Key takeaways
- Systematic probing with a punch and drill bit reveals concealed rot in embedded timber ends.
- The timber engineer recalculates the load-bearing capacity of tie beams and principal rafters in accordance with standard SIA 265.
- Reinstating bearings on masonry often requires a bearing pad or a flitched wall plate.
- The temporary sheeting system must withstand local winds and shed water away from the building.
Probing purlin ends and inspecting structural joints
Before considering the installation of a raised floor or a timber frame, the sanitary condition of the in-situ structural timber governs all carpentry work. The most vulnerable areas remain the ends of intermediate purlins and ridge purlins embedded in masonry gable walls. Direct contact with cold stone or brick promotes capillary condensation, leading to the silent development of wood-decay fungi or wood-boring insect larvae, with no visible signs on the underside of the roof.
- Mechanical probing with a metal punch on the lower edge of embedded timbers to detect internal density loss.
- Inspection drilling with a slow, fine eight-millimetre drill bit to examine drill shavings from the core of the timber sections.
- Partial opening up of the masonry around purlin heads over at least five centimetres to check ventilation.
- Moisture content check using deep-probe needles to confirm a moisture content below twenty per cent in load-bearing members.
The examination of retained traditional trusses then focuses on the working joints. The skew notch joints at the heel of the principal rafter on the tie beam undergo severe longitudinal shear stresses. Heel slippage, the appearance of a grain check at the notch abutment, or the shearing of a tenon under historic loads make the joint unfit to carry additional weight. If the notch abutment exhibits crushing of end-grain wood fibres greater than three millimetres, the connection must be rehabilitated before transmitting new loads.
Verifying the structural safety of existing timber structures takes into account the effective condition of the residual sections, grain orientation, shrinkage cracks and the residual mechanical efficiency of the connections.
norme SIA 265
Reinstating load paths and securing temporary site weatherproofing
Raising the roof radically alters load paths. When the existing timber frame is partially retained to serve as a floor or support for new timber frame walls, wall plates and tie beams often need to be reinforced. Art. 365 CO al. 3 provides that if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the regular or punctual execution of the work, the contractor shall immediately inform the client. In carpentry, the discovery of a degraded or undersized bearing falls directly under this duty to notify.
- Heavy load-relief shoringPlace heavy-duty shoring towers or metal props under principal rafters and purlins to support all permanent loads before opening up the structure.
- Cut-back and distribution bearingClear degraded bearing areas on top of the masonry, cast a reinforced concrete padstone or install a bolted metal corbel to widen the contact surface.
- Flitching of load-bearing timbersBolt glulam flitch plates or steel profiles on either side of degraded members using threaded rods and large-diameter toothed-plate connectors.
- Anchoring new wall platesSet chemical anchor rods into the remediated capping to secure new distribution beams and wall plates receiving the storey structure.
Opening up an existing roof exposes lower floors to severe weather. Temporary weatherproofing leaves no room for improvisation. The carpenter installs heavy reinforced sheeting of at least 650 grams per square metre, secured to robust counter-battening nailed directly onto retained rafters or onto a temporary false-rafter framework. Eaves and temporary ridges must feature battens clamped with coach screws to prevent uplift from violent north winds or storm gusts.
Reinforcing connections and creating roof elevation bearings
Adding an extra storey or modifying roof geometry radically alters the lines of force within existing trusses. Transmitting shear and bending forces to bearings requires direct work on sound material once degraded zones are eliminated.
To take up additional loads without overloading existing masonry wall-head courses, the carpenter installs continuous or point-bearing members sized according to the timber engineer's specifications.
| Existing configuration | Reinstatement system | Fastening methods | Site check |
|---|---|---|---|
| Degraded embedded purlin end | Bilateral glulam or steel flitch plates | Fitted dowels and threaded rods with wide washers | Tight clamping, compliance with edge and end distances |
| Undersized or weakened wall plate | Installation of a cross-laminated timber distribution plate | Mechanical anchor bolts or chemical anchoring into the wall head | Bearing continuity, flatness under sole plate, installation of a damp-proof membrane |
| Fatigued tie-to-rafter joint | Thick steel plate gussets connected into the core | Annular ring shank nails or inclined fully threaded wood screws | Absence of residual splits, uniform tightening of the rebuilt joint |
| Heterogeneous masonry wall head | Anchored timber ground beam with non-shrink grouting | Through tie-rods anchored into the load-bearing masonry | Controlled tightening torque, verticality of load transfer |
Anchoring new wall plates or distribution beams into spandrel walls requires a rigorous analysis of the mineral substrate. Drilling must extend past deteriorated surface layers into solid masonry, followed by thorough dust removal before resin injection or anchor expansion.
Organising packing, jacking, and temporary weather protection maintenance
Reinstating loads prior to roof elevation often requires temporarily relieving truss feet or ridge purlins using hydraulic jacks. This operation demands a strict sequence to avoid shearing retained joints or destabilising underlying masonry.
- Mechanical decoupling and liftingRemoval of secondary fixings and preloading of shoring towers using synchronised hydraulic jacks. Stroke is monitored with dial gauges to limit differential deflection.
- Stripping and remediation of bearing areasCutting back deteriorated timber with a trimming chainsaw or reciprocating saw. Cleaning the load-bearing wall head, applying curative fungicide and insecticide treatments to retained elements.
- Insertion of new bearing componentsInstallation of distribution sole plates, metal corbels or glulam timber blocks. Execution of guided drill holes for dowels and tie-rods in accordance with execution drawings.
- Final load transferGradual lowering of jacks in balanced increments. Locking of anchor ironwork, checking truss plumb lines, and final securing by tightening to specified torque values.
Throughout these open-roof phases, maintaining weather protection dictates the safety of the existing structure. Heavy reinforced site tarpaulins must be fixed onto a primary structure of temporary rafters, forming a grid capable of draining rainwater clear of the working area.
Once the bearing is stabilised and the existing frame strengthened, the erection of the new timber frame can begin. Scheduling ensures that each load-transfer step occurs on a bearing that is fully cured, bolted and approved by the carpentry work supervisor.
Action required in the event of structural defects or water ingress during the site phase
The accidental discovery of a purlin end degraded by wood-decay fungi or an internal failure at a skew notch requires stopping lifting operations in the affected area immediately. The carpenter immediately sets up a temporary load-relief system using shoring towers or timber props wedged onto the floor joists below, ensuring the latter provide a bearing capable of taking the point load. This deviation from the expected state requires an immediate joint inspection record with the site management and the civil engineer responsible for the structural design.
If the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the regular or punctual execution of the work, the contractor shall immediately inform the client pursuant to art. 365 CO. In the context of an old structure, this written notice halts the technical situation prior to any underpinning attempt or flitching on existing principal rafters. The engineer must recalculate the residual load-bearing capacity and prescribe the necessary glulam reinforcement sections or replacement steel profiles before continuing with the erection of the new framework.
In the event of sudden severe weather tearing away or saturating the heavy temporary sheeting, the absolute priority is to prevent dynamic forces from transferring to the stripped timber frame and to stop water ingress into occupied floors. Mechanically reinforcing retaining battens and pumping out ponding water prevents any unforeseen asymmetrical overloading on retained ridge or intermediate purlins.
Frequently asked questions
How should an embedded wall-plate purlin end that is rotten over 15 centimetres be treated?
The purlin should be propped 50 centimetres from the wall to remove the load from the defective bearing. The deteriorated wood is then cut back using a chainsaw or chisel down to sound timber. Load transfer is restored by flitching with two pieces of construction timber bolted with threaded rods and toothed-plate connectors, or by installing a steel corbel chemically anchored into the sound masonry course.
What should be done if the retained truss exhibits deflection exceeding allowable tolerances?
Excessive deflection of the tie beam or principal rafter indicates historic creep or past overloading. The condition must be reported to the timber engineer without attempting to jack the member straight forcefully, which could shear the skew notches. The typical solution is to sister the sagging member with a new custom-cut section or install pre-tensioned metal tie rods to arrest defects without overloading the bearings.
How are new timber frame walls tied into the existing framework?
The wall-frame sole plate must bear on a floor or stiffened purlins capable of resisting shear forces and wind uplift. Mechanical fastening is achieved using anchor bolts, fully threaded structural screws or galvanised bent brackets. Precise millimetric packing beneath each stud ensures continuous contact and prevents parasitic torsion on retained historic members.
Which method should be used to anchor temporary weatherproofing against high winds?
Heavy-duty reinforced roof tarpaulins are tensioned directly onto timber lathing nailed to existing rafters, leaving no wind catch under the ridge. Simple weighting with sandbags or rubble stones is strictly prohibited, as these present major hazards of falling objects. The perimeter is systematically clamped with counter-battens screwed into the perimeter rafters to withstand unforeseen thermal wind gusts.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the sound quality of the material he provides; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the regular or punctual execution of the work, he shall immediately inform the client, under penalty of bearing the consequences (al. 3).
- OTConstprotection against collapse of construction elements or falling objects and materials: at workstations and passageways, measures must be taken so that workers are not endangered.