Key takeaways
- SIA 253 standard makes installation conditional on climatic conditions and perfectly stabilised substrates.
- Wet trades must have cleared all their moisture before wood is brought in.
- The complete shell and roof guarantee air-tightness and prevent thermo-hygrometric shocks.
- The operational heating system running continuously ensures the equilibrium moisture content required for gluing or nailing.
The three technical ambient conditions set by the SIA 253 standard
Parquet is not an ordinary floor covering that can be installed based on the theoretical progress of the general schedule. Solid or engineered wood remains a living, hygroscopic material that constantly exchanges water vapour with the ambient air and the substrate until it reaches its equilibrium moisture content. Unloading pallets of planks into a building still saturated with mixing water or exposed to drafts risks irreversible cupping, shrinkage cracks or widespread debonding. For these strictly technical reasons, the parquet layer systematically intervenes in the final finishing work phase.
Wooden floor coverings and parquet must only be installed when the building is closed, wet work is completed and dry, and the premises have the future usage climate.
norme SIA 253
- Full completion of wet work: plasterers, tilers and painters have left the rooms long enough for renders, smoothing compounds, wall tiles and wall paints to be thoroughly dry, with no residual moisture release.
- Closed and covered building: all exterior joinery is glazed and jointed, exterior communication doors are locked, and no temporary tarpaulin replaces a glazed bay.
- Continuous heating: the final heating system is operating stably, making it possible to maintain an ambient temperature and relative humidity in accordance with the operating requirements set out in the SIA 253 standard.
The presence of other trades carrying out dusty or wet finishing work on the same level prohibits the start of installation. Likewise, measuring the residual moisture of the screed is the responsibility of the trade that poured it: the parquet layer does not perform this initial diagnosis, but formally demands the delivery of the calcium carbide measurement report certifying that the substrate has reached the prescribed threshold before authorising the delivery of the parquet.
Locking in prerequisites in the quote and managing site management pressure
On construction or major renovation sites in Suisse romande, compliance with overall deadlines frequently pushes site management to demand premature intervention by the parquet layer. If the craftsman yields to this verbal injunction without the building meeting the basic physical criteria, they bear full responsibility for future defects. The company is protected right from the tender phase by introducing clear suspensive technical clauses.
- Including prerequisites in the quoteSpecify clearly in black and white in the quote or tender that the start date of the work is conditional upon the provision of the screed heating protocol, proof of admissible residual moisture according to SIA 253 and the achievement of a stable indoor climate.
- Prior joint inspectionRecord on site, forty-eight hours before the theoretical delivery date, the surface temperature, ambient temperature and relative humidity of the air using a calibrated thermo-hygrometer.
- Non-compliance record and formal noticeIf the paints are not dry, if the building has drafts or if the heating is turned off, immediately record the situation in writing to the site management, refusing to unload the parquet.
- Schedule postponementSet the new intervention deadline from the actual date when the three prerequisites are observed and jointly verified on the construction site.
The Code of Obligations requires the contractor to notify the client without delay when circumstances jeopardise the proper execution of the work. The lack of operational heating or the persistence of moisture from plaster precisely constitutes an imperative circumstance justifying the refusal to enter the construction site. This contractual firmness protects the work against cupping and plastic deformation and guarantees the durability of oil or varnish finishes.
Joint inspection record and technical release of the premises
The entry of the parquet layer onto the construction site marks the irreversible transition from structural work and heavy finishing work to high-end finishes. This handover cannot rely on a simple oral agreement or a scheduling instruction formulated during a site meeting. Solid or engineered wood reacts immediately to residual moisture transfers by swelling, cupping or premature debonding. Therefore, access to the surfaces must be preceded by a formalised joint inspection with the site management, recording the final release of the rooms and the complete exclusion of other trades.
- Envelope closure recordCheck the actual installation and adjustment of all exterior joinery, glazing, thresholds and shading systems. The premises must be completely air- and rain-tight, without precarious temporary closing devices or tarpaulins likely to tear in the wind.
- Validation of the completion of wet workEnsure that plasterers, tilers and painters have completed their wet phases. Massive renders, roughcasts and wall smoothing compounds must show complete core drying, with no visible or measurable moisture release in the ambient air.
- Verification of thermal commissioningDemand the written certificate of functional heating activation in accordance with the thermal protocol executed by the heating installer and screed layer. The system must maintain an ambient and surface temperature complying with the requirements of the SIA 253 standard.
- Signing of the installation start reportRecord the ambient humidity values, air temperature, substrate temperature and total absence of third parties within the intervention perimeter. The handover of keys or exclusive access control is recorded on this document.
| Trade | Required prior work | Parquet layer inspection point | Immediate refusal criterion |
|---|---|---|---|
| Plastering and partitions | Smoothed, sanded and core-dry renders | Visual inspection and surface hygrometry | Presence of fresh renders or scheduled rework |
| Interior painting | Primer and finishing coats applied | Absence of damp tarpaulins and solvents | Paint touch-ups planned above the floor |
| Sanitary installations | Pressurised networks and connected appliances | Leak-tightness check at column bases | Valves open without flow or risk of leaks |
| Heating and ventilation | Regulated and monobloc installation in service | Thermal protocol record and air flow rate | Mobile direct-combustion auxiliary heater |
The requirement for a tight and temperature-controlled room strictly prohibits the use of direct-combustion heat cannons running on gas or oil. These mobile generators release massive quantities of water vapour and carbon residues into the confined atmosphere, saturating the ambient air and causing a sudden resurgence of moisture in the kiln-dried wood. If the building's final heating network is not yet operational, site management must imperatively install a temporary thermal plant connected to the hydraulic circuit or forced-air electric unit heaters.
Sanctuary protection of the installation zone and management of construction site interferences
As soon as the first packs of planks are opened for acclimatisation or the start of full-surface gluing, the workspace becomes a closed workshop. No outside personnel may walk on surfaces currently being assembled. The mineral dust generated by any drilling of false ceilings, sawing of electricians' metal profiles or walking with soles soiled by mortar instantly destroys the surface finish of bare wood and contaminates the impregnation, glue or varnishing coats.
- Physical condemnation of accesses: installation of physical barriers at door openings, application of prohibition adhesive tape and display of a sign indicating the application of fresh finishing products.
- Refusal of premature waterproof protections: strictly prohibit covering glued or varnished parquet with non-breathable plastic sheets that block evaporation and create destructive condensation.
- Immediate notification of rule breach: prompt reporting to site management of any unauthorised intrusion, releasing the installation company from liability for scratches, impact marks or surface pollution discovered subsequently.
- Continuous measurement of the indoor climate: recording by autonomous thermo-hygrometer of hygrometric variations to prove the maintenance of required climatic conditions in the event of a nighttime heating failure.
When ambient conditions deteriorate during the construction site due to a power outage, boiler breakdown or permanent draft caused by secondary trades, the parquet site foreman applies a conservatory work stoppage. The withdrawal of teams and the securing of unopened wood packages are recorded on the daily installation report. This technical rigour protects the work against late hygrometric defects whose repair would require the complete removal of the glued assembly.
Refusal of installation and management of site deviations
When one of the three prerequisites is missing during the entry inspection, the parquet layer does not compromise. Installing on a substrate that is too wet, in a permanent draft or in the middle of ongoing plastering constitutes a direct technical fault. If the windows are not installed, if heating appliances are turned off or if painters are still spraying renders, the team leader suspends wood unloading operations and documents the situation.
- Recording of ambient parametersMeasure and record air temperature, ambient relative humidity and substrate surface temperature using calibrated devices, with timestamped photos.
- Written notification of reservationsDraft a reasoned notice to site management on the same day, recalling the contractual prerequisites defined in the quote and the requirements of the SIA 253 standard.
- Adjournment and removal of equipmentPostpone the delivery of conditioned parquet or place the pallets under closed tarpaulins in a secure, dry and temperature-controlled room while waiting for the site to stabilise.
Resumption of work takes place only after verified elimination of parasite moisture sources and restarting of thermal installations in continuous operation. A new joint inspection then formalises the definitive opening of the installation workshop.
Frequently asked questions
Can installation begin if underfloor heating is running on a temporary boiler?
Yes, provided that the temporary installation ensures a stable and regulated temperature according to technical instructions. The heating activation protocol must be completed before any intervention. If the mobile boiler generates sudden variations or nighttime cut-offs, the environment is not controlled: the parquet layer refuses to start installation until final connection or proven thermal stabilisation of the substrate.
What should be done if the facade builder is still erecting scaffolding in front of unsealed glazed bays?
The construction site is not considered a closed room according to SIA 253 standard. The absence of waterproof glazing or the presence of simple plastic tarpaulins exposes the parquet to bad weather, wind and sudden variations in relative humidity. The parquet layer adjourns the delivery of noble wood. They demand the complete closure of exterior joinery by report before authorising the acclimatisation of planks on the screed.
How to justify a refusal of installation facing a painter applying a primer coat?
The application of water-based paints and renders releases large quantities of water vapour in closed rooms. This ambient humidity is rapidly absorbed by dry wood, causing premature swelling of the planks even before gluing. The parquet layer relies on the initial reservations of their quote to demand the evacuation of vapour and complete drying of wall surfaces before intervening.
Do ambient prerequisites included in the quote protect in case of construction site delays?
Perfectly. When access criteria are explicitly stated in the accepted quote, they have contractual force between the parties. If the parquet layer cannot enter the site due to lack of heating or because a screed has not been released, the delay is not their fault. Site management must bear the schedule postponement without being able to attribute contractual delay penalties to them.
Texts and standards cited
- SIA 253Installation of glued floor coverings, room climatic requirements and substrate conditions
- SIA 118General conditions for the execution of construction work and notice of defects