Key takeaways
- The light weight of CLT requires an addition of mass to dampen impact sound.
- Total decoupling of the heavy screed prevents the load-bearing panel from being set into vibration.
- Flanking transmission through walls ruins acoustic insulation without continuous resilient strips.
- Through-screwing that is not decoupled creates a direct acoustic bridge that destroys sound reduction.
Adding mass and decoupling the screed on a CLT floor
Cross-laminated timber panels offer an excellent strength-to-weight ratio, but this low density is a direct handicap for building acoustics. Unlike a solid reinforced concrete slab, a bare CLT floor vibrates under airborne noise and resonates strongly under impact sound, particularly at low frequencies. To meet the acoustic comfort requirements set by standard SIA 181, the carpenter cannot rely on the structural panel alone: the floor build-up must incorporate an added mass.
Protection against noise in building construction defines the minimum and increased requirements relating to airborne and impact sound insulation between separate dwelling units.
norme SIA 181
This added mass takes the form of bound or loose heavy gravel ballast beneath a flowing or cement screed, or directly a heavy screed cast onto a compressible insulating layer. The physical principle is based on the mass-spring-mass system: the CLT provides the lower stiffness, the acoustic insulation acts as an elastic spring, and the heavy screed constitutes the upper dampening mass. If the screed comes into direct contact with the load-bearing element or the vertical walls, structure-borne sound transmission short-circuits the spring.
- Cleaning and airtightness of the CLT substrateVacuum the timber floor, check panel joints, and lay a continuous protective sheet or dust barrier with sealed overlaps.
- Installing the perimeter resilient stripStaple or bond a high-density mineral wool or foam strip to the base of all partitions and perimeter walls, extending higher than the finished floor level.
- Laying impact sound insulationLay the insulation boards with tight butt joints without leaving voids, avoiding any overlapping of layers that would create an unstable extra thickness.
- Watertight protection before castingRoll out a watertight polyethylene membrane with an upturn taped to the perimeter resilient strip to stop any cement slurry.
Cutting flanking transmission through walls and managing fixings
Even with a perfectly floating heavy screed, a dwelling's acoustics can fail acceptance measurements if flanking transmission is not controlled. Acoustic energy transmitted to a CLT floor does not merely travel down through the slab: it spreads horizontally and excites the vertical timber walls located along the perimeter or beneath the bearing. Multi-storey continuous CLT walls then convert the footsteps from the upper floor into radiated sound in the room below.
| Junction configuration | Primary transmission path | Required execution measure |
|---|---|---|
| Continuous CLT passing through the storey | Direct transmission through the vertical panel | Panel break or independent internal lining |
| Slab resting directly on timber wall head | Unbroken structure-borne bearing transmission | Continuous elastomeric resilient strip beneath the slab bearing |
| Metal brackets screwed without gaskets | Vibrational short-circuit through anchor screws | Acoustic washers under screw heads and decoupled brackets |
| Non-load-bearing internal partition screwed to the floor | Transmission from the floor to the partition | Partition fitted onto the bare slab with a resilient strip |
Interrupting structure-borne conduction requires the insertion of specific microcellular elastomer resilient strips under the bases of walls and under slab bearings. These materials must be laid out according to the permanent and imposed loads transmitted, in order to ensure the required elasticity without premature crushing. If the strip is too stiff, it does not filter vibrations; if it is too soft, settlement destabilises the geometry of the structure.
Corner junctions and mechanical decoupling of vertical load-bearing elements
Theoretical sound reduction calculated in the laboratory for a CLT floor build-up frequently collapses on the construction site due to secondary flanking paths. The impact sound rating or airborne sound insulation according to standard SIA 181 depends directly on attenuation at constructive nodes. If the CLT floor panel rests directly on a lower load-bearing wall while supporting the upper wall without a thermal/acoustic break, the vibrational energy injected into the surface travels vertically via direct structure-borne transmission, short-circuiting the mass of the screed.
To block this flanking acoustic bridge between two stacked dwellings, the carpenter inserts an engineered microcellular elastomer beneath the foot of the upper wall or at the head of the lower wall. The continuous resilient strip must take up structural dead loads without being compressed beyond its dynamic dampening range. Incorrectly calibrated dynamic stiffness results in timber-to-timber contact or causes the material to shear under wind loads.
| Node configuration | Predominant acoustic risk | Constructive arrangement on the construction site |
|---|---|---|
| Continuous floor passing between two dwellings | Massive horizontal flanking transmission from one room to another | Saw the panel along the separating partition or install an acoustic break profile |
| Upper CLT wall screwed directly through the floor | Acoustic short-circuit via rigid metal fixings | Dampening collars under washers or angle brackets with integrated elastic decoupling |
| Timber-to-timber bearing without an interlayer strip | Direct sound radiation to the floor below | Insertion of a continuous closed elastomeric strip over the full bearing width |
Sound transmission also takes place through anchoring ironmongery. A base angle bracket fixed with fully threaded screws creates a rigid steel link that transmits impact sound across the resilience. The timber engineer therefore specifies decoupled brackets or the insertion of polyurethane washers under screw heads, or even screws fitted with thick neoprene washers, tightened to the specified torque without total crushing.
Installation of perimeter resilient strips and airtightness of junctions
The success of a floor build-up on CLT lies in the integrity of the tank formed beneath the screed. Before unrolling the impact sound insulation and casting the mortar or spreading the heavy aggregate, the carpenter and the finishing trades ensure that the perimeter resilient strip of at least ten to fifteen millimetres extends above finished floor level. The slightest direct contact between the liquid screed and the CLT wall panel ruins the mass-spring-mass effect required by standard SIA 181.
- Airtightness treatment beneath the resilient layerApply reinforced airtight tape over the joint between CLT floor panels prior to laying sound insulation to block airborne noise leaks through assembly gaps.
- Levelling and alignment of the base stripClean the bearing edge with an industrial broom, unroll the continuous resilient strip without excessive stretching, and staple only in the neutral bearing zone away from the load area.
- Inspection of vertical penetrationsSleeve every service pipe or conduit with a felt or elastomeric sleeve of at least ten millimetres before screed pouring to eliminate any hard mechanical contact.
According to art. 365 CO, the contractor notifies the client of circumstances that jeopardise the proper execution of the work. If execution drawings omit the decoupling of internal walls or specify direct fixings through dampening strips, the carpenter must immediately submit written notice. Furthermore, according to art. 3 OPA, the employer shall take protective measures and arrangements in line with recognised technical rules to ensure the safety and health of staff when handling heavy levelling masses and lifting gear required for the installation of these multi-layered floor systems.
Management of acoustic defects and remedial measures on CLT
On a cross-laminated timber floor, an in situ acoustic inspection that does not comply with the requirements of standard SIA 181 almost systematically stems from a rigid acoustic bridge or improper flanking decoupling. When impact sound measurements reveal an unacceptable deviation, the carpenter and the site management must proceed methodically before undertaking any major demolition.
- Systematic inspection of edges: check with a utility knife that the heavy screed does not touch any CLT wall panel and that the perimeter resilient strip has not been folded down or punctured during casting.
- Investigation of parasitic mechanical links: identify structural screws, angle brackets or metal fixings piercing the resilient layer without an elastomeric washer or decoupling collar.
- Verification of service penetrations: ensure that no ventilation duct, heating pipe or sanitary conduit has been grouted with rigid mortar directly into the CLT floor opening.
If the acoustic bridge is located at the screed perimeter, remediation consists of cutting the contact with a diamond disc to restore a continuous void of at least ten millimetres, subsequently sealed with a flexible bead. Conversely, if flanking transmission occurs through direct structural continuity of the CLT wall panels beneath slabs without a resilient bearing compliant with execution details, remediation becomes complex.
When the added mass or the sub-screed build-up can no longer rectify the issue due to structural load limits, the fallback solution often requires adding a heavy suspended ceiling on anti-vibration hangers beneath the CLT panel, or installing self-supporting acoustic wall linings on the timber panels to block flanking radiation.
Frequently asked questions
How do you repair a liquid screed that has flowed against the CLT wall?
The area of rigid contact must be precisely located, the skirting board removed, and the screed edge cut through its entire thickness using a diamond disc. The objective is to recreate a continuous empty joint of at least ten millimetres along the CLT wall. This joint is then dusted and filled with an elastomeric sealant to restore airtightness without re-establishing structure-borne sound transmission.
Can a metal fixing angle bracket ruin the acoustics of a CLT floor?
Yes. A single rigid metal fixing connecting the CLT floor directly to the lower load-bearing walls without a flexible interlayer or elastomeric washer negates the benefit of the resilient strip. The fixing creates an acoustic bridge that transmits the vibrational energy of impact sound directly into the vertical structure. Decoupling fasteners according to the timber engineer's details is essential to comply with standard SIA 181.
Why is added mass on CLT not always sufficient for impact sound?
A heavy screed provides the inertia needed to compensate for the light weight of solid timber, but it only addresses direct transmission. If the vertical CLT walls remain rigidly connected to the slab without an elastic break, sound travels horizontally via flanking paths through the walls of the storeys below. Overall acoustics requires the indispensable combination of mass, impact sound insulation material, and complete decoupling.
When should the screed perimeter resilient strip be installed?
The perimeter resilient strip must be installed by the screed layer prior to laying floor insulation and casting the heavy screed, but the carpenter must check the substrate. The edges of CLT panels must be free of protruding screws or roughness that could puncture it. The strip must project above the finished floor level and only be trimmed flush after the floor covering is installed.
Texts and standards cited
- SIA 181Protection against noise in building construction
- CO art. 365Materials and site: the contractor is liable for the sound quality of the material he provides; if the material provided by the client or the ground designated by him is found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, he immediately informs the client, under penalty of bearing the consequences (para. 3).
