🧱 CFC 283Moisture in timber and in the roomChapter 9 of 10 in the section

Storage: flat, dry, away from cold walls, and not before wet trades are finished

This chapter provides the method for securing parquet supplies: refusing premature delivery on a damp slab, checking the storage room climate according to SIA 253, organising flat stacking on battens, and recording the wood moisture content as soon as the packages arrive.

Key takeaways

  • Refuse delivery as long as plasters, paints and screeds are releasing their residual moisture.
  • Demand a closed, glazed, heated room with controlled air humidity.
  • Stack strapped packages flat on square timber, kept clear of the floor and walls.
  • Systematically measure the moisture content of the boards and the room climate upon unloading on site.

Schedule the delivery time after the water from the wet trades has evaporated

Delivering solid or engineered parquet flooring to a construction site where screeds are still drying constitutes a serious technical error. Wood is a hygroscopic material that continuously balances with the water vapour contained in the ambient air. During the screed-pouring, plastering or paint-spraying phases, the indoor atmosphere often approaches saturation. Board packages stored in such an environment absorb this residual moisture through carton joints or through non-waterproof packaging films. The wood swells even before installation, which will inevitably cause severe cupping or structural defects after shrinkage caused by the heating being turned on.

Wooden flooring must only be delivered and installed when the wet construction works are completed and the moisture of the substrates as well as the climatic conditions of the room meet the prescribed requirements.

norme SIA 253

In construction practice in Western Switzerland, supply planning requires close coordination with site management. The site manager or parquet foreman must demand the prior transmission of drying reports drawn up by the preceding trades. Even though the official measurement of the screed moisture content is the responsibility of the screed layer, the parquet installer must verify on paper that the screed is declared ready to receive the flooring and that the heating-up protocol is completed before giving the green light for factory dispatch. Early delivery under the pretext of freeing up a warehouse or arranging a transport schedule exposes the company to costly disputes.

Site conditions prior to parquet delivery
Site elementMandatory state before deliveryRisk in case of non-compliance
Liquid or traditional screedHeating-up protocol completed and compliant acceptance reportMassive moisture ingress from underneath the pallets
Plasters and wall rendersThoroughly dry surfaces, evaporation phases completedSaturated atmosphere causing premature swelling of the boards
Building envelopeWindows installed, final glazing, air tightness ensuredDamp draughts, condensation and rainwater ingress
Heating systemOperational and capable of maintaining a regulated climateCooling of rooms below the dew point

Set up the storage area and record moisture upon receipt

The room designated for storing parquet elements must offer climatic characteristics identical to those of the future living rooms. Uninsulated garages, basements without forced ventilation, technical rooms or rooms open to the weather are strictly prohibited. SIA 253 specifies a relative air humidity between forty and sixty percent, combined with a minimum ambient temperature of eighteen degrees Celsius. These values must be stabilised several days before the materials enter and maintained without interruption until the end of the construction work.

  1. Preparation of the floor baseCarefully clean the substrate and roll out a thick polyethylene film to cut off any rising residual moisture from the slab or screed.
  2. Installation of bedding battensArrange dry and perfectly planed battens, spaced at a maximum of fifty centimres, to provide a ventilated air gap of ten centimres under the first row of packages.
  3. Cross or regular flat stackingStack packages strictly flat, without overhang, maintaining a setback of at least fifty centimres from peripheral walls or raw concrete walls.
  4. Retention of original packagingLeave packages closed and strapped in their airtight factory shrink-wrap until the exact moment of installation to prevent asymmetrical moisture exchange.

Upon unloading, the team leader or parquet installer carries out the mandatory acceptance check. Wood moisture is measured using a calibrated pin moisture meter or a capacitive device calibrated to the density of the species concerned. Measurements are taken at the core of several packages sampled at random from the delivery, by slightly slitting the protective film which must be resealed with tape immediately after measurement. Values must correspond to normative ranges in Western Switzerland, i.e., generally a moisture content of eight to ten percent for solid or engineered boards intended for a heated interior.

Rules for flat stacking and insulation from cold walls

Unloading parquet packages on site requires rigorous organisation of buffer storage. Solid or engineered boards must never rest directly on the raw floor or cement screed, even if surface-dry, nor be stood vertically against a partition. Vertical support causes creep deflection under the wood's own weight, which the installer will no longer be able to correct during installation. Packages must rest flat, in their original waterproof film, on regular battens or rigid pallets. These supports must have an identical thickness, be spaced at a maximum of 50 centimres and be strictly plumb-aligned to transmit loads without warping intermediate packages. This arrangement guarantees sub-stack ventilation and eliminates any contact with potential water splashes on the floor.

The placement of the stacks in the room determines the dimensional stability of the wood. Uninsulated facades, window sills and cold concrete shear walls create negative thermal radiation and local relative humidity higher than the average room ambiance. Leaning packages against an external wall creates a cold spot conducive to condensation under the plastic film. Boards facing the masonry absorb moisture through capillarity and warp into a cupped shape. Storage stacks must strictly occupy the centre of rooms, away from draughts, forced ventilation ducts and direct sunlight passing through glazed bays.

On-site storage methods and geometric risks for parquet boards
Storage configurationPhysical effect on woodExecution rule
Packages stored verticallyIrreversible longitudinal bending under the boards' own weightStack flat on regular cross battens spaced at most 50 cm apart
Packages placed directly on the screedRising residual moisture via condensation under packagingElevate by at least 10 cm on planed battens or dry pallets
Stacks pressed against a perimeter wallLocal moisture gradient, condensation and asymmetrical cupping of boardsMaintain a free ventilation corridor of at least 50 cm around the stock
Packaging opened upon receiptImmediate reabsorption of ambient water vapour and premature swellingKeep plastic films hermetically sealed until actual installation

Contradictory thermo-hygrometric inspection and management of non-conformities

SIA 253 strictly makes the introduction of parquet conditional upon the complete and verified completion of wet trades: plastering, rendering, smoothing compounds, tiling and initial coats of paint. The parquet installer does not produce the residual moisture measurement of the screed, which is the screed layer's responsibility, but must obligatorily request and record the carbide measurement report prior to any delivery to the installation rooms. The building must be completely enclosed, glazed and heated, with an ambient temperature between 17 and 22 °C and a stabilised relative humidity between 30 and 60 %. Premature delivery in a volume whose mixing water is still evaporating immediately saturates the wood with water vapour with no possibility of escape.

  1. Room climate checkMeasure air temperature and relative humidity using a calibrated thermo-hygrometer in the centre of the storage area, away from draughts.
  2. Inspection of package conditionCheck the integrity of shrink-wrap covers and protective cartons: refuse any torn, deformed, damp or site-splashed package.
  3. Wood moisture measurementTest several random boards using a resistance pin meter with insulated pins, driven parallel to the fibres into the core of boards sampled from different packs.
  4. Recording on the transport noteRecord the wood moisture mass values, ambient temperature and room humidity rate on the slip with the carrier's joint signature.

When the measured wood moisture content deviates from prescribed tolerances or ambient humidity exceeds 60 %, the team leader records detailed reservations in writing. If the carrier unloads the material anyway, the batch is segregated and isolated in a sound room without opening the protective covers. The parquet installer sends a written notice to site management, reiterates the climatic requirements of SIA 253 and adjourns work until a healthy, dry indoor climate is restored. Accepting water-impregnated packs or tolerating storage in a damp building commits the installer's full liability for subsequent defects such as cupping, delamination or substrate detachment.

Management of non-conformities and fallback measures in the event of a moisture incident

When parquet packages are deposited on a site where plasters are fresh or the screed is not dry, the wood insidiously absorbs ambient vapour, including through micro-perforations in the shrink-wrap packaging. This moisture reabsorption leads to premature board deformation, edge cupping and internal stresses incompatible with subsequent regular assembly. Faced with a delivery forced too early by the site management schedule, the parquet site manager must refuse unloading in these rooms and have the clear incompatibility of environmental conditions recorded.

  1. Joint inspection record of ambient parametersMeasure the relative air humidity and room temperature using a calibrated thermo-hygrometer. Check the moisture content of the wood boards on a representative sample of packages in the presence of site management, then record the values in the site log with reference to SIA 253.
  2. Emergency transfer to a fallback locationIf the building has no closed, temperate room sealed against the residual moisture of other trades, arrange for pallets to be returned to a secure warehouse. This transport and external storage shall be the subject of an immediate written confirmation to protect the company's liability.
  3. Drying period and requalification of the batchBefore resuming installation, let the packages stabilise in an environment between forty and sixty percent relative humidity. A new complete moisture reading validates whether the boards have regained their equilibrium moisture content without geometric alteration.

The hasty recourse to direct-combustion site heaters or air dehumidifiers pushed to maximum often worsens the incident by aggressively drying board edges while trapping core moisture. Such thermal stress creates final shrinkage cracks and destroys the tongue-and-groove joint. When deformations exceed permissible tolerances, the pure and simple replacement of the supply is required, with the extra cost charged to the party that ordered premature delivery onto a damp substrate or environment.

Frequently asked questions

Can parquet be stored on site if the screed was poured three weeks ago?

No, this is strictly prohibited until the screed has reached its permissible residual moisture and the measurement report has been validated. Three weeks after pouring, the massive evaporation of residual water saturates the ambient air. Storing boards in such an environment, even in sealed packaging, causes immediate swelling of the wood. Storage on a slab or screed is only considered after complete completion of drying and wet works.

How to react if the carrier deposits the parquet pallets under an external shelter?

Unloading must be refused or the immediate return of the pallets ordered. A simple external canopy or porch offers no protection against morning fog, ambient hygrometric variations or rainwater splashes. Solid or engineered parquet boards must stay in an enclosed, frost-free room, heated between eighteen and twenty-two degrees, in accordance with the requirements of SIA 253, under penalty of rendering the wood unfit for installation.

Why is it essential to maintain a free space along cold walls?

Exterior perimeter walls have a surface temperature significantly lower than that of the ambient air. When a parquet package is placed directly against these cold masonry walls, the dew point phenomenon generates condensation water on the back and under the packaging plastic. Maintaining a gap of at least fifty centimres allows continuous air circulation and prevents mould as well as asymmetrical deformation of the end boards.

Should parquet packages be opened several days before installation to acclimatise the wood?

No, this old practice no longer applies to factory-finished parquet delivered in sealed shrink-wrap film. The boards are conditioned at the factory to a precise equilibrium moisture content for a standardised indoor climate. Opening packaging in a building whose climate is not perfectly stabilised exposes the wood to uncontrolled dimensional variations. Packages must only be opened at the exact moment of installation in ready rooms.

Texts and standards cited

  • norme SIA 253Requirements for the installation of resilient and textile floor coverings, and parquets