Substrate, preparation and underlays: the execution reference guide
This section is intended for team leaders, foremen and site managers who need to inspect a substrate, check its condition and install intermediate layers beneath parquet flooring. It details the technical rules for floor preparation, the management of acoustic or water vapour tightness interfaces, as well as the methodical treatment of critical details, from old timber floors to stairwells.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
2 mm / 2 m
Maximum permissible flatness tolerance under the straightedge for bonded parquet
0.2 mm
Minimum thickness required for the polyethylene vapour barrier film
20 cm
Minimum watertight overlap between vapour barrier membrane strips
0.5 %
Maximum residual moisture content CM for a heated calcium sulphate screed
Technical scope of the parquet installer and limits of intervention
The parquet installer works on a finished surface to install a high-end wooden covering. Their professional responsibility begins as soon as they take possession of the substrate. They are required to rigorously verify that the acceptance conditions meet the requirements of current standards, in particular SIA 253 for bonded or floating floor coverings and SIA 181 for sound protection in buildings. Pursuant to art. 365 CO, if the designated site or the substrate provided by the client proves to be defective, the contractor is obliged to notify them immediately in order to release themselves from liability.
The trade boundary clearly separates CFC 283 from other finishing work trades. The incorporation of underfloor heating coils and temperature regulation are the responsibility of the heating installers (CFC 241). Waterproofing under tiling and the installation of mineral tiles are the responsibility of the tilers (CFC 282). Wall painting and self-levelling resins belong to the painters (CFC 272). Finally, the supply and installation of metal thresholds integrated into door frames, general joinery skirting boards and wall panelling depend on the joiners (CFC 273), while the parquet installer handles the parquet, its sound insulation and its associated surface finishes.
- What this section covers: geometric control of the substrate, assessment of the risk of rising damp, selection and installation of waterproofing films, interposition of acoustic resilient underlays, surface preparation sanding, industrial vacuum cleaning, application of bonding primers and recording of formal reservations.
- What this section excludes: creation of slope formations, heavy structural compensation smoothing compounds belonging to the screed layer, dimensional calculation of floating screeds, as well as the general contractual duty to notify developed under CFC 201.
Organization of inspection and logical preparation workflow
The preparation of a floor prior to laying parquet follows a strict chronology. Each step determines the mechanical stability of the work, its acoustic comfort and its longevity in the face of indoor climate variations. The methodical sequence of checks avoids costly repairs resulting from debonding, cupping or impact noise transmitted to neighbouring apartments.
- Geometric inspection and flatnessThe process begins by checking flatness with an aluminium straightedge. Chapter U2-01 details the permissible tolerances under the 2 m straightedge and the 20 cm ruler in accordance with standard SIA 253, as well as the limit beyond which a levelling compound must be requested from the client prior to any installation.
- Moisture barrierChapter U2-02 covers protection against rising water vapour from ground-bearing slabs or crawl spaces, specifying the required polyethylene membrane thicknesses and watertight overlaps.
- Impact sound insulationChapter U2-03 sets out the choice of underlay beneath floating parquet to meet the requirements of standard SIA 181, analyzing deformation under continuous load and footstep noise transmission.
- Preparation for bonded installationChapter U2-04 details the mechanical actions prior to bonding: keying surfaces, removing laitance on calcium sulphate screeds, industrial vacuuming and choosing compatible primers.
- Specific substrates and sensitive worksChapters U2-05 to U2-09 cover specific situations: stabilization of old nailed timber floors, waterproofing constraints and technical limits in wet rooms with a written disclaimer, level connections at door thresholds, meticulous creation of invisible technical access hatches, as well as complete recladding of stair treads and risers.
- Joint inspection formalizationThe process concludes with Chapter U2-10 by drawing up the entry inspection record. This document records ambient moisture measurements, observed tolerances and written reservations notified to the agent before starting installation.
📘 Chapters in this section 10
Flatness: tolerance for parquet flooring, straightedge measurement and mandatory smoothing compound
Check flatness with the straightedge to prevent defects before any intervention.
Substrate, preparation and underlaysThe vapour barrier: ground-bearing slab, crawl space and rising damp
Install the watertight vapour barrier to definitively neutralize the risk of wood cupping.
Substrate, preparation and underlaysThe underlay: footstep noise, impact noise to the neighbour and thickness under load
Select the resilient underlay ensuring acoustic compliance with building requirements.
Substrate, preparation and underlaysPreparation for bonding: sanding, vacuuming, primer and anhydrite laitance
Remove laitance and prepare the bond to guarantee perfect adhesion of the glued flooring.
Substrate, preparation and underlaysOn an old timber floor: board play, stiffening, panels and squeaking
Stiffen an old floor to eliminate creaking under the new parquet.
Substrate, preparation and underlaysWet rooms: what is possible, what is not, and the waiver to be signed
Identify limits in wet rooms to contractually secure the work against water ingress.
Substrate, preparation and underlaysAt the threshold: level difference, separation joint between rooms and maintained clearance
Achieve successful adjustment at thresholds while maintaining the perimeter clearance essential for expansion.
Substrate, preparation and underlaysKeeping access: hatch cut out of the parquet, frame and discreet marking
Design an invisible flush inspection hatch without interrupting the installation pattern.
Substrate, preparation and underlaysOn a staircase: step by step, add-on nosing, slip resistance and nosing wear
Clad a staircase with durable nosings ensuring safe use and mechanical strength.
Substrate, preparation and underlaysInitial inspection: records, photos, refused areas and transmission to the client
Draft the initial joint inspection record to release your liability before work begins.