Carpenter safety: roofing, lifting and wood dust: the execution reference

This section is intended for carpenters, site foremen and project managers who erect non-stabilised timber structures and work on roofs. It brings together Swiss operational requirements to prevent fatal falls from height, control heavy crane operations and eliminate the chronic inhalation of hardwood dusts classified as carcinogenic, from workshop preparation through to critical assembly phases on the construction site.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 5

OTConst art. 41

2 m

Fall height triggering edge restraint measures on the roof

OTConst art. 41

60°

Limit slope requiring the use of scaffolding or a mobile elevating work platform

OTConst art. 22

100 cm

Minimum top rail height for perimeter guardrails

OTConst art. 22

47 cm

Maximum vertical clear distance between guardrail components

OTConst art. 22

15 cm

Minimum height of the toeboard at platform level

Technical scope of the carpenter and limits of intervention

Erecting a timber frame exposes the crew to a unique situation: working positions are at height while the structure itself has not yet reached its final rigidity. Spatial stability relies on temporary bridging, diagonal bracing straps and push-pull props installed progressively as work advances. This configuration dictates strict discipline regarding collective restraint measures, the organisation of working areas and the continuous assessment of loads applied to the structure during assembly.

  • Collective protection beneath the frame: safety nets installed before laying rafters or roof panels.
  • Heavy lifting and crane handling: sling angle calculation, timber sharp-edge protection and centre-of-gravity verification.
  • Temporary stability: immediate securing of trusses, purlins and framing elements as soon as the crane is unhooked.
  • Health at the machining station: direct extraction of fine hardwood dust in the workshop as well as on mobile cutting platforms.

Pursuant to art. 41 OTConst, prevention of falls from height becomes mandatory as soon as the working level exceeds 2 m above the ground or a lower level. On roofs with a slope exceeding 60°, direct work on rafters or purlins is prohibited: work must be carried out exclusively from a mobile elevating work platform or a suitable service scaffolding.

Methodological route: from the workshop to the open roof space

To ensure the physical safety of the crew, the ten chapters in this section must be tackled in a strict chronological sequence. Risk management begins in the fabrication hall with the extraction of chips and the adjustment of cutting machinery, continues with the craning of prefabricated sub-assemblies, and concludes with securing the open roof space against severe weather.

  1. Initial collective protection and roof edgesBefore sending any installer onto windbracing binders or rafters, the crew installs the under-purlin safety nets described in Chapter 1, then secures perimeter edge protection according to the slope criteria in Chapter 2.
  2. Respiratory health and portable machineryChapters 3 and 4 cover the extraction of fine oak or beech dust classified as carcinogenic and the adjustment of the riving knife on high-capacity saws to prevent violent kickbacks.
  3. Temporary anchorages and lifting operationsChapters 5 to 7 detail the search for solid points on a timber skeleton during nailing, load calculations on textile slings and the stable positioning of self-propelled MEWPs.
  4. Co-activity, noise environment and weatherChapters 8 to 10 regulate the protection of underlying trades against falling tools, the management of acoustic exposure to planers and lifting shutdown thresholds in wind gusts.

📘 Chapters in this section 10

Carpenter safety: roofing, lifting and wood dust

Safety net under purlins: the protection installed before climbing onto the roof

Install your nets under purlins from the very start to work on the framing without the risk of an internal fall.

Carpenter safety: roofing, lifting and wood dust

Work at roof edge: protection threshold and solutions according to pitch

Determine the compliant edge protection system according to the exact pitch of your roof planes.

Carpenter safety: roofing, lifting and wood dust

Wood dust: a recognised carcinogen, source extraction and masks

Neutralise carcinogenic hardwood dust using workshop-appropriate extraction classes.

Carpenter safety: roofing, lifting and wood dust

Portable circular saw: riving knife, guard and machine kickback

Accurately adjust the riving knife and guard to eliminate circular saw kickback.

Carpenter safety: roofing, lifting and wood dust

Harness in timber framing: anchor point on an unstable structure

Identify frame joints capable of absorbing fall-arrest impact forces during assembly.

Carpenter safety: roofing, lifting and wood dust

Slinging timber components: sling angle, edge protection and actual load

Adjust your sling angle and protect sharp edges to hoist without crushing the timber.

Carpenter safety: roofing, lifting and wood dust

MEWPs in carpentry: ground bearing capacity, harness in the basket and limits

Calculate ground bearing capacity and secure the operator to operate the boom lift without overturn.

Carpenter safety: roofing, lifting and wood dust

Falling objects from timber framing: tethered tools, exclusion zone and coactivity

Lanyard every hand tool and cordon off the area below to prevent co-activity incidents.

Carpenter safety: roofing, lifting and wood dust

Woodworking machinery noise: sound levels, protection and workshop organisation

Attenuate the acoustic sound pressure of cutting machinery through the rational layout of your machining stations.

Carpenter safety: roofing, lifting and wood dust

Wind, rain and frost: when to stop lifting and how to secure the open structure

Measure wind speed and anchor the open structure immediately before severe weather arrives.