades.
Membranes: bitumen, synthetic, laying and jointingRepairing a membrane: substrate preparation, patch, and durable weld
Decontaminate the aged substrate and apply chamfered reinforcement patches for a fully watertight repair.