Key takeaways
- Lay insulation boards with their length perpendicular to the ribs of the profiled steel sheet.
- Comply with the maximum permissible span of the boards to eliminate any risk of deflection under load.
- Calculate the fixing with an effective length protruding through the upper crown by at least twenty millimetres.
- Strictly distribute traffic loads during the works using timber walkway decking.
Laying direction of insulation boards and permissible span across steel deck crowns
On a flat roof supported by profiled steel sheeting, the orientation of the insulation board dictates its immediate mechanical strength. Rigid thermal insulation boards (high-density stone wool, polyurethane, or expanded polystyrene) must imperatively be laid with their long side perpendicular to the direction of the ribs. This arrangement ensures that each element rests on multiple rib crowns (the upper flanges), reducing cantilevering. The longitudinal joints of the boards must systematically coincide with the continuous centreline of a solid upper crown. A joint positioned over a rib valley creates an instant shear failure zone under the load of a roofer or the impact of an imposed load.
- Permissible span of the insulation
- Maximum clear distance between two successive upper crowns of the steel deck that a rigid insulation board can bridge without undergoing excessive deflection under live load or point loading.
The permissible span depends directly on the nature of the insulation, its density, and its nominal thickness. On trapezoidal profiles common in French-speaking Switzerland, the top opening of the valley can vary from 70 mm to more than 130 mm. If the opening exceeds the technical limit certified by the insulation manufacturer for a given thickness, the board risks snapping cleanly upon installation. For thin first-layer insulation or levelling boards, an excessive rib opening requires either an increase in insulation thickness or the interposition of load-spreading timber decking or an appropriate composite deck before installing the vapour control layer.
| Insulation board type | Minimum thickness required | Maximum permissible rib opening | Installation precautions |
|---|---|---|---|
| Mineral wool (high density) | 60 mm | 80 mm | Transverse joints staggered by at least 200 mm |
| Mineral wool (dual density) | 80 mm | 130 mm | Dense face must face upwards |
| Polyurethane (PIR) with foil facing | 40 mm | 90 mm | Tongue-and-groove joint recommended |
| Polyurethane (PIR) with foil facing | 60 mm | 140 mm | Secured span for standard single-layer installation |
| Expanded polystyrene (rigid EPS) | 80 mm | 100 mm | Square edges tightly butted, strict deflection control |
Calculation of effective fixing length and deck protection during site traffic
The mechanical fixing of the insulation and membrane assembly into a steel deck requires anchoring exclusively into the crown of the corrugation (the upper flange). Fixing into the valley of the rib is strictly prohibited, as this is where potential condensation accumulates and where the risk of pull-out due to lever action is highest. The roofer uses self-drilling screws adapted to the steel gauge (generally 0.75 mm to 1.25 mm thick), combined with square stress plates or plastic tubes to break the thermal bridge. These fixings must comply with recognised technical rules to prevent structural failures, as recalled by the Swiss Criminal Code in art. 229 CP regarding compliance with the recognised rules of the art in the management and execution of a work.
Calculating the length of the self-drilling screw or sleeve system requires millimetric precision. To fix a compressible or rigid board, the total length includes: the actual thickness of the insulation build-up under mechanical settlement, the thickness of the waterproofing membrane, the thickness of the vapour control layer, and the mandatory minimum protrusion of 20 mm below the underside of the profiled steel sheet. This safety margin ensures that the load-bearing thread fully protrudes through the drilled hole and locks the fastener against back-out caused by mechanical vibrations and cyclic wind uplift effects. An undersized screw results in partial engagement that tears through the sheet metal at the first storm; an excessively long screw risks puncturing building services suspended beneath the deck.
- Checking the bearing crownsMark the exact longitudinal centreline of the sheet's upper crowns with a chalk line before laying the insulation build-up to avoid blind drilling into valleys.
- Validating the build-upMeasure the actual cumulative thickness of the system (insulation + membrane) and select appropriate thermally broken tubes to limit the metal length of the screw.
- Setting the torque limiterUse a roofing screw gun fitted with a depth stop or torque limiter to seat the stress plate without crushing or cracking the cellular structure of the thermal insulation.
- Checking thread engagement beneath the sheetCheck visually from the underside of the building that no drill bit has slipped off the crown and that each screw protrudes by at least 20 mm with its active thread.
Traffic during construction represents a critical phase for the structural integrity of the works. Until the waterproofing and ballast or final fixings are completed, the steel deck substrate and insulation boards remain highly vulnerable to permanent deformation. To transport bitumen rolls, welding equipment, or personnel, temporary access tracks made of hardwood ply or OSB boards at least 15 mm thick must be deployed. Stacking material pallets at mid-span of the deck without verifying the local load-bearing capacity of the sheeting is strictly prohibited. The safety of personnel working on these industrial roofs is governed by art. 3 OTConst, which requires construction works to be planned so as to reduce accident risks to the lowest possible level, notably by securing routes across unwaterproofed sheeting to eliminate any risk of tripping or local failure of the insulation.
Setting out fixing lines on rib crowns
On an industrial flat roof with a profiled steel deck, the mechanical anchoring of thermal insulation tolerates no blind fixings into the rib valley. The fixing pattern must be aligned strictly over the usable width of the rib crown, referred to as the positive profile. To secure the insulation and vapour control layer against wind uplift pressures, the fixing lines must follow the longitudinal centreline of the trapezoidal profile's upper crowns.
| Build-up component | Required positioning | Spacing tolerance | Corrective action |
|---|---|---|---|
| Self-adhesive or bituminous vapour control layer | Continuous without sagging into valleys | 100 mm lap | Reinforced pressure-rolling over lap joints |
| Insulation board (PIR / EPS) | Joints perpendicular to ribs | Maximum offset of 5 mm | Trim to fit without cantilevering |
| Screw and stress plate | Dead centre of the rib crown | Maximum deviation of 10 mm | New fixing installed 50 mm away on the crown |
| Telescopic plastic tube | Perpendicular to the crown plane | Plumb deviation max 3° | Replacement if the sleeve shears |
The contractor checks the thread pitch type used based on the thickness of the metal substrate. For 0.75 mm to 1.25 mm galvanised steel sheets, fine-thread self-drilling screws provide the required pull-out resistance without stripping the tapped hole during tightening. Using a screw gun with an adjustable depth stop prevents localised crushing of the insulation board and protects the seal provided by the sealing washer or the thermally broken plastic tube.
Deck protection and organisation of installation traffic
The installation phase exposes rigid insulation laid over deck profiles to severe point loading. Heavy transport using pallet trucks or wheelbarrows over boards not yet protected by their final waterproofing causes punch-through of the insulating material over the negative valleys. To transport bitumen rolls, synthetic membranes, and fixing packs, the team sets up continuous walkways using timber load-spreading boards at least 22 mm thick.
These temporary deck boards distribute point loads across at least three consecutive ribs of the steel deck, preventing flexural failure of mineral wool or polyurethane foam boards. Pallets of materials deposited by crane must never be set down on areas where the insulation is not fully anchored to the underlying substrate.
Where building services are suspended beneath the roof by other trades (ventilation ducts, sprinklers, cable trays), roofers coordinate the elevation of metal penetrations. A screw penetrating through the profiled steel sheet with excessive effective length poses an injury hazard to installers working below or could puncture services running in close proximity to the steel.
Managing non-conformities in span, anchoring and site traffic
On a profiled steel sheet substrate, failures arise primarily from incorrect board orientation, blind fixings outside the crown, or local deformation under construction site traffic. When the thickness or nature of the insulation cannot span the crown openings according to the manufacturer's permissible span, direct installation must be stopped. Two technical solutions must be applied immediately: replacement with an insulation of higher compressive strength capable of bridging the span, or the preliminary installation of an intermediate load-spreading metal sheet secured to the steel deck.
Air drilling is the most frequent fixing defect. A self-tapping screw that misses the upper rib punctures the vapour control layer into the void without providing any wind uplift resistance. The supervisor or foreman marks these areas with paint or grease chalk. Leaving an unanchored fastener is strictly prohibited. The defective screw must be extracted, the perforation in the vapour control layer sealed using a compatible adhesive collar, and a new fixing repositioned on the adjacent rib complying with the minimum effective embedment depth defined by standard SIA 118.
In the event of deck denting or rib crushing under the wheels of transport trolleys, the roofer must document the deformation. In accordance with the duty of care set out in CO, if the material supplied by the client or the site designated by them is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor shall inform the client. Finally, OTConst requires measures to be taken at workstations and traffic routes to ensure that workers are not endangered. Damaged areas must be cordoned off and protected with rigid timber load-spreading decking before any resumption of operations.
Frequently asked questions
What should be done if a screw passes through the deck into the void beside the rib?
The screw must be backed out immediately. The puncture in the insulation and vapour control layer creates an air and vapour leakage path. Seal the hole using an airtight mastic or self-adhesive patching piece. Then install a new self-tapping screw with its stress plate dead centre on the crown of the rib, at a minimum distance of 50 mm from the previous hole.
What should be done if the span between ribs exceeds the permissible thickness of the insulation?
Never attempt to lay the insulation in an unapproved cantilever. You must either double the first layer with an intermediate rigid board capable of spanning the rib profile, or install a thicker composite steel deck. Report the discrepancy to the site management to approve the modification of the thermal build-up and the appropriate lengths for additional mechanical fasteners.
What is the required effective fixing length beneath the profiled steel sheet?
The screw must fully penetrate the steel sheet. To ensure full mechanical engagement of the self-tapping thread, the screw tip must protrude 15 to 20 mm beneath the underside of the rib profile. This extra length guarantees the specified pull-out resistance against wind uplift suction, taking into account manufacturing tolerances of the insulation.
How can heavy traffic on the deck be organised without deforming the ribs?
Pallet trucks or trolleys must never roll directly over unprotected insulation or bare ribs. Dedicated traffic routes must be formed using rigid load-spreading boards, such as OSB or plywood at least 22 mm thick. These boards distribute point loads across at least three consecutive ribs, preventing localised bucking of the substrate.
Texts and standards cited
- norme SIA 118General conditions for construction works
- COMaterials and site: immediate notice to the client in case of defects or circumstances jeopardising the work (para. 3)
- OTConstProtection against structural collapse or falling objects and materials