🧱 CFC 211.1Slabs, floors and precast half-slabsChapter 6 of 10 in the section

Slab deflection: precamber during execution and measurement after striking formwork

After reading this chapter, you will know how to manage the deflection of a reinforced concrete slab according to the requirements of standard SIA 262. You will master the precise adjustment of the precamber during propping, taking measurements with a site level after striking formwork, and anticipating the expansion gaps required to protect finishing work partitions.

Key takeaways

  • The deflection of a concrete slab is normal mechanical behaviour governed by standard SIA 262.
  • The precamber applied to the propping compensates for immediate deformation and long-term creep of the concrete.
  • Altimetric measurement is carried out immediately after striking formwork using a total station or an optical level.
  • Finishing work partitions require flexible connections to prevent the transfer of structural loads.

Understanding mechanical deflection and adjusting the precamber on the propping

In reinforced concrete structures, slab deformation under the effect of its self-weight and live loads is an inevitable physical phenomenon. A measured deflection does not constitute a workmanship defect as long as it remains within the serviceability limits defined by the civil engineer and SIA 262. Total deformation consists of an immediate component upon striking formwork and a deferred component caused by creep and shrinkage of the concrete over several months.

To visually and geometrically negate the final deformation, the engineer prescribes a precamber on the formwork drawings. The chargehand or foreman must apply this initial camber to the formwork directly when adjusting the height of the props. This correction is primarily applied at mid-span and on cantilevers.

  1. Reading the setting-out drawing and locating valuesIdentify on the formwork drawings the precamber values specified by the engineer (expressed in millimetres, generally at mid-span).
  2. Marking the datum lineTransfer the construction site metre reference line (+1.00 m) onto perimeter walls and columns using a rotating laser level.
  3. Adjusting the curvature of the formwork skinAdjust the prop heads and the central bearer to raise the centre of the formwork to the required value relative to the horizontal reference datum.
  4. Geometric inspection prior to concretingCheck the parabola of the formwork skin using a laser or a measuring rod to ensure a progressive, regular rise without breaks in slope.

Measurement after striking formwork and provision for finishing work partitions

Deflection measurement is carried out at two key stages: immediately after removing the props to validate immediate deformation, then during the as-built altimetric survey. The foreman uses a construction site optical level or a total station to record altimetric points on the soffit of the concrete slab. These measurements are recorded in the structural work acceptance report.

To absorb deferred deflection without damaging the finishing work, strict construction details must be observed at the head connections of separating and dividing partitions.

  • Installation of a sliding head connection (shadow gap) at the top of plasterboard partitions.
  • Provision of a gap of at least 15 to 20 mm beneath the concrete slab before injecting flexible polyurethane foam or mineral wool.
  • Strict prohibition against wedging bricks or gypsum tiles with rigid mortar directly against the reinforced concrete ceiling.
  • Coordination on the construction site between the site manager and the plasterer/dryliner to validate the magnitude of expected deformations.
Impact of deflection on finishing work construction details
Slab span (m)Estimated deflection under load (mm)Impact on partitionsExecution corrective measure
Up to 5.00 m5 to 10 mmLow load transferReinforced plaster joint or acrylic bead
From 5.00 to 8.00 m10 to 20 mmRisk of cracking at partition headsRigid sliding joint with U-channel
Greater than 8.00 m> 20 mmRisk of stud bucklingSpecial telescopic head channels

Compliance with the instructions of standard SIA 262 together with rigorous level monitoring on the construction site guarantees the integrity of the structure. In accordance with the Code of Obligations (CO), the contractor is required to notify the client of any deformation anomaly observed when striking formwork before the finishing trades intervene.

Slab behaviour and implementation of precamber

The deflection of a reinforced concrete slab does not in itself constitute a workmanship defect. It is a mechanical deformation inherent to the material's behaviour under the effect of its own weight, permanent loads, and live loads. Standard SIA 262 sets stiffness criteria and allowable deformation limits to ensure the serviceability of the structure and prevent damage to secondary elements.

To compensate for immediate and deferred deformation (concrete creep), a precamber during execution is incorporated when adjusting formwork and propping. The value of this initial camber is defined by the structural engineer on the formwork drawing. The chargehand or foreman must apply this value at mid-span when setting up the formwork skin.

  1. Adjusting the precamber on the proppingWhen erecting shoring towers or shore props, adjust the threaded heads to form a regular curve rising towards mid-span. The maximum value prescribed on the drawing must be checked against the support lines.
  2. Check prior to concretingVerify formwork height using an optical level or a rotating laser calibrated to the reference datum of the construction site level (±0.00 m benchmark).
  3. Locking the prop basesEnsure the propping system is rigidly locked to avoid any settlement under the load of fresh concrete during pouring and vibrating.

Measurement after striking formwork and requirements for finishing work

Striking the formwork causes an immediate tensioning of the reinforcement and an initial immediate deflection. Measurement of this deformation is carried out using an optical level or a laser profilometer immediately after removing the props, and is repeated before finishing work to monitor the development of deflection under load.

Deformation monitoring and slab levelling tolerances
Construction site stageMeasurement methodInspected elementImpact on the structure
FormworkRotating laser / Optical levelPrecamber valueValidation of camber before pouring
After striking formworkAltimetric survey with levelImmediate deflectionVerification of SIA 262 compliance
Before finishing workPrecision laser on gridLong-term deflection (creep)Adjustment of gap beneath partition

If the measured deflection remains within the limits permitted by the engineer, it does not constitute defective workmanship. However, deferred deflection continues to develop over subsequent months under the effect of concrete creep. This change in elevation directly impacts the installation of lightweight finishing work partitions.

Dividing or separating partitions must under no circumstances become de facto load-bearing elements. To prevent the upper slab from crushing the head of the partition during continuous deformation, the finishing work must incorporate sliding connections or provide a deformable top runner. The site manager ensures that altimetric survey data is passed on to the plastering and metalworking contractors before they intervene.

If a discrepancy from theoretical elevations is detected on site, the contractor complies with notification obligations. In accordance with art. 365 CO, the contractor immediately informs the client if any circumstance jeopardises the proper or timely execution of the work, particularly when observations are made regarding support geometry or transferred loads.

Management of deflection variances and on-site technical arbitration

When the deflection measured after striking formwork exceeds the values calculated by the civil engineer or the tolerances permitted for finishing work, site management must immediately suspend the assembly of rigid elements located beneath the span concerned. Excessive initial deflection does not automatically signify a lack of structural load-bearing capacity in the reinforced concrete, but it directly compromises the installation of drywall partitions, facades, and building services. The first step consists of carrying out a complete altimetric survey using an optical level or a sweeping laser level, establishing a grid of points every metre across the top and bottom faces of the slab to isolate the actual deformation.

If the level recorded after striking formwork reveals insufficient precamber during execution or higher deformability than predicted, the contractor must formally notify the client and the engineer. Under the Code of Obligations (CO), when a circumstance jeopardises the proper execution of the work, the contractor immediately reports the situation to discharge liability and decide on corrective measures. The specialist structural engineer must re-analyse the stiffness of the slab, incorporating the actual elastic modulus of the concrete and the actual position of the reinforcement.

  1. Joint survey of the soffitDraw up a measurement log with an optical level between the site manager and the site foreman to map the actual elevations beneath the span.
  2. Deformability check by the engineerForward the survey to the civil engineer to verify permissible deflection according to standard SIA 262 and evaluate foreseeable deferred deformations.
  3. Adaptation of finishing work detailsAdjust the height of partition head sliders or plan planing of gypsum blocks if deformation remains compatible with safety.

In extreme cases where deformation impairs serviceability without endangering structural safety, targeted remedial works by profile compensation on the top surface or custom sliding connection details for finishing work are determined in coordination with the site manager. Any alteration to interface details must be agreed in writing before plasterers and finishing contractors intervene.

Frequently asked questions

Is concrete slab deflection considered a construction defect?

No, deflection is normal mechanical behaviour of reinforced concrete under load and flexibility. It only constitutes a defect if it exceeds the limits specified by standard SIA 262 or if it impairs the normal function of finishing work, such as jammed windows or cracked partitions.

How is the precamber set on the propping before concreting?

Precamber is set during formwork assembly by adjusting the prop heads according to the engineer's drawing. An upward convex curvature is applied, generally peaking at mid-span, using a laser level or a site optical level. This adjustment aims to compensate for the anticipated sag under self-weight.

When should deflection be measured after striking formwork?

The initial measurement must be taken immediately after the complete removal of props and wedges. An optical levelling survey of the slab soffit and top surface should be carried out before storing finishing work materials or laying masonry, in order to record the immediate deflection under pure self-weight.

What is the impact of unanticipated slab deflection on lightweight partitions?

Excessive deflection crushes the heads of rigid partitions or distorts drywall U-channels. Without an adequate expansion joint or sliding head connection, plasterboards crack, doors jam, and metal studs buckle under the load transferred from the upper slab.

Texts and standards cited

  • SIA 262Requirements for concrete structures and verification of serviceability limit states, including deflection limitation
  • Code des obligations art. 365Contractor's obligation to immediately inform the client if any circumstance jeopardises the proper execution of the work