Key takeaways
- An average one-hundred-square-metre apartment quickly accumulates over a tonne of hardwood.
- The Construction Work Ordinance requires handling operations to be organised so as to reduce physical risks.
- Above twenty-five kilograms per package, manual handling strictly requires coordinated two-person work.
- The façade material hoist remains the preferred technical solution to preserve the integrity of stairwells.
Calculate the total mass of a batch and apply unit load limits
The transport of wooden floor coverings is frequently underestimated during the preparation of renovation or multi-family housing construction sites. A standard engineered parquet flooring with a thickness of fourteen millimetres has a surface mass of approximately eight to ten kilograms per square metre. For a twenty-millimetre solid oak parquet, this value regularly reaches fifteen to sixteen kilograms per square metre. For a one-hundred-square-metre dwelling, incorporating an installation surplus of seven to ten percent for cuts, the gross delivered mass ranges between nine hundred kilos and over 1.6 tonnes.
| Type of parquet | Common thickness | Average surface mass | Surface area per package | Indicative package weight |
|---|---|---|---|---|
| 3-ply engineered | 14 mm | 8.5 kg/m² | 2.40 m² | 20.4 kg |
| Single-strip engineered | 15 mm | 10.0 kg/m² | 1.80 m² | 18.0 kg |
| Tongued and grooved solid oak | 15 mm | 11.5 kg/m² | 1.60 m² | 18.4 kg |
| Traditional solid oak | 20 mm | 15.5 kg/m² | 1.50 m² | 23.3 kg |
| Dense hardwood solid (e.g. doussie) | 20 mm | 18.0 kg/m² | 1.40 m² | 25.2 kg |
The OTConst requires the employer to plan operations so that impairment to workers' health is kept as low as possible. In Swiss finishing work practice, Suva recommendations set an indicative continuous individual carrying threshold at twenty-five kilograms for an adult male under ideal geometric conditions. As soon as a bundle exceeds this limit, or when handling takes place in narrow stair flights, carrying must obligatorily be carried out by two people.
Deploying the material hoist and organising rolling on the landing
When the construction site does not have a lift approved by the site management, the external material hoist becomes the technical reference. Installed on an inclined ladder from the public domain or an inner courtyard, it allows bundles to be brought directly to the floor through a window or balcony. This solution eliminates human vertical effort, preserves wooden stringers, prevents chipping on step nosings and protects the freshly painted plastered walls of common areas.
- Access and parking analysisCheck the ground load-bearing capacity at the foot of the façade, municipal permits for occupation of public land and the clearance gauge of the skip through floor openings.
- Reception and unloading at the floor landingTilt the bundles from the material hoist platform directly onto a swivel-caster trolley without placing the loads on the floor.
- Rolling and distribution of indoor loadsTransport the packages using a clean, non-marking rubber-tyred trolley to the installation rooms while avoiding any point overloading of the screed.
- Acclimatisation storageStack the bundles flat, on wooden shims, distributing them along load-bearing walls in piles not exceeding one metre in height.
The landing handling trolley must be selected with care. Six-wheel platforms are preferred for crossing door thresholds smoothly, or panel-carrying trolleys adapted to the format of boards longer than two metres. The movement of loads indoors must always be carried out without damaging the unbonded screed or indenting any peripheral acoustic insulation strips.
Carrying in stairwells and paired handling thresholds
When a renovation construction site's layout prohibits the installation of a façade material hoist or the use of a service lift, transport via the stairwell remains the only supply route. For a typical one-hundred-square-metre apartment fitted with fifteen-millimetre-thick three-ply engineered wood or solid oak, the surface weight varies between eight and twelve kilograms per square metre, excluding installation accessories and glue. The complete supply of such a dwelling involves the direct transfer of over a tonne of wood across flights of steps, which generates acute muscle fatigue and increases the risk of stumbling.
Ready-to-use parquet packages have variable masses depending on the width of the boards and the density of the wood species. While small-format bundles commonly weigh between twelve and eighteen kilograms, wide-board or long-length packages frequently exceed twenty-five or even thirty kilograms. Any load exceeding twenty-five kilograms requires exclusive carrying by two workers, under penalty of critical lumbar overloads in narrow or winding stairs.
| Type of wood flooring | Mass per m² | Average weight per package | Cumulative gross mass (100 m²) | Required carrying method |
|---|---|---|---|---|
| 2-ply engineered (10 to 11 mm) | approx. 6 to 7 kg | 14 to 18 kg | 650 to 700 kg | Individual with straps or relays |
| 3-ply engineered (14 to 15 mm) | approx. 8 to 9 kg | 20 to 25 kg | 800 to 900 kg | Individual (limit) or paired |
| Solid oak parquet (20 to 22 mm) | approx. 15 to 16 kg | 28 to 34 kg | 1500 to 1600 kg | Mandatory pair (2 installers) |
| Polyurethane / silane glue (buckets) | approx. 1.2 kg / m² | 15 to 18 kg | 120 to 150 kg | Individual with balanced grip |
- Binomial synchronisation on flightsThe worker positioned upstream moves backwards or three-quarters turned while the downstream worker pushes the load towards the upper floor. Both operators pace their walking rhythm to avoid vertical jolts that destabilise footing on step nosings.
- Positioning and holding of loadsThe package is held by its ends with anti-slip gloves or stabilised using carrying straps crossed under the cardboard. Loads must never rest directly on the top of a shoulder to preserve balance in corners.
- Intermediate drop on resting landingsEach intermediate landing is used to briefly place the package down to straighten the upper body. The bundle is placed flat without twisting the torso, then picked up with controlled knee flexion before tackling the next flight.
Compliance of the access route and temporary storage on the floor
The Construction Work Ordinance requires strict planning of vertical traffic and access safety to prevent falls of workers and materials. Raw concrete stair flights or temporary metal structures must be free of any clutter before transport begins. Rubbish, power supply cables and packaging from other trades must be completely cleared from walking areas to provide a clear passage of at least sixty centimetres in width.
The use of manual trolleys remains reserved for horizontal landings and level circulation. As soon as leaving the stair flights or the floor landing, the loads are tilted onto a platform trolley with soft polyurethane or non-marking rubber bandage wheels, so as not to mark thresholds or recent screeds. These devices must have a parking brake system to immobilise the load during unloading and prevent any involuntary rollback towards the stair opening.
Once inside the dwelling, parquet bundles must never be stacked in a single column against a single partition or in the centre of the same span. Concentrating a tonne of materials over two square metres creates an unacceptable point overload for lightweight floors, floating screeds or technical raised floors. The team leader organises the immediate dispatching of the bundles: these are stored flat, in piles of four to five cartons maximum, distributed along the load-bearing walls of each room where the parquet will be laid. This distribution limits mechanical stresses on the supporting structure and facilitates the hygrometric acclimatisation of the boards before gluing operations.
Stopping procedure and fallback solutions in the event of logistical failure
On a renovation or multi-family housing construction site, the inability to use the material hoist immediately turns the supply into a critical situation. Faced with a mechanical breakdown, a refusal of permission to encroach on a courtyard, or an inaccessible opening, the reflex of dumping the entire load into the stairwell manually constitutes a site management error. One hundred square metres of multi-layer or solid parquet represent between 1000 and 1600 net kilograms, not counting glue buckets and possible self-levelling compounds. Imposing this repeated manual carrying in a winding staircase directly opposes the OTConst requirements relating to health protection and the prevention of physical injuries.
- Securing vertical accessesProhibit the improvised use of unsecured or cluttered emergency stairs. Check the emptiness of intermediate landings to rule out any point overload on lightweight flooring.
- Deployment of a mechanical alternativeDemand the mobilisation of a façade winch complying with the machinery safety ordinance or an electric tracked stair-climbing hand truck for unit packages weighing over twenty-five kilograms.
- Reorganisation of team rotationsIf residual passage via the stairs proves temporarily unavoidable for a few light packages, enforce the systematic pair, split the batch into batches of two hundred kilograms and intersperse layout planning phases.
Forced transport in an emergency invariably leads to back accidents, damage to step nosings and chipping of board tongues. If the site management refuses to provide a replacement lifting device, the company confirms its technical impossibility of supplying in accordance with good trade practice and requests a formal rescheduling of the intervention plan.
Frequently asked questions
From what weight must a parquet package imperatively be handled by two people?
According to health protection directives and Suva recommendations, the manual handling threshold for an adult worker is set at twenty-five kilograms under optimal conditions. As soon as the package exceeds this mass, or when handling takes place in a narrow staircase requiring torso twisting, lifting strictly requires the work of two workers or the use of a suitable mechanical lifting device.
How to temporarily distribute a tonne of parquet on a slab before installation?
A tonne of parquet concentrated in the same place risks exceeding the permissible live load of the floor. Stacking a complete pallet in the centre of a room must be prohibited. The rule requires dispatching bundles in piles of a maximum height of six to eight units, distributed along load-bearing walls or above main beams, taking care to clear the circulation corridors necessary for the transfer trolley.
Does the façade material hoist require a municipal permit on a Swiss pavement?
Yes. The installation of a façade material hoist or an inclined ladder encroaching on the public road domain or a municipal pavement requires an official permit for increased use of the public domain issued by the municipal police or the competent public works department. The device must be accompanied by standardised road signage, sealed pedestrian perimeter demarcation and protection against falling objects in accordance with OTConst requirements.
Which trolleys should be preferred for rolling packages on a finished landing?
On already finished floor surfaces or building landings, the use of steel workshop pallet trucks with rigid polyamide rollers is formally banned to avoid any indentation or scratching. Only manual platform trolleys equipped with wheels featuring non-marking elastic rubber tyres or soft polyurethane are used. The rolling deck must be equipped with side panels to prevent the lateral sliding of board bundles.
Texts and standards cited
- OTConstOrdinance on the Safety and Health Protection of Workers in Construction Work, providing for work planning and the prevention of fall risks and physical injury
- OMachOrdinance on Machinery Safety, governing the essential safety requirements applicable to lifting devices and site material hoists
