Phasing the concreting of a large slab: dividing, strips and pour sequence

Concreting an 800 m² slab requires rigorous organisation to prevent uncontrolled construction joints and shrinkage cracking. You will learn how to define a coherent phasing plan, technically locate pour stop-ends at one-fifth of the spans, and synchronise mixer truck delivery rates with the levelling and power-floating gang on the construction site.

Key takeaways

  • The phasing plan approved by the civil engineer defines the strict location of the pour stop-ends.
  • Construction joints are placed at one-fifth of the span, away from zones of maximum shear force.
  • Division into alternating strips limits the effects of differential shrinkage on the finished slab.
  • The delivery rate of the mixer trucks must compensate for discharge, spreading, and continuous vibration times.

Division into strips and technical setting-out of construction joints

Pouring a continuous 800 m² floor slab in a single stage often represents excessively high operational risk in Swiss building construction. Between ready-mix plant supply constraints, team availability, and the footprint of propping zones, the site foreman must divide the structure. The sectional division is organised according to a phasing plan approved by the structural civil engineer. This contractual document establishes the exact centerline of the daywork joints, the execution sequence of the sections, and the geometry of the crossing reinforcement sections. An improvised joint during the working day, caused by a lack of preparation, impairs the mechanical continuity of the load-bearing element.

The positioning of the pour stop-end complies with strict structural requirements. Pouring must never be interrupted directly above a support (main beam, load-bearing shear wall, or pillar head), because shear force reaches its maximum value there. Likewise, mid-span concentrates the highest positive sagging moment on the soffit. The construction joint must therefore preferably be located between one-fifth (L/5) and one-quarter (L/4) of the clear span. In this transition zone, bending moments are low and shear force remains moderate. The stop-end is formed vertically using specific formwork, such as expanded metal mesh or perforated boards that allow reinforcing bars to pass through without uncontrolled bending.

  1. Topographical setting-outMark the joint line with a chalk line on the slab formwork, respecting the L/5 dimension relative to the face of the supports.
  2. Installation of the perforated stop-endFix a perforated steel sheet or ribbed expanded metal stop-end formwork to ensure optimum roughness of the interface.
  3. Passage of reinforcementCheck the correct positioning of continuous rebar and shear reinforcement passing through the joint plane.
  4. Inspection of starter barsClean bottom and top reinforcement to remove all laitance before the next pour.

Pouring in alternating longitudinal strips (known as "piano keys" or staggered bays) offers the advantage of dissipating a significant portion of initial plastic shrinkage. By allowing the first strip to harden for several days before pouring the adjacent strip, the width of micro-cracks at the interfaces is drastically reduced. The interface must exhibit a rough, clean surface: wire-brushing the surface laitance prior to final set or wet grit-blasting guarantees adhesion of the new concrete to the hardened concrete.

Volume sizing and mixer truck delivery rates

For a standard 25 cm thick slab, a 250 to 300 m² bay represents a volume of 62.5 to 75 m³ of concrete to be placed. Delivery logistics are the operational backbone of the day. The site agent must order a continuous flow suited to the actual placement rate of the gang on the ground. If deliveries arrive too quickly, mixer trucks queue on public roads and the material risks exceeding its workability time limit. Conversely, excessively slow rotation leads to downtime on the construction site and causes uncontrolled early setting, creating an unwanted cold joint within the strip itself.

Timing parameters according to discharge method for a 70 m³ strip
Placement methodAverage outputTruck turnaround (8 m³)Strip concreting duration
Crane discharge skip on tower crane10 to 12 m³/hEvery 40 to 45 min6 h 30 to 7 h 00
Mobile concrete pump25 to 30 m³/hEvery 15 to 20 min2 h 30 to 3 h 00
Truck-mounted conveyor belt15 to 18 m³/hEvery 25 to 30 min4 h 00 to 4 h 30

Organisation on the slab must balance each work station: two plant operators discharging and raking, two operatives equipped with poker vibrators ensuring continuous compaction at the joint connection, and two tradesmen dedicated to screeding and power floating. Once concreting of a strip has begun, the pouring front advances in a single continuous operation, parallel to the planned joint. The team plans ahead for access areas for skips or the deployment of the concrete pump boom so that top reinforcement mats are never trampled.

All vehicle movement management on site falls under the general health and safety prevention rules defined in art. 82 LAA, where the employer takes organisational measures adapted to local conditions to avoid hazardous heavy vehicle manoeuvres. Furthermore, art. 3 OTConst stipulates that works must be planned in order to limit accident risks from the preparation phase onwards. Signposting mixer truck access routes and maintaining radio coordination with the crane operator eliminate crowding around the slab during pouring.

Design of the phasing plan and approval by the engineering consultant

For an 800 m² slab, monolithic concreting exposes the structure to excessive thermal and shrinkage stresses, while overwhelming lifting equipment and structural work teams. Establishing a rigorous phasing plan provides the central reference document linking the general contractor, the site foreman, and the civil engineer. This drawing details the precise layout of the bays, the geometric centerline of the stop-end formwork, and the sequential chronology of operations.

The spatial division of the slab must incorporate the state of internal stresses during both service and temporary phases. Daywork joints must under no circumstances cross zones of high shear or concentrated punching, typically located over column heads or along primary beams. The joint axis must be set in the third or quarter of the span, where bending moments and shear force remain moderate.

Under CO, if any circumstance arises that compromises the proper or punctual completion of the work, the contractor must inform the client. Applying the phasing plan requires formal approval from the civil engineer before installing any crossing reinforcement. The engineer must recalculate shear forces at the construction joint, verify the efficiency of shear connectors or tie-back reinforcement, and confirm the continued stability of falsework beneath adjacent unpoured bays.

Phasing matrix for dividing an 800 m² continuous slab
Phasing elementLocation zoneTechnical specificationApproval condition
Central strip (Bay 1)Clear internal spansStraight stop-end using expanded metal and starter barsClearing of crane-serviced storage zone
Temporary shrinkage stripSpan third between columnsInfill strip left open (1.00 m)Minimum curing period of 14 days before closure
Edge bays (Bays 2 and 3)Cantilevers and facadesIndented joint with reinforcement boxes and linksFormwork level check under load
Continuity pourLongitudinal axis of the slabDense crossing reinforcement, scabbled surfaceFormal approval from the consulting engineers

Coordination of placement equipment and supply logistics

Managing concreting rates governs the mechanical performance of the structure. When the slab is divided into 250 to 300 m² sections for a typical thickness of 25 cm, the unit volume reaches 60 to 75 m³ per stage. The delivery schedule must synchronise the flow of mixer trucks to prevent involuntary cold joints from forming within the same pour phase.

The site manager determines the interval between delivery rotations with the ready-mix plant, accounting for actual transit times, access arrangements on the ground slab or haul road, and the effective capacity of pumping or skip placing by crane. Planning must comply with art. 3 OTConst, which requires work to be planned so that the risk of occupational accidents, occupational diseases, or health impairments is as low as possible, notably by eliminating hurried manoeuvres and dangerous congestion around discharge hoppers.

  1. Physical preparation of the pour stop-endInstallation of a rigid perforated expanded metal stop-end formwork, tied to the top and bottom reinforcement. Fixing trapezoidal timber fillets to create a continuous keyway capable of resisting residual horizontal shear.
  2. Mixer truck delivery rate adjustmentScheduling phased supply at a rate of 20 to 25 m³ per hour. This delivery rate ensures steady progression of the concreting front without queuing vehicles on the access road or extended delays between vibrated layers.
  3. Interface treatment before resuming the pourStriking of formwork stop-ends after sufficient curing, high-pressure washing or mechanical scabbing of surface laitance to expose aggregate without displacing shear reinforcement.
  4. Concreting the adjoining sectionPre-wetting the joint face without leaving standing water on the formwork base, followed by concreting the adjacent bay with meticulous compaction against the existing roughened surface.

Contingency management and emergency stop-ends during pouring

On a large-scale pour, a pump breakdown, a logistics failure at the ready-mix plant, or a sudden storm forces the site foreman to improvise a daywork joint. When delivery ceases and setting time threatens to create an uncontrolled cold joint, a clean vertical stop-end must be installed immediately. Continuing to pour as a sloping feather-edge impairs the slab and compromises the transmission of shear stresses.

  • Halt placement directly within a low or zero bending moment zone, typically at one-fifth or one-third of the span between supports, strictly avoiding column support zones subjected to punching shear.
  • Erect an emergency vertical perforated stop-end formwork using expanded metal or braced timber boards, ensuring optimum roughness for the future joint.
  • Extend continuous steel through the stop-end without bending it and place temporary tie bars if the reinforcement layout allows, following the civil engineer's instructions.
  • Clean off laitance using high-pressure water or compressed air before final set to expose aggregate and ensure adhesion of subsequent concrete.

As soon as the unplanned stop-end is secured, site management and the engineering consultant must be notified. Under CO, if any circumstance arises that compromises the proper or punctual completion of the work, the contractor must inform the client. This allows the engineer to recalculate the residual concrete section and specify any required remedial reinforcement or drilled dowel bars before concreting resumes.

Frequently asked questions

What must be done if a mixer truck is delayed in traffic and exceeds the initial setting time?

If the transit time exceeds the permitted limit or if the concrete begins to set inside the drum, the truck must be rejected. Adding water on the construction site to re-temper the mix is strictly prohibited, as it destroys structural strength. The team must immediately close the pour front with an emergency vertical stop-end at the third of the span, then clean the area while waiting for scheduled deliveries to resume.

Can a construction joint be located directly over a line of columns?

No, a construction joint must never be located directly over a support or column. These zones experience maximum shear stresses, hogging moments, and heightened risks of punching shear. The pour stop-end must imperatively be shifted to the zone of minimal shear force, generally located between one-fifth and one-third of the bay span, subject to formal approval by the civil engineer.

How should the surface of a construction joint be prepared before pouring the adjacent strip?

The construction joint face must present a clean, rough surface completely free of laitance. If the stop-end was cast against expanded metal mesh, simple air-blowing or washing is sufficient. Against traditional timber formwork, scabbing with a needle gun or high-pressure washing is required to expose aggregate. The surface must be soaked to saturation several hours before pouring, but left free of standing water.

Who must approve a modification to the strip pouring sequence on the construction site?

Only the structural civil engineer can authorise a modification to the concreting sequence. The initial phasing accounts for load redistribution onto falsework, concrete shrinkage, and forces transferred to vertical load-bearing elements. Altering the sequence without recalculation exposes the structure to early cracking or impermissible localized overloads on underlying formwork.