🧱 CFC 214Cross-laminated timber (CLT): panels, lifting and jointsChapter 2 of 10 in the section

Lifting CLT panels: assembly sequence, push-pull props and stability at each stage

This chapter details the lifting kinematics of cross-laminated timber walls. You will learn how to organise the assembly sequence ensuring overall stability at each installation stage, adjust and lock the push-pull props prior to any crane unhooking, and strictly cordon off the slewing and movement area on the ground in accordance with Swiss safety requirements.

Key takeaways

  • The push-pull prop must be anchored and locked before releasing the crane hook.
  • Assembly must imperatively begin with a rigid corner forming the primary stability core.
  • The movement area beneath the moving load remains strictly prohibited to all personnel.
  • The installation plan defines the direction of progress to avoid isolated panels exposed to the wind.

Lifting kinematics and the absolute rule of unhooking under propping

Handling a large-height cross-laminated timber panel requires absolute rigour during the transition between crane suspension and self-support on the slab. An eight-metre vertical element presents significant windage and substantial self-weight. As long as the crane supports the panel, equilibrium is maintained by the rigging. As soon as the cables are slackened, the panel offers no inherent resistance to lateral overturning without prior mechanical fastening.

The push-pull prop absorbs both the thrust caused by the wind and the tensile forces generated by any potential overturning in the opposite direction. The selection of fittings and temporary fastenings is not improvised on the construction site: the diameter, length and number of wood screws driven into the face of the CLT must take up the forces specified in the assembly concept. Likewise, the connection to the floor must be drilled and anchored into sound concrete or screwed through the underlying timber floor in accordance with the working drawings.

  • Check the cleanliness of the base and the presence of the sealing strip or acoustic felt before landing.
  • Guide the base of the panel using tag lines to prevent any direct contact with the moving load.
  • Fasten the prop footplates to the slab before full upending if the kinematics permit, or immediately upon plumbing the panel.
  • Screw the prop head into the CLT panel according to the prescribed drilling pattern prior to any release of the lifting hook.

At workstations and passageways, measures must be taken so that workers are not endangered pursuant to art. 17 OTConst. The crane operator must not initiate any clearance manoeuvre until the foreman has visually confirmed and communicated via radio signal the self-supporting stability of the element.

Box-structure assembly sequence and demarcation of the exclusion zone

The stability of a CLT storey does not rely solely on temporary props, but on the rapid formation of undeformable volumes. Aligning straight panels single-file creates a domino effect that is particularly vulnerable to thermal wind gusts frequent across the Swiss plateau or in alpine valleys. Assembly must begin with a corner or a shear wall core.

  1. Creation of the initial rigid cornerLift two panels first to form a ninety-degree corner. Immediately assemble the corner junction using fully threaded screws or structural angle brackets to create a geometrically undeformable cell.
  2. Closed-loop progressionContinue installing external wall panels by systematically connecting them to transverse shear walls. Each additional panel must close a rigid sub-structure rather than extending a straight line that remains free at the head.
  3. Box closureInstall the lintels and solid panels forming the room enclosure. As soon as a cell is closed and screwed together, it constitutes a fixed point capable of taking up the assembly loads from subsequent bays.
Temporary stability criteria according to the installation layout
Panel layoutTemporary retaining systemCondition for crane release
Isolated straight panelTwo push-pull props minimum, angle between 45° and 60°Slab and timber anchorages verified, locking pins secured
Corner panelOne prop per face plus complete corner mechanical connectionCorner screws installed and tightened over the entire accessible height
Internal shear wall panelTwo push-pull props or direct clamping to the adjoining wallFoot connection locked and propping locked under pressure

Ground-level spatial management is inseparable from lifting operations. Work must be planned in such a way that the risk of occupational accidents, occupational diseases or damage to health is as low as possible in accordance with art. 3 OTConst. The working radius of the jib and the load travel path constitute an absolute exclusion zone demarcated by physical barriers or rigid warning tape across the slab.

Inspection of propping fastenings and wind load transfer

The temporary stability of a vertical cross-laminated timber element relies entirely on the load transmission path: the solid wood panel, the head bracket, the body of the telescopic prop, the swivel footplate and the anchorage to the substrate. On large-format elements, windage generates alternating tensile and compressive forces that the temporary fastenings must absorb with zero mechanical play. An improperly positioned or undersized anchor in the floor slab compromises the stability of the panel at the very first gusts of wind.

Selection and fixing criteria for push-pull props on vertical CLT elements
Load-bearing elementBase anchoring substrateRecommended fixing typeKey checkpoints on the construction site
Internal CLT panel (standard height)Reinforced concrete slabConcrete screw with large washerDrilling depth respected, systematic borehole cleaning
Large-height CLT panel (> 6 m)Reinforced concrete slabThrough-bolts or certified through-anchor studsControlled tightening torque, verification of slab thickness
Upper-floor CLT panelUnderlying CLT floorAngled fully threaded wood screwsSufficient number of screws, verification of edge distances on base panel
Corner shear wallSole plate or timber ground beamStructural coach screws with bearing platesAbsence of splits in supporting timber, appropriate pre-drilling

The angle formed by the push-pull prop with the floor must be between 45 and 60 degrees to ensure a balanced distribution between the horizontal retaining force and the vertical load transferred to the support. Two props per panel constitute the absolute technical minimum to prevent any overturning and to control torsional forces during precise alignment of the structure using an optical or laser level.

Phase transition: corner consolidation and prop release

Push-pull propping is merely a temporary emergency measure to stabilise an isolated panel. Permanent structural safety is only achieved when 3D box rigidity is established through the complete assembly of corners and the installation of structural mechanical connections. The erection team must carry out perimeter consolidation continuously before the end of each daily shift.

  1. Packing and plumb adjustmentTurn the threaded collars of the props to align the panel precisely on its chalk line, while monitoring the waterproof bearing shims.
  2. Corner connection screwingInstall double-threaded screws or structural screws in a staggered pattern at the corner junction with the perpendicular wall that is already erected and propped.
  3. Base bracket fixingPermanently anchor shear and hold-down brackets to the slab before applying any additional loads.
  4. Installation of horizontal or roof elementsPlace the CLT floor slabs that ring the box structure and create the rigid diaphragm essential for overall stability.
  5. Methodical removal of proppingUnscrew and remove push-pull props only after confirmation from the site manager that the upper diaphragm is fully nailed or screwed off.

For general safety on the construction site, the employer must, in accordance with LAA, take all measures that have been shown to be necessary by experience and that are feasible according to the state of technology. The strict maintenance of temporary bracing systems until the building cell is fully closed directly applies this fundamental technical principle of the carpentry trade.

Handling installation contingencies and maintaining stability

On a solid timber construction site, a guidance error or a sudden gust demands an immediate, codified reaction. If a wind gust exceeds the operating limits of the crane or the holding capacity of the tag lines, the absolute instruction is that releasing the panel is forbidden. The element remains suspended from the hook until both push-pull props are anchored at the foot to the floor and anchored at the head to the CLT panel. The crane maintains residual tension to relieve wind loads without pulling out the installation fixings.

In the event of an obstruction on the sole plate or a setting-out discrepancy exceeding tolerances, it is strictly forbidden to leave a vertical panel standing freely on simple bearings. If the element does not seat into its rebate or if a metal connector blocks the path, the component must either be returned flat to the storage area, or held on the hook with its props deployed and tightened to the floor before any manual work is carried out at the base. No operative is to place hands or a pinch bar under the edge of a suspended panel.

  • Immediate evacuation of the floor sweep area as soon as an oscillating movement escapes control via the tag lines.
  • Strict prohibition against removing a prop to adjust an adjacent panel without first installing substitute bracing.
  • Immediate re-tensioning by the crane if a prop shoe shows pull-out signs or cracks appear in the concrete or timber base.

When a corner joint fails to pull tight, the crew first stabilises the shear wall with its own propping before forcing mechanical closure using cable pullers or angled screws. Under CP, whoever intentionally breaches the recognised rules of the building trade when directing or executing a construction project and thereby knowingly endangers the life or physical integrity of people is liable to a custodial sentence or a monetary penalty. Box geometry is never rectified by prematurely releasing temporary propping.

Frequently asked questions

Can the crane be unhooked if only one of the two push-pull props is fixed?

No. Unhooking requires the complete anchoring of both specified push-pull props per panel. A single prop creates a potential pivot point under wind action or accidental impact. An unbracketed CLT panel behaves like a sail. The crane must keep the load under slight tension until both footplates are screwed down and locked to the floor.

What should be done if the sole plate is out of level beneath the suspended panel?

Never attempt to pack the suspended panel directly at the base while it hangs on the winch line. Lower the element back onto its storage bearers or stabilise it on its two locked push-pull props before intervening. Bearing shims must be set with a laser level prior to final placement of the panel along its setting-out line.

How should one react if the wind increases suddenly while guiding a CLT wall?

If the wind makes rope guidance uncontrollable, the crane operator must stop lowering and slowly bring the panel back towards the landing zone if the approach is already committed, or place it back on the transport trailer. The ground crew maintains a safe distance without attempting to restrain the load with bare hands, then waits for a lull within safe working limits.

At what exact moment can push-pull props be dismantled on a CLT storey?

Push-pull props must only be removed once the floor above is installed, screwed down and tied to the load-bearing panels, or when the diaphragm provides the final bracing of the storey. The foreman verifies that the spatial rigidity of the box structure is established through all corner connectors and head fixings before any prop feet are released.

Texts and standards cited

  • OTConst art. 17protection against the collapse of building components or the falling of objects and materials: at workstations and passageways, measures must be taken so that workers are not endangered.
  • CPbreach of the recognised rules of the building trade: whoever, when directing or executing a construction or demolition, intentionally breaches the recognised rules of the building trade and thereby knowingly endangers the life or physical integrity of people is liable to a custodial sentence not exceeding five years or to a monetary penalty; in cases of negligence, to a custodial sentence not exceeding three years or to a monetary penalty.