Skip to content
Website
🧱 CFC 211.1Reinforcement: bending, laps and placementChapter 5 of 10 in the section

Spacers and chairs: keeping reinforcement in position during pouring

This chapter details practical methods for securing reinforcement before and during concreting. You will learn how to size and distribute cover spacers according to structural elements, tie bar layers effectively to withstand foot traffic from the teams, and apply a rigorous inspection procedure just before the skip or concrete pump arrives.

Key takeaways

  • The choice of spacer material ensures load transmission and face tightness.
  • A minimum spacer density prevents reinforcement bars from sagging under the weight of workers.
  • Methodical bar tying stabilizes the reinforcement against the thrust of fresh concrete.
  • The final visual inspection validates the integrity of the reinforcement cage before concrete is discharged.

Selecting spacers and calculating their distribution according to loads

The nominal cover specified on structural engineering drawings ensures corrosion protection of the steel and the correct transmission of bond stresses. According to SIA 262, the position of reinforcement bars must be guaranteed with strict geometric accuracy against the forces of pouring. Poor spacer selection or underestimating construction site loads leads to spacers crushing or tipping over. The steel is then pressed against the formwork panel or shifted inwards, compromising the durability of the structure without any visible external signs after striking.

Spacer selection criteria by type of formwork element
Type of spacerMaterialField of applicationBehaviour during pouring
Clip-on point spacerRigid plasticWalls and vertical facesLateral support without direct heavy load
Pyramidal spacer or blockResin mortar or fibre-reinforced concreteSlab soffits and raft foundationsHigh crushing resistance, intimate bond
Continuous linear spacerFibre-reinforced concrete or galvanized steel wireDense bottom layersRoll-over stability, quick placement on formwork
Zigzag high chair (continuous wire chair)Ribbed hard-drawn wireSeparation of top and bottom layersWithstands foot traffic and the weight of the pump hose

The density of spacers at the bottom of the form is not decided at random. For bar diameters of 12 mm or less, the inherent flexibility of the steel requires closer support spacing to prevent sagging between two contact points. On raft foundations and building slabs, proven trade practice requires placing at least 4 spacers per square metre for the bottom layer. As soon as the diameter exceeds 16 mm or worker traffic becomes heavy on the reinforcement layers, this density increases to 5 spacers per square metre, staggered to avoid continuous lines of weakness in the hardened concrete.

For shuttered walls, cages are subjected to the lateral thrust of concrete during free fall and mechanical compaction. Star wheels or circular spacers clipped directly onto distribution bars must exhibit sufficient resistance to impact failure. At least 4 spacers per square metre are required on each face of the wall, with mandatory reinforcement within 20 centimetres of door openings, window openings, or construction joints.

Ensuring rigidity through tying and securing sign-off before concreting

The best spacer becomes ineffective if the reinforcement cage deforms under the passage of poker vibrators or under the weight of an equipped worker. Three-dimensional rigidity depends directly on the frequency and tightness of ties made with annealed steel wire of appropriate gauge. Tying every second intersection is not always enough: on slab edges, main beams, and starter bars, every corner and top-bar intersection must be tied using a double knot or a figure-eight tie to form a rigid cage.

  1. Stabilising the bottom layerPlace formwork spacers staggered under the main bars, then tie distribution bars securely with annealed tie wire.
  2. Arrangement of layer spacersPlace continuous chairs level between both layers at a rate of at least one line every 80 centimetres, then tie them to the bottom layer to prevent displacement.
  3. Fixing the top layerInstall top steel on the continuous chairs and make complete ties around the perimeter and along the concrete hose travel route.
  4. Securing vertical spacersOn vertical formwork, position and lock spacers onto external reinforcement to prevent any movement when closing the formwork panels.

Applying the recognised rules of the trade involves direct liability for the structural integrity of the work. Art. 229 CP penalises anyone who intentionally or through negligence breaches the recognised rules of the trade when managing or executing construction work, thereby endangering the life or physical integrity of persons. A displaced reinforcing bar or a mesh fallen to the bottom of the formwork alters the actual load-bearing capacity of reinforced concrete elements, which can lead to major structural failures.

Mechanical behaviour of spacers under load and choice of material

The stability of the reinforcement skeleton depends not only on the dead weight of the steel bars, but also on intense point loads generated during preparation and placement. Steelfixer movement, workers dragging the vibrating screed, pump delivery hose supports, or direct impact from concrete discharged from the skip place severe demands on cover spacers. An incorrectly sized spacer crushes under load, slides along smooth bars, or punches through the formwork soffit, reducing the nominal cover thickness required by SIA 262 and initiating premature degradation through carbonation or chloride ion ingress.

Suitability of spacer types according to building element and finish
Type of spacer / chairMaterialPreferred building elementMain risk to manage
Clip-on point spacerSynthetic materialWalls, beam sidesAxial sliding under concrete flow during filling.
Truncated cone block or padFibre-reinforced micro-concreteRaft foundations, solid slabs, beam soffitsLoss of bond if the material absorbs mixing water.
Linear spacer stripFibre cement or micro-concreteFirst bottom layer on blinding concreteCreation of a continuous plane of weakness if the strip is not discontinuous.
Zigzag continuous chair / deck chairWelded steel wiresSeparation of bottom and top layers in slabsSurface rust spot if feet touch the formwork face.

For fair-faced concrete or exposed surfaces, synthetic spacers are prohibited because they leave circular imprints and cause local homogeneity defects. Micro-concrete pads whose composition and porosity remain compatible with the surrounding concrete are used. These spacers must incorporate an integrated galvanized tie wire or a spring clip to prevent them from rotating when reinforcement elements vibrate under compaction equipment.

Layout, critical density, and final check at the concreting front

The density of spacers is calculated based on the stiffness of the steel bars used. With small-diameter bars, such as light mesh made of 6 to 8 mm bars, sagging between support points is pronounced: spacer spacing must not exceed 50 to 60 cm to avoid deflection under the weight of the concreting teams. For main longitudinal reinforcement exceeding 16 mm in diameter, center-to-center spacing can reach 80 to 100 cm, provided checks ensure the layers do not tip over at edge stop-ends.

  • Under raft foundations and bottom layers: arrange blocks in a staggered pattern to prevent any rolling effect when placing mesh.
  • In shuttered walls: place plastic wheels or circular spacers at a rate of at least 4 units per square metre of formwork panel, increasing density around edge zones and lintels.
  • On free edges and slab openings: install a line of spacers no more than 10 cm from the stop-end formwork to prevent lateral concrete pressure from pushing the cage against the edge.
  • High chairs for top layer support: provide at least 1 chair per square metre, or 1.5 per square metre in anchorage zones where high steel concentration creates a heavy concentrated load.
  1. Visual inspection of the steel skeletonWalk the surface to identify spacers that are crushed, broken while moving bars, or knocked out of alignment. Check that no tie wire offcuts are hanging down towards the formwork face.
  2. Foot traffic load testTest the rigidity of the top layer by walking firmly on critical areas (continuity over supports, opening zones). The layer must not sag or come into contact with the bottom reinforcement.
  3. Final cleaning and removal of temporary spacersVacuum up wire offcuts, tie scraps, and sawdust remaining at the bottom of the formwork. Replace temporary timber blocks or rebar offcuts that may have been used by mistake to support the cage.
  4. Immediate validation before the skip signalConfirm with the foreman that the cover clearances specified on the formwork drawings are observed at all points before authorizing the discharge cone to open.

In the event of an accident or bodily injury caused by reinforcement collapse resulting from lack of foresight on the construction site, art. 229 CP penalises anyone who breaches the recognised rules of the trade intentionally or through negligence. Complying with assembly rules and consolidating reinforcement constitutes a direct safety obligation for all personnel present on the slab during pouring.

Managing cover non-conformities and spacer failures

On slabs or in walls, mesh shifting or a spacer crushing under worker traffic directly compromises structural durability according to SIA 262. If reinforcement touches the formwork or the top layer sags before or during concrete placement, the team leader must halt the skip. Continuing concreting over unstable reinforcement constitutes technical negligence with serious consequences for corrosion protection.

  1. Halting the pour and immediate inspectionImmediately stop concrete delivery to the affected area. Never attempt to submerge misaligned reinforcement. Measure the deviation from the formwork face using a straightedge or folding rule.
  2. Restoring rigidity and emergency spacingInsert fibre-reinforced concrete or notched synthetic point spacers under deformed load-bearing bars. If the layer has shifted in a wall, use wheel spacers to re-establish the nominal cover specified.
  3. Reinforcing bar tyingRetie broken intersections with annealed wire using tower pincer pliers. For sagging top slab layers, double up metal chairs or zigzag spacers to carry dynamic loads.
  4. Authorisation to resumeVerify the mechanical stability of the rectified area under human foot traffic before swinging the skip or directing the pump line.

If the concrete has already started to set around improperly covered reinforcement, the foreman must record the incident in the site log. The liability of site management and the contractor is assessed according to the recognised rules of the trade. Under art. 229 CP, whoever intentionally breaches the recognised rules of the trade while directing or executing construction or demolition work, knowingly endangering the life or physical integrity of persons, is liable to a custodial sentence not exceeding five years or a monetary penalty; in cases of negligence, the penalty is a custodial sentence not exceeding three years or a monetary penalty. Strict adherence to concrete cover guarantees structural safety.

Frequently asked questions

What should be done if plastic spacers slip on oiled metal formwork?

Plastic ring or wheel spacers slip easily on heavily oiled metal formwork. They must be replaced immediately with fibre-reinforced concrete spacers with integrated tie wire, or mechanically locked at bar intersections with annealed wire tightened using tower pincer pliers. Never allow a bar to rest directly against the formwork on the assumption that concrete will lift it.

Can rebar offcuts be used to space the bottom layer?

Using black steel rebar offcuts or raw metal components as spacers at the bottom of the formwork is strictly forbidden by SIA 262. By coming into direct contact with release agent and outside air, these pieces of steel rust immediately, creating pitting corrosion starters that contaminate all the main reinforcement in the slab or beam.

What should be done when a top-layer chair tips over as the concrete skip passes?

Tipping indicates missing ties or an undersized base width on the spacer chair. Stop the crane, stand the zigzag spacer back up, and tie its base to at least three bars of the bottom layer. Add supplementary individual triangular chairs under the top reinforcement to distribute the impact of the falling concrete before resuming the pour.

What solution should be applied if wall reinforcement deflects against climbing formwork?

Before closing the second formwork face, install clip-on synthetic wheel spacers on the external vertical bars at a reduced spacing of 50 cm. If the formwork panel is already closed and the steel binds, use specific tie rods or spacers secured into the panel to push the reinforcement cage back towards the centre of the wall before the pump arrives.

Texts and standards cited

  • SIA 262Technical standard for concrete structures, defining execution, cover, and reinforcement arrangement requirements.
  • CP art. 229Breach of the recognised rules of the trade, imposing penalties for violations that endanger life or physical integrity.

In the same section