Key takeaways
- Raise timber stacks at least twenty centimetres above stabilized ground.
- Align all spacing bearers vertically to prevent warping of load-bearing components.
- Ventilate the underside and sides of the pack thoroughly beneath an overhanging top sheet.
- Limit unsheltered storage to a few weeks to preserve workshop-machined moisture content.
Above-ground blocking and stacking: preventing warping and rising damp
Unloading structural timber elements directly onto a damp concrete slab, a gravelled area, or soft soil immediately exposes the wood to moisture uptake through capillarity. Moisture from the ground migrates into the bottom fibres, causing surface mould, discoloration, and asymmetric dimensional variations. The carpenter must prepare a sound base before any crane-truck delivery.
- Warping under stress
- Three-dimensional geometric distortion of timber resulting from uneven drying or poorly supported stacking, making machined surfaces and joints unusable for assembly without rework.
Stacking requires absolute regularity in load transfer to eliminate creep and deformation in long-span components, such as purlins, glulam rafters, or post-and-beam elements. Spacing bearers must have an identical cross-section and lie in a strictly plumb vertical alignment.
- Primary blocking made of timber balks or rigid blocks raising the first layer 20 to 30 cm off the ground.
- Spacing of transverse bearers every 1.20 m to 1.50 m at most, depending on member thickness.
- Strict vertical stacking of spacing battens to avoid local bending stresses.
- Arrangement of end blocks less than 30 cm from the ends of components to prevent sagging of cantilevers.
Ventilated sheeting and storage duration: banishing the sealed greenhouse effect on the construction site
Hermetically wrapping a timber package in plastic film sealed at ground level is the worst mistake made upon delivery. Under solar radiation and ground vapour, the stack acts like a greenhouse: trapped moisture heats up, water evaporates and then condenses on cold faces, creating an ideal breeding ground for dote and wood-decay fungi in just a few days.
| Protection method | Air circulation | Risk of deterioration | Permissible duration on site |
|---|---|---|---|
| Tarpaulin sealed hermetically at ground level | None (closed greenhouse effect) | Critical (blue stain, soft rot) | Less than 48 hours |
| Canopy tarpaulin with lateral overhang | Continuous (thermal draw) | Very low (faces protected from rain) | 2 to 4 weeks |
| Original factory wrap slit on underside | Partial (drainage of trapped water) | Medium (possible pooling at knots) | 5 to 7 days |
| Storage under open, ventilated shelter | Optimal (hygrometric equilibrium) | Negligible | Up to 8 weeks |
- 1. Fit a roof-style cover sheetDeploy the waterproof protective sheet only over the top of the package, providing a pitch for run-off to prevent any pooling of stagnant water.
- 2. Keep the sides and base well clearAllow the sheet to hang down the sides without ever touching the ground, maintaining at least a 20 cm open gap at the base to initiate natural ventilation.
- 3. Ballast and secure against windFasten the cover with nailed battens or straps independent of the stack. Valley winds or plain draughts must neither tear the cover off nor press it flush against the ends of the components.
- 4. Drain condensation from factory packagingSlit transit shrink-wrap using a utility knife beneath each blocking bearer to drain any water pockets that may have collected during offloading.
Strict adherence to these provisions ensures structural timber components retain their contractual moisture equilibrium between the joinery workshop and assembly on the slab, eliminating disputes related to premature drying shrinkage splits and joint distortion.
Active stack ventilation system and elevated sheeting
The recurrent error on construction sites consists of wrapping a timber stack in heavy plastic sheeting whose skirts drop straight to the ground and are weighed down with timber or concrete blocks. This hermetic containment traps moisture rising from the soil or fresh foundation slab. Under solar radiation, the space under the sheet acts as a steamer: water contained in the air evaporates, saturates the enclosed atmosphere, and then condenses against the underside of the sheet during the night. Water droplets then drip directly onto the upper faces of timber-frame or glulam members, producing indelible stains, blue stain in softwoods, and differential swelling that compromises precision machining.
To eliminate this greenhouse phenomenon, sheeting must be designed as an external roof, independent of the stack body. Protective sheets must strictly terminate 30 cm above natural ground or the slab. This bottom clearance allows outdoor air to enter freely beneath the load, sweep the bottom faces, and escape at the top. The top of the pack receives spacing battens or tapered wedges that create a water-shedding slope towards the eaves, thus preventing stagnant rainwater pockets that eventually puncture the sheet under wind action.
- Forming the ventilation ridgePlace timber offcuts or inclined wedges along the upper longitudinal axis of the stack to form a dual pitch and elevate the sheet at least 10 cm above the top load-bearing elements.
- Tensioning and canopy fixingDeploy a reinforced vapour-permeable membrane or a woven tarpaulin that is impervious to driving rain but held open laterally with battens nailed along the edges, creating a 20 cm projecting overhang.
- Ballasting without choking airflowSecure ratchet lashing straps around the entire stack or suspend ballast at the foot of the sheet using reinforced eyelets, strictly avoiding knots that bind the base of the stack and block airflow.
Permissible on-site durations and moisture control upon installation
On a construction site in Romandy, seasonal weather swings impose strict limits on how long finished timber can remain outdoors. While rough-sawn solid timber tolerates several weeks of storage provided it is stacked on regular, ventilated bearers, engineered wood products such as finger-jointed solid timber (KVH), glulam, or cross-laminated timber (CLT) require installation within extremely short lead times. These industrial components, kiln-dried in the workshop, have a precise initial moisture content; any uncontrolled moisture uptake creates shrinkage cracking stresses, warping, or partial delamination incompatible with modern structural assembly tolerances.
| Timber family | Delivery moisture content | Max duration under ventilated sheet | Specific preservation measures |
|---|---|---|---|
| Cross-laminated timber (CLT) | 12 % ± 2 % | 1 to 2 weeks max | Flat storage, insertion of bearers aligned over supports, ventilated underside. |
| Glued-laminated timber (BSH) | 12 % ± 2 % | 2 to 3 weeks max | Cut transit shrink-wrap on the underside to drain condensation water. |
| Finger-jointed solid timber (KVH) | 15 % ± 3 % | 3 to 4 weeks max | Continuous above-ground blocking (minimum clearance 15 to 20 cm), regular spacing. |
| Rough-sawn solid timber C24 | 18 % to 20 % | 4 to 6 weeks max | Stickered stacking with battens at each row to promote drying without twisting. |
Before undertaking lifting or incorporating a component into the closed building envelope, the site foreman must carry out a systematic inspection using an insulated-pin moisture meter. Measurements are taken at the core and not at the surface, where moisture fluctuates rapidly with ambient relative humidity. If the material has experienced excessive site exposure leading to moisture uptake beyond acceptable limits for the future equilibrium state of the structure, erection must be deferred until natural stabilization under a ventilated shelter is achieved.
Managing storage damage and remediation of degraded timber
When sheeting has been laid flat to the ground or blocking has sunk into the mud, condensation water and rising damp turn the stack into a steamer. Within days, heating triggers the onset of surface mould, premature blue stain, or early wane decay on solid and glulam timbers. As soon as abnormal moisture is detected, the foreman stops all further deliveries and performs a methodical row-by-row sort.
- Removing containment and forced ventilationImmediately remove hermetic sheeting. Re-stack components by inserting blocking bearers of at least 25 mm between each tier, perfectly aligned plumb over the ground blocks to prevent differential creep. Allow air to circulate freely under temporary shelter.
- Systematic moisture measurementRecord core moisture content using an insulated-pin moisture meter on at least five members per pack. Drive the pins perpendicular to the wood grain, at mid-length and one-third of the thickness to obtain a representative value.
- Surface treatment and stabilized dryingDry-brush non-wood-decaying fungal efflorescence. If the moisture content exceeds the required tolerances for machining or assembly, store components in a ventilated shed until stabilized prior to final erection.
Even if the client has designated a flood-prone or muddy unloading zone, responsibility for proper preservation still rests with the carpenter. Pursuant to art. 365 CO, if the ground designated by the client is recognized as defective, the contractor must immediately notify the client. This written notification formalizes the refusal to store calibrated timber on unstabilized ground or ground lacking drainage gravel. In the vicinity of access roads and site plant traffic routes, art. 17 OTConst stipulates that measures must be taken at workstations and passageways to ensure workers are not endangered by the collapse of building components or falling objects and materials. The blocking of timber bundles must ensure absolute stability under west winds or during craning manoeuvres.
Frequently asked questions
What should be done if surface mould appears on freshly unpacked glulam?
Immediately remove the airtight plastic transit wrap. Clean off the mould using a stiff, non-metallic brush without soaking the wood with water. Measure surface and core moisture using a professional moisture meter. Position clean, dry intermediate bearers to restore a continuous air gap of at least 20 mm between members. Protect the stack with a breathable sheet elevated above the ground.
What minimum ground clearance must be maintained beneath storage bearers?
On a stabilized site platform or concrete slab, provide primary blocking at least 150 mm above ground level. On soft or grass-covered ground, increase this height to a minimum of 300 mm to prevent mud splatters and capillary absorption of standing water. Spreader balks must rest on sound, cleared, and levelled ground, away from surface run-off paths.
How long can machined structural timber be stored on site under sheeting?
The duration should not exceed two to three weeks under ventilated, non-hermetic protection. Beyond this, hygrothermal variations cause geometric distortion, bow, or drying shrinkage splits detrimental to joints. If the erection schedule is deferred for several months, return engineered timber to an enclosed store or construct a rigid temporary roof that allows ambient air circulation.
How do you properly sheet a stack without generating condensation?
Fasten the protective cover only over the top face and draped partially down the sides as an overhanging canopy. Keep the bottom edges and both ends of the stack open by at least 200 mm to promote natural thermal draw. Never seal the undersides hermetically at ground level, as ground-source moisture would collect directly inside the core of the pack.
Texts and standards cited
- CO art. art. 365 COmaterials and ground: the contractor is liable for the sound quality of the material they provide; if the material provided by the client or the ground designated by them is recognized as defective, or if any other circumstance jeopardizes the regular or timely execution of the work, the contractor must immediately notify the client, under penalty of bearing the consequences (para. 3).
- OTConst art. art. 17 OTConstprotection against collapse of building components or falling objects and materials: at workstations and passageways, measures must be taken to ensure workers are not endangered.