Safety net under purlins: the protection installed before climbing onto the roof

This chapter details the installation method for safety nets under purlins in timber framing, which must be performed from the ground or from an elevated work platform before any access at height. You will learn how to size anchor points on the timber structure, respect the regulatory overlap of net sheets, and plan the assembly in accordance with Swiss regulations.

Key takeaways

  • The safety net is installed entirely from below before any work on the timber frame.
  • Fixing is carried out on purlins or load-bearing elements sized to withstand dynamic loads.
  • A minimum overlap of the net sheets is required to ensure the continuity of collective protection.
  • Second-stage personal protection is used in the absence of a collective solution in accordance with regulations.

Sequence of execution and structural anchoring of safety nets under purlins

The fundamental rule in timber framing requires the implementation of collective fall arrest protections before carpenters access the upper structure. When installing purlins and rafters, the installation of a safety net under purlins constitutes the priority measure to secure the work area beneath the roof void. Assembly is systematically carried out from the floor below, by means of a mobile elevating work platform or suitable attachment poles. No one may climb onto the joisting or the purlin until the safety net sheet is deployed and locked.

Where it is technically impossible or too dangerous to erect a perimeter guard rail, a facade scaffolding, or a safety net or catch scaffolding, equivalent protective measures must be taken and laid down in writing with the assistance of an occupational safety specialist.

art. 29 OTConst

Net attachment requires strict attention to the strength of the supports. Anchor points are secured directly to solid timber or glued-laminated timber frame elements, such as ridge purlins, intermediate purlins, or wall plates already anchored to the masonry. It is strictly forbidden to attach suspension ropes to non-braced secondary elements such as simple battens or sarking boards. Attachment straps or tension ropes must encircle the timber section to distribute the load without risking tearing the fibres.

Anchoring and inspection criteria for nets under purlins
Inspection itemTechnical requirementOn-site check
Attachment supportMain purlin or sized sandwich beamAbsence of through-splits at the clamping point
Connecting elementAttachment strap with locking buckleCheck for wear condition and compliance label
Maximum fall heightFree fall limit according to manufacturer instructionsMeasurement of deflection under the net and low clearance

Continuity of sheets, overlap, and construction site coordination

To ensure an effective catch surface under the entire roof, the net system must cover all bays. When several net sheets are joined to span a large distance, the overlap must be executed according to good practice. Adjacent borders are connected by an all-purpose lacing rope or regularly spaced safety carabiners. The objective is to prevent any spreading of the meshes that would allow a body to pass through in the event of a fall.

  1. Material inspection on the groundCheck the annual inspection date of the nets, the condition of the polypropylene meshes, and the presence of the border mesh rope.
  2. Lifting and pre-attachmentUnroll the net sheet under the bay and raise the corners using assembly poles or from an elevated work platform.
  3. Connection and overlapConnect contiguous sheets by mesh-by-mesh lacing or approved clipping, ensuring continuity without vertical gaps.
  4. Tensioning and final lockingTension the perimeter attachment straps around the main purlins while preserving the required cushioning flexibility.

In the event of specific structural constraints preventing the complete installation of nets under purlins, the site foreman applies the provisions prescribed by the Construction Work Ordinance. The use of personal fall protection equipment is considered only as a last resort, after written validation of the work methods chosen for the construction site.

Installation of the net from the ground and checks before access

The fundamental rule in timber framing requires that collective protection be fully operational before a carpenter's first access onto the purlin system. The installation of safety nets is systematically carried out from the ground or by means of a mobile elevating work platform (MEWP). This principle of anticipation eliminates the risk of falling from height right from the installation phase of the primary structure.

  1. 1. Unrolling and inspection on the groundSpread the sheet on the ground beneath the bay to be protected. Check the condition of the meshes, the presence of compliance labels, and the absence of cuts on the edge ropes.
  2. 2. Throwing suspension ropesPass attachment ropes over the purlins using telescopic poles or from an aerial platform positioned below the joisting.
  3. 3. Hoisting and progressive tensioningHoist the sheet evenly. Adjust the tension to respect the maximum authorised deflection without exerting overtension on the edge ropes.
  4. 4. Locking anchor pointsSecure the attachment ropes to the solid timber or glued-laminated structure using locked knots or safety carabiners.
Checkpoints before authorising roof access
Inspected itemAcceptance criterionCorrective action
Potential fall heightMaximum distance beneath the purlin complies with manufacturer dataTighten the suspension ropes to raise the net
Attachment points on timberAnchorage executed on a sized load-bearing element (purlins, trusses)Move the attachment away from light trimmers or sarking boards
Mesh integrityNo broken mesh, valid annual inspection labelImmediately replace the damaged sheet

Structural attachment, net overlap, and compliance

The transfer of loads in the event of a fall relies entirely on the strength of the attachment points and on the continuity of the catch surface. In timber framing, the selection of load-bearing members for anchoring requires a prior analysis of sections and material condition to avoid any risk of structural failure under impact.

  • Anchoring to main load-bearing members: Only large-section purlins, trusses, and glued-laminated timber beams must serve as attachment points. Secondary elements such as battens or lightweight soffits are prohibited.
  • Connection of sheets: When the void to be covered requires several sheets, the overlap must be at least 1 m or the borders must be connected mesh by mesh using a compliant lacing rope.
  • Edge protection: Insert sleeves or strap protectors over the sharp edges of cut timber in order to protect attachment ropes against shearing.
  • Record keeping: The Construction Work Ordinance requires traceability of operations. The site supervisor records the installation inspection before authorising assembly of the timber frame or roof covering.

Incident management, defects, and shutdown procedures on safety nets

The safety net under purlins constitutes the essential collective protection for timber framing work. In accordance with OTConst art. 29, when other collective equipment cannot be installed, equivalent measures ensuring safety must be applied. Should a defect on the net sheet, anchor failure, or a worker fall occur, the response on the construction site must be immediate and governed by strict procedures.

  1. Securing the area and rescueAlert the designated competent person according to OTConst, rescue the worker without endangering emergency personnel, then clear and isolate the area beneath the stressed sheet.
  2. Decommissioning and structural checkA net that has absorbed the fall of a person or a heavy load must no longer be reused. It must be taken down and replaced immediately. Anchor points on the timber frame (purlins, rafters) undergo a visual and structural inspection to detect any cracks or fibre tear-out.
  3. Management of material degradationIf mesh cuts or slippage of attachment rails are detected during the daily inspection performed from the ground, access to the roof is prohibited until the affected sheet is replaced or repaired by a qualified person.

In the event of serious damage caused to the structure by a failure of the structure or anchorage that has endangered persons on the construction site, the liability of the parties involved may be invoked within the meaning of the Swiss Criminal Code (CP). Organizing prevention and checking attachments from below remain the primary guarantee for preventing any fatal accident in timber framing.

Frequently asked questions

Can a safety net under purlins that has arrested a carpenter's fall be reused?

No. A safety net that has absorbed the fall of a carpenter or sustained a significant impact must be immediately taken out of service. Dynamic stresses alter the strength of polyamide meshes and attachment ropes. The sheet must be scrapped or returned to the manufacturer for an in-depth technical assessment prior to any reuse on another construction site.

How should one react if an anchor point on the purlin shows signs of weakness?

If a solid timber or glued-laminated purlin shows splits, grain deviation, or initial tear-out at the net anchorage, access to the overlying roof area must be prohibited immediately. The attachment strap or hook must be relocated to a sound load-bearing element sized to withstand dynamic catch loads.

Who is entitled to validate the conformity of the net installation before assembly work on the roof?

The check is carried out by the competent person in charge of occupational safety designated on the construction site by the employer. This person checks from the ground the correct attachment of straps, the closure of carabiners, the overall tension of the sheet, and compliance with the overlap between the different nets before authorising access to the timber structure.

What should be done if the overlap between two net sheets has separated during the works?

Any opening in the protection system constitutes a risk of axial falling. Carpenters must immediately cease work at height above the area. From an aerial platform or an elevated work platform, the joint must be restored from the ground or at a safe height by re-lacing the coupling rope mesh by mesh.

Texts and standards cited

  • OTConstorganisation of occupational safety and health protection through the designation of a competent person
  • OTConst art. 29other fall protection measures in the event of technical impossibility to install a guard rail or scaffolding
  • CPbreach of the recognised rules of the art of building endangering life or physical integrity