🧱 CFC 283Substrate, preparation and underlaysChapter 10 of 10 in the section

Initial inspection: records, photos, refused areas and transmission to the client

Upon arrival at the construction site, ten minutes of methodical inspection protect your liability before unloading the bundles of wood. You will learn to thoroughly check the six critical points of the substrate, record each anomaly using dated and geolocated photographs, and then transmit a formal notice of anomaly on the same day to the site management to refuse access to non-compliant areas.

Key takeaways

  • The initial visual and climatic check governs the guarantee derived from standard SIA 253.
  • Six specific points must be checked methodically before storing a single package of parquet.
  • Each disputed area is the subject of sharp photographs with a metric reference and unalterable timestamp.
  • The written notice of anomaly must reach the site management on the same day with reservations.

Initial inspection checklist: six points to check before opening a package

Before unloading the bundles of wood or spreading the adhesive, the parquet layer assumes technical liability from the moment they take possession of the premises. According to the recognised rules of standard SIA 253, the laying craftsman is responsible for carefully examining the substrate to verify that it is suitable for receiving the planned parquet. This methodical visual and metrological examination takes only about ten minutes per room, but it constitutes an essential bulwark against defects caused by hidden flaws or pre-existing disorders.

The six essential points of the initial inspection checklist
Checked pointVerification toolAlert or refusal criterion
1. Ambient climateCalibrated thermo-hygrometerAir temperature below 18 °C or relative humidity outside the permissible range of 35% to 65%.
2. Cohesion and cleanlinessScratch sclerometer and broomPresence of friable laitance, powdery plaster residue or formwork oil stains.
3. Cracking and jointsCrack gauge and straightedgeThrough cracks not stapled with resin or disregarded screed expansion joints.
4. Screed documentationVisual examination of reportsAbsence of the official first heating protocol or the carbide moisture measurement record.
5. Thickness recessesRigid folding rule and spirit levelIncompatible level differences at door thresholds, French windows and tile junctions.
6. Enclosed and weather-tight buildingInspection of exterior joineryAbsence of installed glazing, continuous draughts or ongoing wet work in the same space.

Mechanically, a quick test with the scratch sclerometer makes it possible to detect a chalky surface or a burnt screed. The presence of cement laitance prohibits any direct bonding without prior sanding to remove the laitance. Similarly, each expansion joint of the structural work or screed must be located to ensure it is correctly transferred into the laying pattern.

The parquet layer does not produce the reference moisture measurement of the screed themselves, nor do they manage the heating, which falls under the responsibility of the screed layer. On the other hand, the parquet layer must strictly demand these written reports before starting any installation. If the complete heating protocol is missing or if the carbide measurement record is lacking, the work must be declared not ready to receive the parquet.

Timestamped photographs and written notification: formalising the zone refusal

A merely verbal complaint transmitted on the construction site to another trade has no legal value in the event of a dispute. As soon as a non-conformity appears during the initial inspection, the parquet layer must demarcate the defective sector and establish material proof of it. Digital photography thus becomes your primary evidentiary means, provided it complies with a rigorous protocol of framing and technical legibility.

  • Take an overview locating the defect in the room with a fixed architectural reference such as a window or a wall corner.
  • Produce a sharp close-up shot incorporating an unfolded folding rule or a millimetre gauge to precisely dimension the defect.
  • Verify the activation of the timestamp and geolocation metadata recorded directly in the image file.
  • Visually mark the refused area on the floor with construction site tape or chalk to prevent any accidental installation.

The written transmission to the client or site management must take place on the very day of the inspection. This formal email, supplemented if necessary by registered mail in accordance with the customs of standard SIA 118, records the suspension of operations on the non-compliant surfaces. The parquet layer details the observed anomalies therein, attaches the supporting photographs and makes the resumption of work conditional on the certified restoration of the substrate.

The written notification expressly mentions the incompatibility of the substrate with the requirements of standard SIA 253. By formally suspending installation on defective surfaces and requesting written instructions, the parquet layer preserves all their warranty rights. If the client nevertheless demands the continuation of work without prior repair, they alone assume the risk of a future defect linked to the substrate.

Transmission of the report to the client and management of zone refusal

The initial inspection report has legal and technical value only if it leaves the construction site circle to reach the site management and the client in evidentiary form. When the parquet layer identifies an anomaly on the screed during the initial inspection, visual delimitation is not enough. The transmission of the documented report must take place on the very day of the visit, by official email supplemented if necessary by registered mail, in order to freeze the chronology of interventions and prevent a third party's delay from being blamed on the flooring layer.

The written transmission must precisely identify the lot concerned, the floor, the room and the exact surface area subtracted from the intervention. According to the principles of the Code of Obligations and the guidelines of standard SIA 253, the contractor points out the defects of the supplied substrate that compromise the good performance of the parquet. This notification suspends the obligation to install on the incriminated portion. As long as the reported defects are not corrected by the responsible trade, the area remains under the exclusive responsibility of the site management.

Contractual and practical consequences of reservations issued during the inspection
Defect noted on screedImmediate action by the parquet layerSite management obligationContractual status of the zone
Flatness outside local tolerancesMarking hollows or bumps with grease chalk, dated photographOrder for remedial work to the screed layer or validation of a levelling addendumFrozen zone, execution deadline suspended for the room
Excessive residual moisture in the protocolRefusal to supply wood packages to the roomMaintenance or relaunch of ventilation and drying heatingTotal ban on installation, risk of major defect
Through crack not bridgedTransfer to plan and notification of the risk of delaminationPrescription of a resin bridging with metal staplesPartial refusal limited to one metre on either side of the crack
Underfloor heating not stabilisedRequirement for the complete first heating protocolDelivery of the document signed by the heating engineer and managementBlocked zone until compliant thermal curves are obtained

Check of the lifting of reservations, joint countersignature and resumption of installation

The resumption of work on a surface initially refused can never result from a simple verbal agreement or tacit observation. The parquet layer engages their work guarantee as soon as they begin gluing or floating the boards. It is therefore up to the team leader to carry out a methodical follow-up inspection as soon as the completion of remedial work is announced by the site management. This second visit exclusively validates the disappearance of the non-conformities noted in the initial document.

During this second inspection, the practitioner checks the disputed points point by point. If levelling has been carried out by the screed layer, surface adhesion, surface cohesion and complete drying of the levelling product must be verified. If a crack has been injected, the parquet layer ensures the perfect flushness of the staples and the absence of movement under stress. Standard SIA 253 serves as a reference to assess whether the rectified substrate now meets the required conditions to receive solid or engineered wood flooring.

  1. On-site confrontation of remedial workVisual and mechanical examination of corrected areas in the presence of the site manager or the author of the remedial work, two-metre straightedge and surface hardness test in hand.
  2. Joint photographic recordingNew series of timestamped photographs framed from the same angles as those of the initial initial inspection report, showing the corrected state of the substrate.
  3. Signature of the reservation lifting addendumEstablishment of a reservation lifting voucher countersigned by the site management, expressly authorising the start of parquet work on the remediated area.
  4. Integration into the site binderDigital and paper archiving of the entire file including the initial inspection report, notice of defects emails, photos before and after repair, as well as the work resumption sign-off.

This rigorous formalism protects the entire execution chain. In the event of a subsequent dispute concerning acoustic defects, shrinkage cracks reflected in the facing or peeling linked to a powdery underlay, the substrate reception file constitutes the master piece of expertise. It demonstrates that the craftsman has exercised their duty of diligence in accordance with Swiss rules of the art, from site access to final implementation.

Construction site blockage: arbitration and management of persistent refusal

When the initial inspection highlights a non-compliant substrate according to standard SIA 253 and the site management refuses to sign the report or demands the immediate installation of parquet boards to keep to the schedule, the parquet layer faces a crisis situation. Yielding to a simple oral injunction transfers full liability for future defects — cupping, peeling, joint cracking or rotting — onto the installation company. The trade rule dictates formally refusing intervention on the disputed area and recording the technical impossibility of starting the parquet flooring work.

  1. Written notification of partial interruptionTransmit a reasoned notice on the same day to the site management and the client, recalling the measured values, the discrepancies observed compared to standard SIA 253 and the dated photographs of the refused areas.
  2. Joint recording or official reportIf the client disputes the measurements or refuses any dialogue, have the condition of the substrate recorded by an independent expert or a public officer before any alteration of the premises.
  3. Securing materialsStore the parquet packages in a sound and heated room, protected from splashes and ambient humidity, or organise their withdrawal if acclimatisation conditions cannot be guaranteed.
  4. Monitoring corrective measuresDemand written communication of the completion of remedial work carried out by the responsible trades before organising a joint control visit for the lifting of reservations.

Targeted site interruption due to an unsuitable substrate protects the work as well as the company's profitability. By applying the procedure provided by standard SIA 118 and the Code of Obligations, the craftsman demonstrates professional rigor: the time taken to secure the initial reports defuses financial disputes during final billing.

Frequently asked questions

What should be done if the site management demands installation despite a moisture content outside tolerance?

The parquet layer must formally refuse to carry out the installation in this sector. They confirm this refusal on the same day by a written notice mentioning the measured values, the reference to standard SIA 253 and the risks incurred of parquet degradation. Acceptance under duress would engage their liability for defective work, even if an oral order was formulated by the site management.

Who bears the costs induced by the remediation of the refused substrate?

Remedial costs fall exclusively on the trade that supplied the defective substrate or on the client depending on the contracts. The parquet layer does not assume any cost for accelerated drying or heavy levelling. If the interruption generates unnecessary travel or unplanned labour immobilisation, these services are subject to immediate notification for billing on a time-and-materials basis or as additional work.

What visual references must appear on the photographs of the initial inspection report?

Each snapshot must include a metric reference, such as a folding rule or a control ruler, placed directly next to the non-conformity. The plan must incorporate the room number, the reference axis of the architect's plan and a temporal identification element. The image must clearly show the measuring device displaying the measured value or the crack observed on the mineral substrate.

How to react if the site management is absent on the day of taking possession?

The craftsman carries out the check of the six key points alone upon arrival on site. They record their observations on the initial inspection checklist, take the necessary photos and send the completed document electronically with acknowledgement of receipt before the end of the working day. Areas deemed non-compliant are immediately marked to prevent any premature installation.

Texts and standards cited

  • norme SIA 253Installation of wooden flooring and parquet, requirements relating to substrates and ambient conditions
  • norme SIA 118General conditions for the execution of construction work, notice of defects and management of interruptions