Key takeaways
- The written hot work permit defines responsibilities and instructions before lighting the first burner.
- Direct flame is strictly prohibited on unprotected combustible insulation and timber details.
- Each welding station requires two checked fire extinguishers directly accessible within arm's reach.
- The post-extinction surveillance watch is mandatory for several hours using a calibrated thermal imaging camera.
Formalising the hot work permit and demarcating prohibited-flame zones
Working with a naked flame to weld bituminous membranes on a flat roof is one of the most critical operations for a waterproofer. Heat transferred by conduction or radiation rarely causes an immediate visible outbreak of fire: it initiates slow pyrolysis within the thermal insulation or lightweight load-bearing elements. Smouldering, flameless combustion can thus linger for several hours within the depth of the thermal insulation build-up before erupting into a fully developed fire, often after teams have left the construction site.
According to art. 82 LAA, to prevent occupational accidents and diseases, the employer shall take all measures shown by experience to be necessary, applicable according to the state of the art, and adapted to the given conditions. In the context of waterproofing flat roofs, risk assessment requires drawing a strict line between substrates compatible with a blowtorch and zones where a naked flame presents an unacceptable hazard to the structure.
| Configuration or substrate encountered | Thermal risk level | Technical application specification |
|---|---|---|
| Expanded polystyrene (EPS) or extruded polystyrene (XPS) insulation | Critical (melting, flammable vapours) | Naked flame prohibited: self-adhesive application or mineral thermal shield |
| Bare or non-heavy-fleece-backed polyurethane (PIR/PUR) insulation | High (smouldering combustion beneath the facing) | Mandatory self-adhesive underlayer or prior mechanical fastening |
| Timber upstand, boarding, upstand on wood-based panels | High (propagation into assembly joints) | Flame prohibited: self-adhesive waterproofing, liquid resin, or hot air |
| Roof penetration (PVC sleeve, composite upstand rooflight) | Moderate to high (plastic deformation, ignition) | Protection with non-combustible flashing or controlled hot-air welding |
| Reinforced concrete slab with class A1 mineral wool insulation | Low (non-combustible on underside) | Blowtorch welding permitted according to good practice |
The waterproofer must resist the knee-jerk reaction of using a blowtorch on detailing zones. When waterproofing upstands encounter rooflight curbs, service duct penetrations, or roof edges containing timber packers, the use of a direct flame creates a dangerous thermal bridge into the building's interior. For these delicate junctions, the use of self-adhesive bituminous strips, solvent-free liquid waterproofing systems, or adjustable hot-air torches ensures full adhesion without excessive heat input.
Stationing fire extinguishers and conducting thermal monitoring watches
Managing extinguishing equipment tolerates no improvisation. A fire extinguisher left at the foot of the scaffolding or locked inside the construction site welfare unit is completely useless when a fire starts on the waterproofing build-up. VKF fire protection regulations and industry safety rules require first-response equipment to be stationed directly at the work location, as close as possible to the propane gas cylinders and the unrolling area for membranes.
- At least two operational fire extinguishers per welding team: a water spray extinguisher with additive (minimum 6 litres or 9 litres) to cool substrates and penetrate insulation, and an ABC multi-purpose dry powder extinguisher (minimum 6 kg) to immediately control a gas fire or pressurised equipment fire.
- Clear location less than 5 metres from the active workstation, on a stable area, away from the path of flames and connecting hoses.
- Fire blanket unfolded or immediately accessible to smother an outbreak of fire on work clothing or at a detailing point.
- Daily visual check of pressure gauges and verification of the mandatory annual inspection sticker.
Extinguishing the last burner never marks the end of fire risk. The thermal gradient accumulated in the bituminous waterproofing layers and adjacent insulation boards can continue to feed internal pyrolysis over a prolonged period. Any deliberate departure from surveillance rules incurs professional liability and is assessed under art. 229 CP, which penalises the violation of the rules of the art of building endangering the life or physical integrity of persons.
- Fluid shut-off and initial visual checkClose gas cylinder valves, bleed the blowtorch supply hoses, and secure equipment away from hot zones as soon as welding ceases.
- Immediate watch using infrared thermographyScan the entire treated surface and upstands with a thermal imaging camera. Identify temperature anomalies exceeding 60 °C on insulation and penetrations.
- Intermediate on-site surveillanceMaintain an active presence on the roof for at least 2 to 3 hours after the last flame application. Check for the absence of burning smells, suspicious smoke, or abnormal blistering.
- Final check and standing down the watchPerform a final comprehensive thermal scan before definitively leaving the construction site. Sign off the hot work permit with the surveillance end time and record the measured temperatures.
Neutralising smouldering fires: flame prohibition and cold bridging
On a flat roof, accidental overheating of combustible thermal insulation such as expanded polystyrene or polyurethane produces no immediate visible flames. Thermal degradation often begins deep down through slow pyrolysis, driven by air drafts caused by residual voids between boards or along curbs. A pocket of incandescence can smoulder without releasing large amounts of smoke for two to four hours before external oxygen supply or a breach in a joint triggers a fully developed roof fire.
To prevent this insidious phenomenon, the employer shall take appropriate technical measures in accordance with art. 82 LAA, identifying zones where the use of a gas blowtorch poses an unacceptable risk of igniting underlying layers. Timber structures, upstands on lightweight framing, plastic pipe penetrations, and waterproofing crossings must mandatorily be detailed using flame-free bridging methods.
| Work area on flat roof | Thermal or structural substrate | Prescribed method (flame-free) | Critical loss risk |
|---|---|---|---|
| Upstand on timber parapet or box gutter | OSB boards, plywood, timber boarding | Cold-applied self-adhesive angle strip | Ember transfer into the ventilated cavity |
| Ventilation penetration or conduit | PVC pipe, PE sleeve, cable duct | Bonded prefabricated collar or hot air | Immediate melting and internal fire breakout |
| Insulation layer of bare EPS or PUR | Cellular plastic insulation | Flame-free activated adhesive underlayer | Insulation melting creating a flammable void |
| Eaves, verges, and movement joints | Edge profiles, metal flashing strips | Hot-air torch welding or cold-applied bitumen | Thermal flue effect channelling heat |
Organisation of extinguishing equipment and instrumented thermal watch procedure
Performing hot work requires an immediately operational extinguishing system less than five metres from the workstation. The waterproofing team must permanently have a portable water spray extinguisher with additive of at least six litres capacity or an ABC multi-purpose powder extinguisher of at least six kilograms, accompanied by a fire blanket to smother outbreaks on work clothes or adhesive tins. Art. 3 OPA requires employers to adapt these protective measures to the specific risks generated by thermal equipment.
- Station shut-down and securing fluidsClose propane gas cylinder valves, bleed high-pressure flexible hoses by pulling the blowtorch trigger, then disconnect the pressure regulators. Store cylinders upright, secured, and outside traffic routes.
- Immediate initial thermal scanCarry out an initial surface inspection using an infrared thermometer or thermal camera over all recent welds, parapet junctions, and upstand bases executed during the last hour.
- Staggered intermediate watchesVisually and thermally inspect the build-up at regular intervals. Check for the absence of persistent burnt bitumen smells, abnormal membrane wrinkling, or suspicious discolouration of adjacent timber substrates.
- Tactile probing and verificationAt the slightest temperature difference exceeding 15 degrees compared to ambient surface temperature, locally open the weld using a safety knife to inspect the condition of the insulation and thoroughly soak any residual hot spot.
- Joint sign-off of the hot work permitAfter the complete expiry of the minimum two-hour watch period, record the measured temperatures, sign the hot work permit with the team leader and the site management representative, then authorise departure from the construction site.
Managing thermal incidents and emergency measures on a flat roof
Detecting a thermal anomaly or smoke emission following blowtorch use requires an immediate halt to all work. A flat roof fire smoulders without visible flames inside combustible polyurethane or polystyrene insulation boards, migrating beneath the bituminous membrane along parapets or roof penetrations. As soon as an abnormal rise in temperature is detected, the team implements an emergency stop: closing propane cylinder valves, moving cylinders immediately away from the threatened sector, and deploying first-intervention equipment.
- Emergency services call-out and evacuationCall 118 without delay, specifying the roof access point, the presence of pressurised gas cylinders, and the nature of the combustible insulation. Evacuate non-essential personnel to safe zones.
- Targeted attack at the workstationImmediately deploy the two stationed fire extinguishers (water spray with additive or ABC powder) located within ten metres. Aim at the base of the flames with short bursts without scattering incandescent debris.
- Surgical opening of the build-upIf the fire is smouldering under the bitumen without open flames, cut open the bituminous waterproofing sheet around the hot zone with a roofing knife. Drench the underlying insulation with water to break the internal pyrolysis.
- Site securing and preservationAfter extinction, maintain continuous surveillance for several hours. Prohibit any unnecessary foot traffic across the area in order to record the facts accurately in the construction site safety log.
The incident must be reported to the site manager and recorded on the written hot work permit. Under criminal law, pursuant to art. 229 CP, anyone who, in directing or executing a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; if through negligence, to a custodial sentence not exceeding three years or a monetary penalty. Expert analysis will determine whether the absence of a watch or working in a prohibited zone constitutes a culpable breach.
Frequently asked questions
Can welding begin if the hot work permit is not signed on the construction site?
No. The written hot work permit must imperatively be endorsed by site management and the waterproofing supervisor before lighting the burner. This document specifically defines the work location, safety distances, extinguisher positions, and post-intervention surveillance procedures. Working without this signed form directly engages the civil liability and criminal liability of the contractor in the event of an incident.
Why complement dry powder extinguishers with water-plus-additive units?
ABC dry powder knocks down an open gas or bitumen flame very quickly, but it does not cool the bulk of the insulation. A water spray extinguisher with additive penetrates mineral fibres or melting synthetic foam, dropping the temperature below the auto-ignition point. Having both extinguishing agents at the welding station guarantees surface knock-down and the drenching of smouldering fires.
How should upstands be waterproofed in zones where flames are prohibited?
On timber curbs, bare combustible insulation, rooflight penetrations, or movement joints, blowtorch use is strictly prohibited. The waterproofer must install cold-applied self-adhesive sheets or apply flame-free liquid waterproofing resins. Alternatively, electric hot-air welding without an open flame is implemented while maintaining clearance distances from flammable materials.
What must be done if the thermal imaging camera detects a zone above 60 °C during the watch?
Such a reading two hours after extinction indicates abnormal thermal accumulation or a smouldering fire in the insulation board. The waterproofing membrane must be slit open immediately with a utility knife over the suspect area, the condition of the insulation substrate checked, the residual hot spot thoroughly drenched with water, and the thermal watch cycle restarted for an additional two hours until it returns completely to ambient temperature.
Texts and standards cited
- CP art. 229violation of the rules of the art of building: anyone who, in directing or executing a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; if through negligence, to a custodial sentence not exceeding three years or a monetary penalty.