Key takeaways
- Stacking on the lorry strictly adheres to the reverse erection sequence defined by the technical office.
- Crane booking and municipal access permits determine the unloading window.
- The absence of a storage area requires lifting each panel directly from the transport bed.
- A transport delay requires an immediate switch to fastening or sealing tasks.
Synchronise factory layouts, loading and crane windows
On a cross-laminated timber (CLT) building construction site, the lorry serves as the sole temporary storage facility. Most of the time, the ground footprint is limited strictly to the exact footprint of the foundation slab and the safety set-back zones required for excavations. Placing massive panels weighing several tonnes on a freshly poured slab or on soft ground exposes the structure to critical punching shear and needlessly complicates operations. Logistics therefore rely entirely on the principle of progressive erection: each element leaves the transport bed to go directly to its final position in the structure.
This constraint requires pinpoint preparation between the carpenter foreman and the CLT manufacturer's technical office. The loading plan derives directly from the execution model. Panels must be stacked at the factory in the strictly reverse order of their installation. The first element to be craned is systematically at the top of the stack. An inversion of two wall panels forces erectors to perform mid-air flipping manoeuvres or perilous temporary laydowns on the vehicle bed, which halts the cycle.
- Definition of the erection phasingEstablish the precise stability sequence of the structure, starting with stairwells or stiffening shear walls, before placing the associated floor elements.
- Transmission of the layout drawings to the carrierProvide the carrier and manufacturer with the loading plan specifying the exact position, unit weight, slinging points and orientation of visible faces.
- Coordination of the municipal access slotObtain municipal permits for the occupation of public land and align the arrival of the articulated lorry with the plant operator's exact schedule.
- Visual inspection before releasing lashing strapsVerify the correspondence between the delivery note, panel labelling and stack stability before releasing the lashings under the crane.
The Construction Work Ordinance sets strict requirements regarding work planning and the prevention of risks from falling materials. When the mobile crane or tower crane takes charge of a panel, the swing area under the load must be cleared completely of all personnel not assigned to the guidance operation. Smooth unloading ensures that the lorry vacates the roadway within the slot granted by the local road maintenance services.
Manage transport contingencies and adapt crew tasks
Despite meticulous planning, road hazards, customs checks during cross-border deliveries or bad weather can delay the arrival of a transport rotation. On a construction site without a buffer zone, crane downtime represents a direct financial loss for the timber construction company, while risking a bottleneck in the general schedule of the structural work. Management must anticipate this eventuality by establishing an operational contingency plan right from the start of the erection phase.
- Switch the crew to anchoring and final screwing of wall bases already erected using fully threaded screws and angle brackets.
- Install air- and water-sealing membranes along floor edges or accessible vertical joints.
- Install setting-out sole plates and acoustic decoupling strips for the next phase.
- Check the plumb lines and level marks of sub-assemblies erected the previous day using a theodolite or laser level.
| Estimated delay | Logistical impact | Immediate foreman action |
|---|---|---|
| Under 45 minutes | Crane kept on standby | Finalising mechanical fastenings and preparing hardware. |
| 1 to 3 hours | Temporary release of the crane | Reallocation to sealing membranes and installation of fastening angle brackets. |
| Half-day or more | Postponement of the lifting window | Sheeting end-grain timber and falling back on assembling storey sole plates on the ground. |
Under art. 365 CO, the contractor must immediately notify the client if any circumstance jeopardises the timely or proper execution of the works. In the event of a lorry blocked on the road network, logging the incident in the site diary justifies the reorganisation of work shifts without penalising subsequent operations.
At workstations and passageways, measures must be taken to ensure workers are not endangered by the collapse of construction elements or falling objects and materials.
art. 17 OTConst
Access constraints, craning windows and just-in-time delivery without storage
On most construction sites in urban areas or on cramped plots in French-speaking Switzerland, the site footprint allows no intermediate storage for cross-laminated timber (CLT) panels. Each flatbed or low-loader articulated lorry serves as a temporary storage area during its unloading slot. The operation requires direct progressive erection, where the structural element moves directly from the transport bed to its final location in the structure without intermediate handling. This method requires the factory loading sequence to match the exact reverse chronological order of erection, taking into account datum faces and the orientation of slinging points.
The management of lifting infrastructure depends strictly on the permits issued for the public highway. Obtaining an exemption for increased use of public roads, the reservation of parking bays or the temporary closure of a municipal roadway are subject to non-extendable time slots. If the mobile crane or tower crane exceeds its reserved operating window, public space occupancy fees and urban traffic constraints will halt further operations.
| Site configuration | Logistical constraint | Slinging / unloading system | Major operational risk |
|---|---|---|---|
| Dense urban environment (Geneva, Lausanne) | On-street parking limited to 2 hours max. | 4-leg slings with safety hooks or spreader beam with screw-in lifting rings | Traffic blockage, revocation of municipal highway permit |
| Mountain access or steep incline (Valais, Pre-Alps) | Loading gauge limited to 16.5 m max. vehicle combinations, tight bends | Unloading with telescopic mobile crane and direct landing onto sole plates | Inability of standard lorry to manoeuvre, transhipment mandatory |
| Cramped plot without turning area | Compulsory guided reversing exit for the lorry | Remote-controlled automatic hooks or dedicated plates pre-fixed at the factory | Collision with trench shoring or adjacent site installations |
Contingency protocols for delivery failures and erection continuity
A breakdown in the logistics flow — such as a carrier breakdown on the motorway network, customs hold-ups for elements manufactured outside Switzerland, or mechanical failure of lifting equipment — immediately paralyses the erection crew if no fallback plan is in place. Without a storage area, receiving a lorry out of sequence halts assembly: a floor panel delivered before the supporting lower walls cannot be erected, and it cannot be set down on the ground for lack of compliant space.
- 1. Identification of an external overflow holding areaFrom the work preparation phase in accordance with OTConst, the contractor locates an overflow plot accessible to heavy goods vehicles (partner company yard, peripheral industrial estate, or regional carrier depot) located less than 30 minutes from the construction site, to park the vehicle in advance without congesting the work area.
- 2. Triggering non-lifting forward tasksAs soon as a transport delay is announced, the foreman switches personnel to preparatory work on the ground: marking setting-out lines on the slab below, fixing metal sole plates or anchoring angle brackets, installing air-barrier membranes, and preparing structural screw boxes.
- 3. Switching to fastening and bracing componentsThe crew completes the final fastening of panels already erected: nailing sheet metal jointing strips, tightening concrete anchor bolts to the specified torque, and securing push-pull props before resuming heavy lifting operations.
- 4. Reconfiguring the plant operating windowThe site manager immediately notifies the mobile crane hire company and the road authority to reschedule public space occupancy, thus preventing a full crew from waiting around unproductively.
The contractual management of logistical delays relies on the clauses governing the provision of execution resources under standard SIA 118. If the stoppage results from an access issue attributable to general site coordination or uncleaned access routes under the responsibility of structural work, a formal notice of interruption must be addressed to the site management to record the crane hours and personnel downtime caused by waiting for the transport.
Managing disruptions to work cadence and operational choices on the vehicle
On a cross-laminated timber (CLT) framing site, just-in-time delivery directly from the articulated lorry eliminates any ground buffer. Whenever a road obstruction delays the delivery or a stacking error reverses two floor panels, the lifting crew faces an immediate break in rhythm. The erection supervisor must then implement a fallback sequence without congesting public roads or keeping the mobile crane idle unnecessarily.
- Logistics alert and workforce reassignmentAs soon as a transport delay is announced, the foreman redirects the erection crew to pending assembly tasks: torque-tightening metal brackets on lower storeys, fully driving half-lap joint screws, or applying airtightness membranes to accessible edges.
- Releasing the lifting slotIf the lorry is delayed by more than forty-five minutes, the crane is stood down to stop hourly charges or redirected to unloading secondary packages (connector pallets, glulam spandrel beams), avoiding congestion on narrow roads.
- Managing inverted elements on the bedWhen a panel located lower down the stack must be installed before the top element due to a factory loading error, the carpenter must never set the intermediate panel down on an unverified slab: the upper element is slung, set down onto the support lorry or an adjacent certified trestle, and then reslung once the target panel is in place.
The absence of a storage area demands strict contractual discipline. Under art. 365 CO, if any circumstance jeopardises the proper or punctual completion of the work, the contractor must inform the client. This written notice protects the carpenter against delay penalties resulting from transport failures beyond their control.
Frequently asked questions
What should be done if the articulated lorry contains a CLT panel damaged in transit?
The crew leader notes the damage on the delivery note and takes immediate photographs. If the element is structural and cannot be installed, they reject the component and notify the factory for priority remanufacture. The crew adapts the erection sequence by immediately stabilising adjacent walls using push-pull props, then continues erecting independent zones identified by the engineering office to avoid a complete crane standstill.
How should one react when the police permit for using the public highway expires?
As soon as a road delay threatens completion of unloading within the authorised time window, the foreman contacts the municipal highways department or the local trade licensing police. They request an exceptional extension or direct the lorry to park in an off-street holding area outside urban dimensions. Continuing craning operations without an occupancy permit risks the immediate shutdown of the site and the impounding of the transport vehicle.
Where can an extracted CLT panel be placed temporarily to access the component underneath?
The upper panel must remain within the crane radius without touching soft ground. The carpenter sets it down directly on the lorry bed, propping it on sound timber bearers, or onto a dedicated metal trestle designed for this purpose and located within the permitted site footprint. Stacking floor panels on an unfinished subfloor whose grouting and permanent supports are incomplete is strictly prohibited.
Can a lorry that arrives out of layout sequence be turned away?
Yes, if the complete lack of ground footprint precludes intermediate unloading without accident risks or structural overloading. The site manager instructs the driver to wait in an authorised holding area until the priority consignment arrives. Accepting an out-of-order load leads to multiple crane handling operations, increasing the risk of timber damage and lifting hire costs for the company.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the sound quality of the materials they supply; if materials supplied by the client or the ground designated by the client are found to be defective, or if any other circumstance jeopardises the proper or punctual execution of the works, the contractor must notify the client immediately, under penalty of bearing the consequences (para. 3).
- OTConst art. 17protection against the collapse of construction elements or falling objects and materials: at workstations and passageways, measures must be taken to ensure workers are not endangered.