Key takeaways
- Fix the chamfer strip without play to prevent destructive grout leakage.
- Strike edge forms with care to preserve the cohesion of green concrete edges.
- Immediately install effective protective angle sections on every exposed transit corner.
- Reconstitute spalled edges using a repair mortar matched to the shade of the original fair-faced concrete.
Fixing chamfers and striking without concrete pull-out
The straightness of a slab edge depends on the quality of the chamfer strip installation. On traditional or modular formwork, the triangular plastic or wooden strip must be nailed or glued at regular spacings of approximately 15 to 20 centimetres. A void beneath the strip causes grout loss that hardens into a rigid flash. This flash tears the edge away when stripping the slab edge formwork.
- Formwork striking spall
- Localised bursting or fracturing of a hardened concrete edge occurring during the removal of formwork elements, most often caused by mechanical levering with a crowbar or by concrete adhesion to the bottom of the form.
Sharp edges remain particularly brittle and encourage water bleed along formwork panels. Using a 10x10 mm or 15x15 mm chamfer strip reduces this risk by softening the edge geometry. For slab edges cast against steel stop-ends or plywood edge forms, a flexible sealing gasket or compressible mastic placed behind the profile prevents any leakage of cement paste.
- Checking the edge supportClean the edge location on the formwork face to remove dust, then apply release agent in a thin film before setting the strip in place.
- Setting out and fixingPin the strip along a chalk line using lost-head pins or high-strength fabric duct tape, ensuring butt joints between profiles are perfectly flush.
- Progressive strikingRemove slab edge forms without exerting prying pressure against the concrete. Pull the formwork parallel to the face or downwards, away from the hardened edge.
Mechanical protection of corners and colour-matching repair protocol
As soon as edge formwork is stripped, the structure becomes vulnerable to handling impacts: telescopic forklift traffic, offloading of reinforcement rebar packs, or shifting of formwork panels. Edge protection after striking must take place immediately. The standard arrangement relies on rigid plywood or heavy-gauge plastic angle sections, strapped or taped, secured without puncturing the finished concrete face.
| Exposure zone | Recommended device | Method of fixing |
|---|---|---|
| External slab edge (crane access) | Double-layered 15 mm plywood angle | Textile strapping or ratchet straps without nailing |
| Pillars and transit openings | Dense foam or extruded plastic corner profile | Wide non-staining adhesive tape |
| Balcony and access walkway edges | Reinforced waxed cardboard sleeve | Light propping or elastic wedging |
When a spall occurs, making good requires careful treatment to avoid a visible patch. Repairing and colour-matching require cutting back all spalled material with a flat chisel to create a square shoulder at least 5 mm deep. Feather-edged repairs always end up blistering or breaking away.
- Clean chiselling of the edge to remove fractured concrete, followed by dry air dusting.
- Installation of a rigid metal guide straightedge, clamped with cushioned clamps.
- Pre-wetting of the substrate or application of a cementitious bonding slurry.
- Mixing of a fine repair mortar, adjusting the shade by blending white and grey cement based on a trial sample.
- Compacting with a trowel against the guide straightedge, followed by light sponge floating as initial set begins.
Contractual management of visible defects falls under the general rules of the contract for work: according to art. 364 CO, the contractor is liable for executing the work in accordance with the rules of the trade. To prevent disputes regarding facade finishes, temporary protection measures must remain in place until the finishing work trades intervene.
Spall diagnosis and substrate preparation methods
The occurrence of a spall on a slab edge or stripped wall corner constitutes a critical geometric and visual non-conformity for the structure. When concrete pull-out occurs during formwork stripping or following an early impact during wall formwork cycles, repair cannot be carried out without methodical breakout. An unchamfered sharp edge concentrates residual mechanical stresses, promoting corner delaminations that can leave edge reinforcement without the cover specified in the design.
- Hammer testing and marking outSound the edge with a mason's hammer to identify delaminated areas. Mark out the perimeter of the intervention with a straightedge, extending 20 mm beyond visible spalls.
- Straight boundary saw-cutMake a saw-cut using an angle grinder fitted with a diamond blade to a minimum depth of 10 mm. This cut line avoids feather-edges that systematically end up chipping.
- Mechanical breakout of deteriorated concreteRemove damaged concrete using a light pneumatic chisel or pointed chisel down to sound substrate. Remove all dust using dry compressed air or a stiff brush.
- Treatment of exposed steelIf a reinforcing bar is uncovered, clear around its perimeter by at least 15 mm to allow complete encasement by the repair mortar during stop-end formwork casting.
| Defect typology | Primary cause | Structural consequence | Repair procedure |
|---|---|---|---|
| Superficial chipping (< 10 mm) | Premature striking or adhesion to form face | Visual defect, concrete cover preserved | Perimeter saw-cut, surface scarification and non-shrink fine mortar |
| Deep spall without exposed steel | Handling impact or chamfer strip pull-out | Partial loss of cover, risk of water ingress | Clamped formwork, foam sealing and thixotropic mortar |
| Delamination with exposed reinforcement | Inadequate vibration or rebar position out of tolerance | Loss of cover, risk of galvanic corrosion | Breakout behind rebar, passivation and pouring against rigid stop-end formwork |
Geometric reconstitution, colour harmonisation and site shielding
To make a repair on a fair-faced slab edge invisible, the site foreman must act simultaneously on the edge formwork and the mortar mix grading. Using a counter-balance secured with screw clamps ensures strictly straight geometry. Incorporating a triangular or trapezoidal chamfer strip on the repair assembly guarantees seamless continuity of the structure's perimeter chamfer line.
Colour disparity is the most frequent dispute during the acceptance of fair-faced concrete under SIA 118. Proprietary repair mortars often exhibit a very dark grey hue that contrasts sharply with hydrated structural concrete. Tone adjustment is performed on the construction site via test batches by substituting a portion of standard cement with white cement and incorporating fine sands sourced from the same supplier as the ready-mix plant.
- Fluted polypropylene corner profile
- Rigid element bent at right angles or bevelled, fixed to slab edges and wall corners using strapping or non-staining adhesive tape, designed to absorb material impacts during finishing work phases.
- Production of trial tablets with varying ratios of grey and white cement (e.g. 70/30, 50/50, 30/70) air-cured prior to sign-off by site management.
- Systematic installation of a watertight PVC chamfer strip in the patch formwork to reform the bevelled edge without grout lines.
- Tightening of the counter-mould using wedge blocks and screw clamps with cellular foam interposition to stop leaks under pressure.
- Maintaining a damp polyethylene film for 72 hours over the repaired area to avoid premature drying and surface dusting.
- Immediate installation of chipboard or heavy-gauge plastic protective angle sections at crane pick-up paths and unloading zones.
The financial cost of edge repairs weighs heavily on construction site balances: restoring one linear metre of degraded slab edge proves significantly more expensive than installing integrated preventive protection. To cost the overall impact of this finishing work or specific corner protection items, refer to the detailed price schedules under /soumissions/.
Managing edge claims and contractual remedies
On exposed concrete slabs and balcony edges, a spalled edge noticed upon striking triggers an immediate dispute with site management. Manual repairs on fair-faced concrete are costly in skilled labour and frequently leave shade haloes. When confronted with linear damage caused by chamfer strip pull-out or a skip impact, the construction site procedure must distinguish technical urgency from contractual damage classification.
- Halt all improvised making good: never allow standard mortar to be applied without prior agreement on grain size and reference shade.
- Record the condition of the edges through a joint photographic survey before any subsequent work by other trades.
- Make the area safe: scale away unstable fragments with a flat chisel to prevent falling debris on lower levels, in accordance with the general duty of prevention set out in LAA.
- Promptly install temporary protective angles on intact slab edges located in crane transit paths or heavy circulation zones.
When spalling results from third-party intervention, such as facade propping or the shifting of boom lifts by another contractor, liability must be formally documented. According to CO, if any circumstance compromises the regular or timely execution of the work, the contractor must inform the client immediately. Prompt written notice to the client relieves the structural work team from financial liability for repairs on areas previously accepted.
Frequently asked questions
How can one prevent a plastic triangular chamfer strip from tearing away during striking?
Tearing away occurs when the strip is nailed too tightly or when grout seeps beneath the profile. Preference should be given to PVC strips with flexible sealing lips, or the profile should be stapled at regular centres from the rear of the plywood if the edge permits. Careful application of release agent on the chamfer and progressive lateral striking prevent shearing the green concrete.
What is the best solution for protecting a slab edge exposed to light plant traffic?
Fitting wooden or expanded PVC angle profiles, nailed or strapped, is essential as soon as edge formwork is removed. For areas with heavy pallet truck or forklift traffic, folded steel angle plates clamped with screw clamps provide robust protection. The protection must remain in place until facade elements or permanent guardrails are installed.
How can one achieve a colour match when repairing a spall on a fair-faced edge?
The repair mortar must incorporate a ratio of white and grey cement identical to the original concrete matrix, supplemented with the same fine aggregates. The damaged area is cut back square to a depth of at least 10 mm. Producing a trial sample cured rapidly with a hot air gun allows the shade to be verified prior to final application on the edge.
Who bears the cost of repairing an edge damaged after the installation of guardrails?
If the structural work handover record noted compliant slab edges prior to the metalworkers' intervention, the repair costs fall on the installer responsible for the impact. In the absence of an intermediate joint inspection record or maintained physical protection, site management often assigns the defect to the mason under their obligation to deliver a compliant work.
Texts and standards cited
- LAAgeneral safety principles: to prevent occupational accidents and illnesses, the employer shall take all measures that experience has shown to be necessary, that the state of technology permits, and that are adapted to the prevailing conditions; workers shall assist the employer (they shall in particular use personal protective equipment).
- COmaterials and building ground: the contractor is liable for the sound quality of the materials they supply; if the materials supplied by the client or the building ground designated by them are found to be defective, or if any other circumstance compromises the regular or timely execution of the work, the contractor shall immediately inform the client thereof, under penalty of bearing the consequences (para. 3).