Skip to content
Website
🧱 CFC 226Drainage and hydraulic safetyChapter 1 of 10 in the section

Outlets: how many, where to place them and why never just one

This chapter details gravity drainage requirements on a flat roof according to Swiss trade rules. You will learn how to determine the minimum number of drainage points, locate outlets at the actual low point following substrate deformation, and respect the essential clearances to waterproofing upstands to ensure a watertight, durable installation.

Key takeaways

  • Every collected surface requires at least two independent drainage points or one outlet paired with an overflow.
  • A single clogged outlet turns the roof into a retention basin and dangerously overloads the structure.
  • Layout must be carried out at the actual low point of the falls following slab deflection.
  • Connecting flanges require a minimum clearance of fifty centimetres from waterproofing upstands.

Minimum number of drainage points and safety against water overloading

On a flat roof, rainwater drainage tolerates no single point of failure. If an outlet becomes blocked by an accumulation of leaves, gravel or ice, rainwater collects with no way out. In just a few hours of severe weather, the roof accumulates dozens of tonnes of water not accounted for in the civil engineer's load assumptions. This accidental ponding load causes structural deformation, increased slab deflections and, in extreme cases, total failure of the structure through mechanical collapse.

Every roof area bounded by edges or upstands must feature at least two rainwater outlets or one outlet combined with an independent emergency overflow.

norme SIA 271

Hydraulic redundancy is the governing safety principle for warm and inverted roofs. The waterproofing operative must refuse to execute a waterproofing system on an enclosed surface served by only a single gravity outlet without secondary backup. If internal downpipes connect to a collector pipe beneath the slab, emergency overflows must discharge water externally into the open air, visibly, in order to alert occupants or building maintenance staff immediately.

  • Two outlets connected to independent downpipes for each retention zone.
  • A gravity outlet paired with an overflow gargoyle penetrating the parapet wall in the event of saturation.
  • A system of emergency overflows set at an elevation above the maximum service water level.
  • Removable leaf guards with gravel grates on each sump to prevent blockage by aggregate.

Geometric layout: locating the actual low point and clearing roof edges

The theoretical position of a sump on architectural drawings does not always match actual water flow on the construction site. The installation of reinforced concrete structural elements, execution tolerances for mortar screeds laid to falls, or varying insulation thicknesses frequently produce local back-falls. The waterproofing operative must check levels with a laser level or straight edge prior to core drilling or inserting outlets. Placing an outlet five centimetres above the lowest point creates permanent ponding that damages the joints of bituminous or synthetic membranes.

  1. Level surveyCheck the bare substrate with a straight edge or rotating laser to identify the valley line and anticipated slab deflection under permanent load.
  2. Penetration and core drillingSet out the opening in the concrete at the centre of the depressed zone, taking into account the diameter of the thermal insulation collar around the downpipe.
  3. Flange recessingRebate the insulation or screed slightly so the metal or bituminous connecting flange sits recessed below the drainage plane.
  4. Waterproofing tie-inWeld or bond the flange collar with a continuous overlap of at least one hundred and fifty millimetres onto the base waterproofing ply.
Installation clearances and fitting constraints according to standard SIA 271
Adjacent structural elementMinimum required clearanceOn-site technical justification
Parapet wall or masonry upstand500 mmAllows full welding of the joint flashing without creasing the membrane sheet.
Structural work movement joint1000 mmPrevents imposing shear stresses on the body of the outlet.
Roof penetration (plinth, duct)500 mmEnsures the space needed for the torch flame or hot-air gun.
Clearance between two adjacent outlets1000 mmEnsures compact thermal insulation and avoids a continuous thermal bridge.

Edge management requires anticipating the finished height of upstands. When the slope naturally directs water towards a fire wall or an end parapet wall, the drainage sump must not create a hard point preventing the free thermal movement of the insulation build-up. The waterproofing operative coordinates with the tinsmith to install a flexible flashing ensuring seamless continuity between the angle fillet and the drainage outlet collar.

Critical clearances to upstands and collar rebate details

Positioning a rainwater outlet is not just about aiming for the lowest point of the roof plan. On the construction site, the waterproofing operative must contend with insulation thicknesses, connecting flange widths, and the girth of bituminous or synthetic upstands. Installing an outlet too close to an edge or parapet wall immediately compromises the perimeter weld of the collar. Heating tools can no longer access the seam properly, pressure rolling becomes inaccurate, and mechanical stresses at the junction of the upstand eventually shear the waterproofing build-up.

According to standard SIA 271, the centreline of the rainwater outlet must maintain sufficient clearance to allow proper execution of the flat connection. In Swiss Romand practice, the distance measured between the outer edge of the outlet flange and the foot of the waterproofing upstand must not fall below 100 mm, which generally requires a setback of at least 300 mm between the centreline of the drainpipe and the finished parapet wall. This space ensures a fully welded lap around the entire circumference of the collar and prevents material ridges that encourage ponding.

Prescribed minimum clearances around outlet bodies
Adjacent structureMinimum clearance to centrelineInstallation constraint for the waterproofing operative
Parapet wall or masonry upstand300 mmAllows flat pressure rolling of the reinforcement sheet without creasing the bituminous membrane.
Roof movement joint500 mmPrevents differential structural tensile loads transferring onto the clamping flange.
Secondary penetrations (goosenecks, plinths)300 mmEnsures access for hot-air nozzles and visual inspection of perimeter welds.
Adjacent rainwater outlet1 000 mmMaintains a distinct catchment sump without locally weakening the thermal insulation.

Recessing requires a tapered sump cut into the tapered insulation boards. The outlet flange must sit flush-recessed roughly 15 to 20 mm below the general drainage invert of the waterproofing. If the operative installs the flange directly on flat insulation without prior rebating, the overlapping plies of bitumen or synthetic material create a local lip 8 to 12 mm high. The drain then acts as a dam: water ponds in a ring around the collar instead of discharging freely into the trap.

Emergency overflows and back-falls under structural deflection

The rule banning single outlets becomes critically evident during severe storm events or autumn months when fallen leaves clog the strainer. On an enclosed flat roof with perimeter parapets, water accumulation does not just breach upstand laps: it overloads the reinforced concrete slab or profiled steel decking to the point of collapse risk. Consequently, the primary drainage system must be backed up either by a second outlet tied to an independent stack or by emergency overflows discharging freely through the façade.

To validate outlet locations and avoid this defect, the site foreman checks levels with a laser on the bare slab prior to installing the vapour control layer. If the masonry substrate exhibits clear unanticipated deflection, the contractor must fulfil their duty of inspection and notification. Pursuant to art. 365 CO, the contractor shall without delay notify the client of any defect in the ground or the load-bearing structure that compromises the regular execution of the waterproofing work, particularly where planned falls are reversed by actual deflection.

  1. Locating actual low points and survey checkCheck the floor area with a spirit level or rotating laser following rain to mark actual retention zones prior to laying screeds to falls.
  2. Cutting the insulation layer and setting the drain bodyRebate the rigid insulation to sink the sump box and its flange below the drainage plane, then mechanically fasten the outlet body to the slab to prevent any uplift.
  3. Connecting the sleeve and flangeWeld the bituminous waterproofing sheet with a compatible elastomeric or plastomeric collar, ensuring a continuous bitumen bead without creases or thermal bridging.
  4. Layout and sizing of emergency overflowsCore the parapet wall to install rectangular emergency gargoyles, set at an elevation 30 to 50 mm above the invert of the primary outlets.

Emergency gargoyles and sheet-metal overflows must be clearly offset from interior downpipes to avoid overlapping upstand reinforcement layers. The site foreman ensures that the overflow flange is fully integrated into the upstand waterproofing in accordance with standard SIA 271, discharging directly over public ground or a visible zone to provide an immediate warning in the event of abnormal water loading.

Managing drainage non-conformities and remedial actions on the construction site

On the construction site, discovering a misplaced penetration or an unbacked single outlet requires an immediate halt to waterproofing installation. If the opening is located too close to a parapet wall or sits on a back-fall caused by actual slab deflection, the waterproofing operative must record the finding without delay.

Where the mason or tinsmith has provided only one downpipe for an enclosed surface, the risk of ponding surcharge through blockage demands action. In accordance with art. 365 CO, if any circumstance compromises the regular or timely execution of the work, the contractor shall inform the client. The notice of defects must demand either the addition of an independent second outlet or an edge overflow slot cut through the parapet wall.

  1. Laser level surveyMeasure the actual low point after striking props to map the final depression caused by concrete deflection.
  2. Formal written notificationIssue a report to the lead designer highlighting the discrepancy between the theoretical core location and the requirement for two drainage points under standard SIA 271.
  3. Remediation of fallsRectify discrepancies using levelling compound or tapered insulation boards to direct water toward the revised outlet points.
  4. Execution of an emergency overflowForm a free-discharge slot through the façade if no secondary interior vertical connection is technically feasible.

The cost of additional core drilling and waterproofing remediation ranges from 600 to 1200 CHF per drainage point depending on the diameter and slab thickness—a negligible amount compared to the consequences of a roof collapse under ponded water loads.

Frequently asked questions

What should be done if the core drilling through the concrete slab is less than 30 cm from the parapet wall?

The installation of the outlet along this axis must be refused. Connect an offset flange or demand a new core drilling while filling the old hole with non-shrink mortar. Standard SIA 271 requires sufficient clearance to weld the collar and dress the reinforcement plies without creasing the membrane against the upstand. An outlet abutting the curb prevents a proper mechanical seal at the junction.

Does a 15 m² terrace without a raised parapet wall still require two outlets?

If water can shed freely over external edges without risk of ingress into the building, a single downpipe may suffice to convey normal runoff. Conversely, as soon as the terrace is bounded by a waterproof upstand forming an enclosed catchment, standard SIA 271 mandates at least two independent rainwater outlets, or one outlet combined with an overflow slot or gargoyle through the low wall.

How can an actual low point that no longer coincides with the planned outlet be rectified?

Deflection under load frequently produces a low point at mid-span. The fall profile must be corrected prior to waterproofing by installing pre-cut tapered insulation or a compatible screed to falls. If the deviation produces standing water several centimetres deep, the structural engineer and the waterproofing operative must reposition the outlet at the geometric centre of the observed deflection on the struck slab.

Can two rainwater outlets be connected to the same downpipe?

No, each outlet must operate independently. If the single vertical downpipe becomes blocked or freezes, both roof depressions flood simultaneously, defeating the hydraulic redundancy required by professional trade rules. Emergency overflows must discharge freely to the outside and must never be connected into the interior rainwater drainage network.

Texts and standards cited

  • SIA 271Flat roof waterproofing: minimum number of outlets, hydraulic safety and connections at low points
  • CO art. 365materials and site conditions: the contractor is liable for the sound quality of the materials they supply; if the materials supplied by the client or the site designated by the client are found to be defective, or if any other circumstance compromises the regular or timely execution of the work, the contractor shall immediately give notice to the client, failing which they shall bear the consequences (para. 3)

In the same section