Key takeaways
- Standard SIA 414 allows centimetre-level deviations that are incompatible with the millimetric tolerances of CLT.
- The three-dimensional survey of the raw concrete must imperatively precede the start of CNC cutting.
- A nominal installation gap of at least 20 millimetres absorbs wall verticality defects.
- The metal assembly detail must allow structural shimming without blocking crane erection.
Confronting standard SIA 414 and CNC timber machining
On recent Swiss construction sites, combining an in-situ cast central concrete core with a perimeter structure of cross-laminated timber (CLT) panels is common. However, this structural choice brings together two execution cultures with diverging physical limits. On the one hand, the CNC machining centre cuts the CLT panels with an accuracy in the range of 1 to 2 millimetres. On the other hand, concrete structural work applies dimensional tolerances governed by standard SIA 414, where allowable setting-out, verticality, and straightness deviations are measured in centimetres.
| Geometric parameter | Concrete structural work (standard SIA 414) | CNC-cut CLT panel |
|---|---|---|
| Ground setting-out | ± 10 to ± 15 mm depending on span | ± 2 mm |
| Verticality over one storey (3 m) | ± 10 to ± 12 mm | ± 2 mm |
| Face straightness / flatness | ± 8 to ± 10 mm under a 2 m straightedge | ± 1 mm per linear metre |
| Block-out / rebate | ± 15 to ± 20 mm | ± 1 mm |
Attempting to fit a rigid timber panel directly against a concrete shear wall without anticipating these discrepancies inevitably leads to a blockage during lifting. A formwork bulge of 15 millimetres or an out-of-plumb deviation accumulated over two storeys prevents the CLT slab from being lowered into place or skews the alignment of the timber façades upstream. The obligation to check the compatibility of the supporting structures rests with the carpenter before any intervention.
If the material supplied by the client or the site designated by him is found to be defective, or if any other circumstance compromises the regular or punctual execution of the work, the contractor shall immediately inform the client, under penalty of bearing the consequences (para. 3).
art. 365 CO
As-built core survey and shimming systems on the construction site
To eliminate geometric deviations, incorporating the as-built survey into the production flow is the only reliable method. As soon as the staircase core is completely stripped of formwork and the datum line is struck by the masons, the carpentry foreman or a surveyor conducts a three-dimensional survey of the concrete. Using a total station or a laser scanner enables capturing actual edges, local bulges, and the exact altimetry of corbels or bearing recesses.
- 1. Checking the datum line and traverse networkVerification of the primary building gridlines and calibration of the instrument against official benchmark points transferred onto the concrete wall.
- 2. Scanning of bearing facesCapturing the actual face of the wall and connection zones (starter bars, embedded steel sections, load-bearing angle brackets).
- 3. Comparison with the CAD/CAM modelImporting the point cloud or actual polygons into the timber framing software to measure deviations relative to the theoretical model.
- 4. Adjusting machining filesAdapting CLT machining operations (edge cuts, drillings for dowels or coach screws) prior to transmission to the machining centre.
Tolerance absorption relies on a nominal clearance calculated right from the design of the metal fittings. In practice, a service gap of 20 to 30 millimetres is provided between the edge of the CLT panel and the concrete wall. Vertical loads are transferred via continuous angle irons fixed using approved mechanical or chemical anchors, or via recessed steel brackets. Rigid steel shimming plates of graduated thicknesses (2, 5, 10 millimetres) or non-deformable synthetic shims allow altimetry and finished floor levels to be adjusted.
Geometric confrontation: CNC machining versus raw concrete
On a timber construction site, connecting a cross-laminated timber (CLT) floor or wall panel against a reinforced concrete stairwell or lift shaft is a critical juncture from 3D modelling to erection. On the one hand, the CNC machining centre cuts panels in the factory to an accuracy of roughly 1 to 2 mm. On the other hand, the masonry structure formed and cast on site falls within the dimensional tolerances of structural work governed by standard SIA 414. This inherent divergence leads to systematic spatial conflicts if the interface is not anticipated right from the execution phase.
The gap between timber and concrete tolerances appears in three primary forms: out-of-plumb deviations of the cast wall, local surface flatness defects under the straightedge, and overall setting-out drift across the various slab levels. When the carpenter attempts to install a perfectly square CLT panel against a wall that leans 15 mm inward, the panel binds prematurely, shifting the building gridline and misaligning the subsequent bays of the structure.
| Geometric parameter | CNC-machined CLT element | Concrete core (standard SIA 414) |
|---|---|---|
| Cutting / dimensional tolerance | ±1 to ±2 mm | ±10 to ±15 mm |
| Verticality tolerance over one storey | Not applicable (rigid panel) | ±10 to ±20 mm depending on height |
| Local surface flatness | ±1 mm under 2 m straightedge | ±5 to ±10 mm under 2 m straightedge |
| Positioning of block-outs | ±1 mm | ±15 mm |
Surveying the as-built core and designing shimming components
To avoid destructive site alterations or crane downtime during assembly, ordering CLT panels adjacent to the concrete core must never be initiated solely on the basis of architectural or civil engineering drawings. Surveying the core prior to machining is an imperative step. This rigorous measurement takes place as soon as the concrete is completely stripped of formwork and has undergone initial curing, using a total station or a 3D scanner referenced to the primary surveyor benchmarks (main gridlines and 1-metre datum level).
- Scanning and point cloudThree-dimensional survey of the four faces of the concrete core, recording floor slab levels, formwork panel deflections, and the actual positions of starter bars or cast-in steel inserts.
- Import into the CAD/CAM modelSuperimposing the actual survey onto the digital timber model to identify areas of geometric clash, clearance reductions, and variations in shimming thickness.
- Adapting CLT machiningGenerating machine cutting files that incorporate tailored cut-outs, clearance chamfers, or adjusted drilling locations for metallic fasteners.
- Installing interface shimming componentsFixing adjustable continuous steel angles, custom-ripped timber ledger boards, or steel bearing plates with tapered shims onto the concrete.
The planned shimming gap receives specific components depending on the nature of the loads transferred. For direct vertical bearing of the CLT slab on the concrete wall, the continuous steel bearing angle features horizontal and vertical slotted holes allowing three-dimensional adjustment prior to final tightening with approved wedge anchors or concrete screws. The remaining gap between the timber and the concrete is then filled with a compressible material, such as a mineral wool strip under controlled compression or an expanding airtight sealing tape, ensuring acoustic isolation and fire compartmentation continuity.
Where the interface also provides the transfer of horizontal wind-bracing loads (diaphragm action of the CLT floor to the rigid core), the steel connection components combine cast-in plates and through-bolted tie rods. The slotted holes accommodate movement during positioning and are then locked with thick washers welded on site or torqued to specification, fixing the final geometry without inducing stress in the timber.
Managing critical deviations: hold point protocol and remediation solutions
On the construction site, the interface between concrete shear walls and CLT slabs or panels leaves no room for improvisation. As soon as a dimensional or verticality deviation of the core exceeds the tolerances permitted by standard SIA 414 and consumes the shimming allowance provided in the fabrication drawings, installation must be suspended. Forcing a cross-laminated timber panel with a hydraulic jack or overstressing a bearing angle introduces unintended parasitic loads into the anchors and shifts the entire timber gridline of the upper storeys.
- Joint inspection record and point cloudPerform a verification 3D scan or a joint total station survey with site management and the mason to formally record the deviation from the execution model.
- Adaptation of interface componentsConsult the timber engineer to validate modifications to the metal shimming components, the insertion of tapered steel shims, or localised remediation by compensatory planing if the concrete wall is bowed.
- Mechanical remediation of the substrateHave the masonry contractor carry out bush-hammering, scabbing, or concrete sawing if the core encroaches on the theoretical CLT boundary, in order to restore the minimum service gap.
The cost and lead time of a digital workshop remachining remain negligible compared to crane downtime. Anticipation relies on a rigorous survey of the structural work before releasing CLT panel production in the factory.
Frequently asked questions
What should be done if the concrete wall has an out-of-plumb deviation exceeding the designed clearance?
Erection must be stopped immediately and site management notified. The civil engineer and the timber engineer must assess the situation. Two solutions are possible: have the mason chip away or saw off the excess concrete, or have interface brackets redesigned with variable thickness plates to compensate for the verticality defect without inducing stress in the CLT panel.
Can a CLT panel be cut down on the construction site to compensate for a deviation?
Trimming an edge for adjustment is only permissible with formal approval from the timber engineer. It depends on the load-bearing function of the panel, edge distances to connectors, and the presence of factory rebates. Trimming an edge alters bearing spans and may cut into structural cross-layers, weakening the load-bearing capacity of the slab or wall.
How can the airtight seal be guaranteed in the case of an irregular gap?
When the gap varies between 10 and 35 mm along the core, sealing cannot rely on a simple mastic bead. A flexible, highly elastic adhesive sealing tape bonded to the timber and the primed concrete is installed, combined with a calibrated closed-cell foam backer rod to fill the variable void.
Who covers the cost of fabricating special angle brackets?
If the concrete exceeds the contractual tolerances defined by standard SIA 414, the cost of adaptation falls under the responsibility of the mason or the client. The carpenter must notify the defect in writing via a notice of defects prior to any intervention, submitting a revised quote for the supply and installation of the special interface brackets.
Texts and standards cited
- SIA 414Dimensional tolerances in building construction
- CO art. 365Defective material and building site: notification of the client by the contractor