Key takeaways
- The ambient temperature must be maintained between 18 °C and 22 °C throughout the installation.
- The relative humidity of the ambient air must strictly remain between 40% and 60%.
- Standard SIA 253 requires checking climate stabilization before unpacking the boards.
- Any thermo-hygrometric reading must be recorded on the daily report and validated by the site management.
The two reference climate brackets according to Swiss rules of the trade
Wood is a hygroscopic material whose dimensions vary continuously as a function of water vapour exchanges with the ambient air. Installing solid or multi-layered boards in a room where the climate is not stabilized exposes the work to immediate dimensional defects. From the first hours following the opening of packages, air that is too dry causes rapid shrinkage resulting in longitudinal cracks, open joints or surface cracking. Conversely, excessive ambient humidity leads to swelling of the boards, pronounced cupping along the edges, or even complete lifting of the surface due to shear failure of the adhesive film.
Wooden floor coverings must be installed in heated and enclosed rooms enjoying a stable interior climate corresponding to the future conditions of use.
norme SIA 253
To ensure the hygrothermal equilibrium between the delivered wood and the building atmosphere, Swiss practice relies on two rigorous tolerance windows. The air temperature must be between 18 °C and 22 °C, without sudden day-night fluctuations. At the same time, the relative humidity of the air must lie within the range of 40% to 60%. A temporary tolerance of up to 65% relative humidity is permitted only for certain very stable European hardwood species during the summer period, provided that the rate does not drop abruptly afterwards.
| Ambient parameter | Compliant range | Risk in case of under-run | Risk in case of over-run |
|---|---|---|---|
| Air temperature | 18 °C to 22 °C | Slowing down or blocking of adhesive curing, condensation on the floor | Premature drying of polymer or silane adhesives, loss of wetting |
| Relative air humidity | 40% to 60% | Accelerated shrinkage, appearance of open joints, wood cracking | Swelling of boards, cupping of edges, shear stresses |
| Substrate surface temperature | 15 °C to 18 °C minimum | Poor adhesion of primers, condensation under the adhesive layer | Excessive evaporation of solvents or constitutional water from adhesives |
Measurement methodology and recording of the reading prior to opening packages
Checking the ambient climate cannot be improvised by guesswork upon entering the room. The parquet flooring team leader must carry out a methodical instrumental measurement in the centre of each installation zone, at a height between 1.0 m and 1.5 m above the finished floor. Probes must imperatively be kept away from direct draughts, glass facades exposed to solar radiation and active heating units to avoid any biased reading.
- Acclimatisation of the devicePlace the calibrated electronic thermo-hygrometric device in the centre of the room at least 15 minutes before taking notes to stabilise the capacitive sensors.
- Reading of air valuesRead and note the temperature in degrees Celsius as well as the stabilized relative humidity percentage displayed on the screen.
- Dew point checkCalculate or read the dew point temperature on the device to ensure that the floor surface temperature is at least 3 degrees above this critical threshold.
- Surface temperature measurementMeasure the screed surface with an infrared contact thermometer to validate compliance with the minimum threshold prescribed for adhesive application.
Once the values have been recorded, written logging constitutes the parquet layer's legal and technical protection. If the indicators fall outside the tolerances set by standard SIA 253, the parquet packages must under no circumstances be opened or unpalletised. Factory-wrapped elements remain hermetically sealed so as not to absorb excessive moisture or, conversely, not to dry out prematurely in too arid an environment.
Wood deformation kinetics and mechanical stresses under non-stabilized climate
As soon as a parquet board leaves its sealed packaging, its hygroscopic exchanges with the ambient air start without delay. The wood instantly seeks its equilibrium moisture content in relation to the temperature and water vapour pressure of the room. When the relative humidity range prescribed by standard SIA 253 is not respected at the time of unpacking, the moisture gradient between the exposed surface and the underside in contact with the adhesive or substrate creates immediate differential stresses. These internal strains are exerted even before the adhesive has completed its mechanical and chemical cross-linking.
| Observed climate deviation | Physical reaction within 24 to 48 hours | Consecutive defects after commissioning |
|---|---|---|
| Relative humidity above 65% (surplus vapour) | Immediate transverse swelling of edges, pressurisation of joints, convex bending of solid boards through surface water absorption. | Lifting of entire spans, tearing of the adhesive bed on screed, irremediable crushing of edge fibres and longitudinal cracking. |
| Relative humidity below 35% (environment too dry) | Brutal shrinkage of surfacings, concave bending (cupping), transverse tensile stress on glued joints or tongue-and-groove profiles. | Appearance of premature shrinkage cracks, delamination of the wear layer on engineered wood, peeling of board ends. |
| Ambient temperature below 15 °C | Drastic slowing down or blocking of polymer or polyurethane adhesive curing, excessive viscosity hindering the crushing of ridges. | Incomplete adhesion to the substrate, formation of voids under boards favouring squeaking and unevenness under traffic. |
| Ambient temperature above 25 °C | Greatly reduced open time of adhesive, early evaporation of primer solvents, ultra-fast skinning before rolling. | Adhesion failure due to dry skin on adhesive, acoustic bridges due to lack of continuous transfer, lack of final flatness. |
The behaviour of multi-layer engineered parquet differs from that of solid parquet: its central core and backing limit overall dimensional variation, but air that is too dry induces violent shear stresses at the gluing interface of the noble veneer. On solid wood, cupping occurs within a few hours if the air is saturated, with the upper face absorbing ambient humidity while the glued lower face remains momentarily sealed. This dimensional asymmetry generates vertical lifting forces capable of shearing fresh adhesive peaks or leading to definitive unevenness from the very first night.
Management of climate non-conformities, conservatory measures and stabilization
When the recorded reading prior to installation highlights values located outside the limits of standard SIA 253 (temperature between 18 °C and 22 °C, relative air humidity maintained between 35% and 65% depending on the destination of the premises), the parquet layer interrupts the implementation chain. Opening packages in the hope of acclimatising wood to a defective environment constitutes a heavy error: this manoeuvre loads the wood with undesirable moisture or dries it out excessively, guaranteeing a structural defect upon return to normal operating climate.
In a situation of non-conformity noted by the thermo-hygrometric device, technical management imposes the following actions:
- Maintenance of parquet packages sealed and strapped, stored flat on battens in the centre of the room, away from glass facades and cold walls.
- Immediate notification of installation stoppage to the site management, recorded in writing with mention of measured values (temperature, relative humidity and time of reading).
- Requirement to commission compliant technical installations: electric condensation dehumidifiers to lower relative humidity, or regulated electric warm-air heaters to raise ambient temperature.
- Observance of a stabilization period of at least 48 to 72 hours under controlled climate before executing a new contradictory check.
The parquet layer's responsibility extends to maintaining these conditions until the sanding and finishing application phases. A water-based varnish applied in an atmosphere exceeding 65% relative humidity undergoes slowed drying which whitens the film by trapping water, while a natural oil applied below 18 °C penetrates poorly into the wood cellular network, altering the mechanical surface resistance of the work.
Stoppage protocol and traceability in case of non-compliant atmosphere
When the thermo-hygrometer indicates an out-of-tolerance atmosphere on the morning of installation — temperature below 18 °C or relative humidity outside the 40% to 60% range prescribed by standard SIA 253 —, the parquet layer's reflex consists in suspending the opening of packages and gluing. Installing parquet on a construction site that is too humid or too dry condemns the floor in the short term. Lateral crushing stresses or excessive shrinkages appear from the first weeks of heating or ventilation.
- Contradictory measurement and photographyRecord relative humidity and ambient temperature in the middle of each room, one metre from the floor, as well as the screed surface temperature. Photograph the values indicated on the calibrated device framing a fixed element of the room.
- Drafting the interruption reportRecord exact values on the daily construction report. Draft a notice pointing out the impossibility of carrying out the installation according to the rules of standard SIA 253 and specify the technical risks of cupping or tearing.
- Transmission to site managementTransmit the document the same day to the site management and the client. Agree on a new check after thermal stabilization by building heating or controlled dehumidification.
- Securing materialsStore unopened packages in a healthy closed room, elevated from the raw floor and sheltered from outside air infiltrations. Refuse any oral instruction aiming to force installation without climate restoration.
The effective resumption of work requires a new contradictory reading certifying climate stability within the prescribed ranges for a minimum duration of 48 hours. Written logging shared with the site management constitutes the sole technical and contractual guarantee against subsequent disputes linked to dimensional movements of wood.
Frequently asked questions
What to do if the site management demands installation despite 70% humidity to keep deadlines?
Notify in writing a site interruption notice for climate non-conformity by referring to standard SIA 253. Detail the inevitable defects: cupping of boards, cracking and adhesive failure. A signed discharge from the client does not remove your technical responsibility facing a certain risk. Keep packages sealed and request the installation of air dryers until return below the 60% humidity limit.
How long must a room be stabilized before starting parquet installation?
Standard SIA 253 requires that the intended operating climate be established before the start of installation. In Swiss practice, heating and ventilation must operate constantly for at least 48 to 72 hours within the required range of 18 °C to 22 °C and 40% to 60% humidity. This period allows homogenizing the atmosphere, avoiding gradients and ensuring that substrates reach a stable thermal equilibrium.
Can auxiliary gas heaters be used to heat a room before installation?
The use of direct combustion gas or oil warm-air cannons is to be avoided. These appliances release significant quantities of water vapour during combustion, saturating ambient air and greatly increasing the room's relative humidity. To raise the temperature without humidifying the atmosphere, use exclusively auxiliary electric radiators or warm-air heaters with external exhaust of burnt gases.
Who must sign the climate reading report before installation?
The climate reading must be countersigned jointly by the installation manager and by the representative of the site management. In the absence of management on site, the parquet layer carefully records temperature and humidity on their daily report, attaches a time-stamped photograph of the displays and transmits everything by email the same day. This approach constitutes proof of actual ambient conditions during intervention.
Texts and standards cited
- SIA 253Climate requirements and installation conditions for glued floor coverings