Skip to content
Website
🧱 CFC 214Traditional timber framing: trusses, purlins and raftersChapter 4 of 10 in the section

Rafters: spacing, section and span between purlins

This chapter provides the method for determining the spacing, section and allowable span of solid timber or glued-laminated timber rafters. You will learn how to incorporate the snow load specific to the construction site altitude and the roof covering support constraints without relying on standardised spacings, which are frequent causes of excessive deflections or structural failures.

Key takeaways

  • The local snow load and altitude determine the decisive surface load on the rafter system.
  • Standard SIA 265 requires verification of ultimate and serviceability limit states.
  • The roof covering support limits the allowable spacing before any section is chosen out of habit.
  • The span between purlins determines the required section depth to contain the final net deflection.

Calculate spacing according to the local snow load and the roof covering support

Systematically setting a sixty-centimetre spacing is a risky construction site routine. In traditional Swiss timber framing, the geometry of the rafter system depends primarily on the characteristic snow load at the site location and the mechanical requirements of the chosen roof covering material. Standard SIA 265 requires verification of bending and shear stresses as well as allowable deflection under the most unfavourable combination of actions. Fixing rafter spacing without recalculating snow accumulation according to altitude and topography exposes the structure to major defects.

Characteristic snow load
Reference ground value defined for a given Swiss altitude and geographical area, used for calculating roof loads in accordance with structural standards.
Parameters determining rafter spacing according to support and snow load
Altitude zoneReference snow loadType of roof covering supportStandard calculation spacing
Plateau (< 500 m)Moderate according to load mapFull close boarding or structural panel600 mm to 700 mm
Pre-Alps (500 m to 1000 m)Medium to heavy with accumulationStandard battens for clay tiles500 mm to 600 mm
Mountains (> 1000 m)High with potential snowdriftsReinforced counter-battens or close boarding400 mm to 500 mm

The site foreman must demand confirmation of the final roof covering before cutting jack rafters and common rafters. A change from clay tiles to a heavier system during the procurement phase distorts the static equilibrium if the spacing was set on empirical grounds. Liaison with the timber engineering consultancy ensures that the load transferred to each purlin complies with the load-bearing capacity of halving joints or joist hangers.

Determine the section and allowable span between purlins according to SIA 265

The clear span of a rafter is measured along the slope, between the inner faces of the wall plates, intermediate purlins or ridge purlins. For a given span, the timber section is derived from the maximum bending moment and the required section modulus. According to standard SIA 265, checking the final net deflection under total load is almost always the governing condition before pure ultimate failure resistance. Slender sections must also provide sufficient width to allow adequate fastening of secondary elements without risking longitudinal splitting.

  1. Record actual spans from the framing drawingMeasure the distance between purlin supports along the slope and check for the possible presence of eaves cantilevers.
  2. Define the line load per rafterMultiply the sum of the roof self-weight and the local snow load by the tributary width equivalent to the spacing.
  3. Select the timber strength classChoose the load-bearing material, generally spruce or fir of class C24 for solid timber, or GL24 for glued-laminated timber.
  4. Size the section depth and widthCalculate the minimum section to keep deflection within the serviceability limits of SIA 265 and ensure adequate anchorage onto the purlins.

When the thickness of over-rafter thermal insulation becomes significant, the risk of lateral torsional buckling of the rafter increases considerably. It is the carpenter's responsibility to brace the rafters together at regular intervals or ensure that the decking contributes to the in-plane bracing of the roof. The connection to the purlins, executed using sprocket pieces, cross-nailing or fully threaded screws, must resist the sliding component parallel to the pitch imposed by the Alpine snow load.

Coordination with the roofing trade package: key parameters of the rafter layout

Installing rafters at a constant spacing out of workshop habit is a recurring source of structural disputes and site defects. Even if the carpenter sizes the sections according to standard SIA 265, the actual rafter spacing does not depend on an arbitrary standard of 60 cm, but on the direct interaction between the roof covering support and the snow load specific to the structure's municipality.

The mechanical sizing of the rafter must imperatively integrate the inherent strength of the support resting on its top edge. Elements installed perpendicular to the rafters have strict span limits under combined climatic actions:

  • Roof battens: the thickness and section of battens must absorb the weight of tiles and accumulated snow without excessive deflection between two rafters.
  • Close boarding or structural panelling: their minimum thickness depends directly on the clear distance between rafters to ensure resistance to point loads and prevent punch-through under concentrated loads.
  • Anchorage of counter-battens: through-nailing or screwing must transfer shear forces and wind uplift forces into the body of the rafter.
Impact of snow load and support on allowable rafter spacing
Altitude zonePlanned roof covering supportStandard rafter sectionRecommended maximum spacing
Plateau (< 500 m)Battens for clay tiles60 x 80 mm600 to 650 mm
Plateau (< 500 m)Full close boarding 24 mm60 x 100 mm700 to 800 mm
Pre-Alps (800 - 1200 m)Reinforced battens for concrete tiles80 x 100 mm500 to 550 mm
High altitude (> 1200 m)Double close boarding or structural panel80 x 120 mm / 100 x 120 mm400 to 450 mm

As altitude increases, the snow load component quickly becomes the governing action. Reducing the spacing often proves more economical and constructible than excessively increasing the rafter section depth, particularly when insulation cavities or eaves details impose strict dimensions.

Span between purlins, allowable deformations and carpenter's duty to notify

The clear span of a rafter is measured parallel to the line of steepest pitch, between the faces of the supports at wall plates, intermediate purlins or ridge purlins. According to standard SIA 265, rafter sizing is not solely governed by the ultimate limit state (resistance to bending failure and shear force at the supports), but very frequently by the serviceability limit state, namely the maximum allowable deflection under characteristic load combinations.

Excessive mid-span deflection leads to serious consequences for the entire roof assembly: misalignment of roofing elements, loss of water tightness at tile interlocks under the weight of snowdrifts, or crushing of wood fibres at birdsmouth notches on purlins. When the span between purlins exceeds 3.50 m to 4.00 m, maintaining a standard solid timber rafter section becomes impossible without generating visible or dangerous deflection.

  1. Check received structural drawingsVerify alignment between the actual rafter span determined by the purlin layout drawing and the snow load assumptions incorporated into the engineer's sizing.
  2. Assessment of the actual roof covering supportRequest formal confirmation from site management regarding the self-weight of the selected roof covering (tiles, metal, slates) and the spacing limits specified by the fastener manufacturer.
  3. Formulation of the duty to notifyIn the event of an inadequacy between the span, the section specified in the schedule of quantities and the local snow load, report the defect in writing to preserve the structural safety of the building.

On the construction site, the fastening of rafters to purlins also demands rigorous attention. Connections using notches or birdsmouth joints must not excessively reduce the effective section at the support face. The use of twisted nails, partially threaded timber construction screws or framing anchors must resist slope-induced sliding as well as wind uplift forces calculated according to standard SIA 265, ensuring the overall stability of the roof structure.

Managing span variations and duty to notify on the construction site

On the construction site, the classic mistake consists in carrying over the standard 60 cm spacing without checking the local characteristic snow load or the dimensions required by the roof covering support. If purlin installation reveals a distance greater than the allowable span calculated according to standard SIA 265, the carpenter cannot compensate for the inadequate section through mere workshop habit. An undersized section exposes the roof to excessive deflections as soon as the first winter surcharges arrive, compromising the uniform support of battens or close boarding.

As soon as a geometric discrepancy or an unforeseen load arises, formal notification is mandatory. In accordance with art. 365 CO, if the material provided by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the regular or prompt execution of the work, the contractor shall inform the client thereof. The notification must be sent in writing to site management before cutting or installing any timber, quantifying the anticipated deflection and structural deficit.

  • Systematic check of the actual spacing using a chalk line and gauge rod prior to cutting rafter birdsmouth notches on purlins.
  • Verification of consistency between the structure's altitude, the local snow load and the design assumptions.
  • Written request for technical data sheets of the roof covering support to validate its maximum allowable spacing.
  • Refusal to install over spans between purlins exceeding structural calculation values without intermediate support or doubling validated by the timber engineer.

In the event of an established dispute or oral instructions contrary to recognized technical rules, the site agent suspends the rafter installation on the disputed bay. He documents the actual spans through a joint survey and proposes the required adjustments: reducing spacing, increasing section depth or reinforcing by sandwich plating.

Frequently asked questions

How should one react if the spacing required by the roofer does not match the structural calculations?

The carpenter must halt layout operations and recalculate the rafter section according to standard SIA 265 for the required spacing. If the requested spacing exceeds the load-bearing capacity of the specified timber, he notifies site management in writing. The solution requires either reducing the spacing in agreement with the roofing package or increasing the rafter section depth to ensure the required strength.

Why does the local snow load preclude a flat-rate spacing in French-speaking Switzerland?

The pressure exerted by snow varies substantially according to altitude and climatic region, sometimes increasing threefold between the Lake Geneva Plateau and the Pre-Alps. Sizing rafters with an arbitrary 60 cm spacing exposes the structure to failure or excessive deflection. The local load strictly dictates the allowable shear force and bending moment in the timber.

What should be done if the span between purlins on the construction site exceeds the construction drawings?

Installing the rafters without validation is out of the question. The supervisor checks the actual span between purlins and models the deformation under load according to standard SIA 265. Pursuant to the duty to notify under the Code of Obligations (CO), he reports the error to the client. Remedial measures consist of installing an intermediate purlin, doubling the affected rafters or upgrading to a higher strength class.

What maximum deflection limit is commonly applied to traditional rafters?

To preserve the integrity of the roof covering support and ensure proper water drainage, the final net deflection of rafters under cumulative loads is usually limited to one three-hundredth of the span between purlins. A greater deflection leads to fastener defects, causes tile interlocks to gape, and creates low points for water accumulation that undermine the durability of the roof structure.

Texts and standards cited

  • SIA 265Timber structures - design, verification of structural safety and serviceability
  • CO art. 365materials and ground: the contractor is liable for the sound quality of the material he provides; if the material provided by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the regular or prompt execution of the work, he shall immediately inform the client thereof, under penalty of bearing the consequences (para. 3)

In the same section