Key takeaways
- The continuous capillary barrier beneath the sole plate prevents any rising damp from the concrete.
- The sole plate anchor centres are calibrated according to the anchoring layout plan provided by the timber engineer.
- The substrate-specific anchoring ensures resin bonding in cracked or uncracked concrete.
- The pull-out verification test on the threaded rod confirms effective holding capacity before timber-frame erection.
Installing the capillary barrier and tailoring the chemical anchor to the concrete
The contact zone between masonry and timber represents a critical area for the durability of the structure. The blinding concrete, slab or wall head transmits moisture from the ground or residual construction water through capillary action. Placing a sole plate directly onto bare concrete causes water entrapment, rapid rotting of the lower fibres and the mechanical failure of the bearing base. Installing a capillary barrier is the first non-negotiable step before marking out any final setting-out lines.
- Capillary barrier
- Bituminous waterproofing membrane or waterproof synthetic strip installed continuously between the concrete upstand and the underside of the timber sole plate, preventing liquid moisture transfer via capillary action.
The membrane must project on either side of the timber piece to ensure that subsequent screed or levelling compound spillages do not bridge the hygric barrier. A flexible closed-cell air-sealing strip is often combined with it to compensate for micro-roughness in the concrete upstand. If local irregularities exceed the tolerances permitted by standard SIA 118, a non-shrink bedding mortar must be screeded beforehand.
For fixing, a chemically anchored threaded rod is preferred over mechanical expansion anchors when anchoring close to slab edges. Chemical anchoring exerts no mechanical expansion stress in the concrete, preventing edge breakout. The choice of resin depends on the substrate condition: pure epoxy resin for heavy loads and core-drilled holes, or styrene-free vinylester resin for rapid curing in cracked or damp concrete.
| Cartridge type | Performance in damp concrete | Permissible loading time | Preferred application on the construction site |
|---|---|---|---|
| Two-component vinylester | Good adhesion on cleaned concrete | Fast (approximately 30 to 45 minutes) | Standard installation under timber framing |
| Pure epoxy | Excellent performance in saturated environments | Slow (curing over several hours) | Large-diameter rods or starter bars |
| Standard polyester | Reduced adhesion in the presence of water | Medium | Prohibited under external sole plates |
Controlling fixing centres and validating strength via pull-out testing
The transfer of horizontal wind loads, seismic forces and timber-frame uplift relies entirely on the anchoring of the sole plate. The timber engineer determines the diameter of the zinc-plated or stainless steel threaded rods (commonly grade 8.8) as well as the thick, wide bearing washers that prevent cross-grain timber crushing during torque tightening.
The sole plate anchor centres vary according to structural loads. They are commonly between 80 and 120 centimetres in intermediate sections, but must strictly be reduced at wall ends and on either side of openings, with a first fixing located close to the end of the timber piece (typically 10 to 15 centimetres). If the masonry has defects or if the ground is unstable, the carpenter applies the rules of prudence.
Pursuant to art. 365 al. 3 CO, if the material supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor shall immediately inform the client thereof, on pain of bearing the consequences. A slab whose surface strength crumbles or whose reinforcement is systematically struck during drilling requires this formal written notice.
- Drilling and cleaning the holeDrill to the diameter specified by the technical assessment of the anchor. Remove dust by compressed-air blowing and mechanical brushing with a suitable wire brush, repeated at least twice.
- Resin injection and rod installationPurge the initial mix until uniform. Inject from the bottom of the drill hole to two-thirds of the volume. Insert the threaded rod with a slight twisting motion until a regular, slight outflow of resin is achieved.
- Controlled tightening after curingObserve the curing time relative to ambient temperature. Fit the wide timber washer and tighten the nut with a torque wrench according to the manufacturer's target value.
- Pull-out verification testVerify holding capacity through direct tensile testing on a representative sample using a hydraulic anchor tester fitted with a calibrated pressure gauge, without exceeding the yield point of the steel.
The pull-out verification test validates the performance of the chemical anchor under pure axial tension. On site, the tester bears against the concrete around the threaded rod without creating a restrictive cone effect. The test report records the proof load achieved, load retention for a specified duration, and the absence of visible slippage. Costs relating to these pull-out testing campaigns range from 600 to 1500 CHF depending on the number of test points, an amount to be factored in from the initial quotation.
Installation of threaded rods and reliability of chemical anchoring
The interface between the foundation concrete and the timber sole plate forms a critical zone for load transfer and exposure to residual moisture. To ensure mechanical anchoring without splitting the timber or cracking the mineral substrate, the installation of threaded rods demands absolute rigour during drilling, cleaning and injection of the anchoring resin.
- Setting out and concrete drillingMark out anchor centres on the raft or slab according to the sole plate alignment. Drill with a rotary hammer drill to the diameter specified in the resin's technical assessment, perpendicular to the bearing surface, avoiding perimeter reinforcement bars.
- Drilling dust extractionBlow out the hole with a compressor or hand pump, scrub the walls with a wire brush matched to the diameter, then blow out again. Repeat the operation twice to eliminate any concrete dust that could prevent adhesion of the anchoring mortar.
- Injection of chemical mortarDiscard the initial dispenses from the static mixer until a homogeneous colour is obtained. Inject the resin from the bottom of the drill hole, withdrawing the nozzle to fill approximately two-thirds of the volume without forming air voids.
- Rod insertion and curingInsert the galvanised or stainless steel threaded rod using a slight twisting movement down to the bottom of the hole. Allow to cure in accordance with the technical data sheet without touching or loading the component during setting.
| Resin type | Indicative curing time | Performance in damp concrete | Main application |
|---|---|---|---|
| Pure epoxy | 12 to 24 hours at 20 °C | Very good adhesion on wet substrates | Heavy load transfer and deep drill holes |
| Styrene-free vinylester | 45 to 90 minutes at 20 °C | Good performance in damp drilled concrete | Standard construction sites with fast assembly schedules |
| Hybrid polyester | 30 to 45 minutes at 20 °C | Sensitive to the presence of free water | Secondary fixings on dry concrete |
Capillary barrier installation, tightening and pull-out verification
Direct contact between alkaline concrete—inherently damp—and the timber sole plate inevitably causes decay at the base of the walls over time. Installing a continuous capillary damp-proof barrier beneath the sole plate is imperative. Bituminous or EPDM elastomer waterproofing strips must overlap on each side of the plate to direct any infiltration outwards.
- Concrete flatness check prior to installation (maximum deviation of 5 mm under a 2 m straight edge) to prevent localised capillary bridging.
- Precise punching of openings in the waterproofing strip for the passage of threaded rods, sealed with a compatible mastic.
- Fitting of wide washers of appropriate thickness (timber construction washer type according to DIN 440 or equivalent) under the nut to distribute compression without crushing the wood grain.
- Controlled tightening with a torque wrench according to the torque specified by the timber engineer to avoid cross-grain creep.
Once anchored, structural holding capacity is verified by on-site pull-out tests. This non-destructive test consists in applying an axial proof load using a hydraulic jack fitted with a calibrated pressure gauge. The test confirms that the chemical anchor withstands the working tensile load without measurable slip or concrete cone failure.
Management of anchor non-conformities and remediation on concrete slabs
On a construction site, setting-out errors or holding-capacity issues with threaded rods frequently arise during sole plate placement. Whether due to drilling into structural reinforcement, poorly cured resin from inadequate cleaning or plate misalignment, the carpenter cannot improvise makeshift packing without jeopardising the durability of the timber frame.
- Findings and notification of an aborted drill holeIf drilling strikes structural reinforcement, cutting the bar without approval from the structural engineer is prohibited. The hole must be filled with a non-shrink technical mortar. Pursuant to art. 365 CO, the contractor notifies the client if the ground or material found to be defective compromises proper execution.
- Remediation of the sole plate anchor centresA new drill hole is offset by at least three times the hole diameter to avoid the concrete breakout cone. The substrate-specific anchoring is re-injected using a new cartridge, discarding the first centimetres from the static mixer.
- Restoration of the capillary barrierAny incorrect penetration or tear in the bituminous strip or EPDM membrane beneath the sole plate must be bridged with a bonded waterproof overlap to guarantee the complete absence of rising damp into the timber.
- Adversarial pull-out verification testIf in doubt regarding chemical bonding or concrete consistency, an axial pull-out test using a hydraulic anchor tester is carried out on a representative sample of rods, and an inspection report is submitted to site management.
Any structural non-conformity engages the contractor's liability. Under art. 229 CP, whoever breaches the recognised rules of the art of building, thereby endangering life or physical integrity, is liable to criminal sanctions. Traceability of the tightening torque and verification of test results remain mandatory.
Frequently asked questions
What should be done if a threaded rod spins freely during tightening?
The rod must be removed immediately. The fault is caused by inadequate wire brushing, expired resin or unacceptable moisture. The hole must be completely cored out or a new adjacent anchor drilled, respecting edge distances and the sole plate anchor centres, followed by restoring the local integrity of the capillary barrier.
What should be done if the waterproofing strip under the sole plate is accidentally punctured?
A tear in the capillary barrier exposes the timber to rising damp through direct contact with the mineral slab. The damaged area must be trimmed cleanly and bridged with a compatible sheet overlapping by at least 100 mm on either side. A continuous bead of waterproof adhesive ensures a tight seal before final tightening of the washer and zinc-plated nut.
When does the structural engineer require on-site pull-out testing?
This check is required when concrete strength is questionable, in sub-zero temperatures during resin injection, or if drill-hole depth tolerances have not been observed. The pull-out verification test applies an axial tensile force using a calibrated jack to confirm the holding performance of the substrate-specific anchoring without steel slip.
What spacing tolerance applies to sole plate anchor centres?
The sole plate anchor centres specified on the execution drawings rarely permit a deviation exceeding 50 mm, because the studs or rods resist uplift and shear forces at the base of the frame studs. If reinforcement bars prevent drilling, the carpenter consults the timber engineering office before adding a compensatory fixing to maintain overall anchoring capacity.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the good quality of the materials supplied; if the materials supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance compromises the proper or timely execution of the work, the contractor shall immediately inform the client thereof, on pain of bearing the consequences (para. 3).
- CP art. 229breach of the rules of the art of building: whoever intentionally breaches the rules of the art while managing or executing a construction or demolition project, thereby knowingly endangering the life or physical integrity of persons, shall be liable to a custodial sentence not exceeding five years or to a monetary penalty; in cases of negligence, to a custodial sentence not exceeding three years or to a monetary penalty.