Joints, propping and phasing of the structure: the execution reference
This section is intended for site foremen, chargehands and construction managers in Romandy. It brings together the execution rules for temporarily supporting reinforced concrete structures and allowing them to move freely over time: calculation and installation of propping, repropping cycles under slabs, breakdown of concreting stages, assembly of load-bearing shoring towers, installation of bearings and continuity of movement joints.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
30 to 40 m
Usual maximum spacing between expansion joints without specific justification
h / 4 to h / 3
Depth required for crack inducement by shrinkage joint saw-cutting
2 m
Fall height triggering mandatory perimeter edge protection on floor slabs
100 cm
Minimum height of the top rail of a temporary edge guardrail
Technical scope of structural work: what supports and releases the structure
The construction of a load-bearing reinforced concrete structure according to the requirements of standards SIA 262 and SIA 260 relies on a rigorous balance between the temporary site phases and the permanent behaviour of the finished structure. This hub deals exclusively with the stability of the frame during its execution and the structural provisions guaranteeing its deferred movements. Managing the loads transmitted to the underlying suspended slabs, setting out the support lines and the kinematic freedom of the elements constitute the core of our construction trade.
In terms of occupational safety, OTConst requires work stations and accessways to be protected against the collapse of construction elements and falling materials. The site management staff must ensure that every prop, shoring tower or formwork section withstands fresh concrete loads, imposed service loads and dynamic forces without detrimental deformation to the structure or risk to personnel.
- Traditional propping and shoring towers for clear heights and heavy loads.
- Striking protocols and load transfer through methodical repropping.
- Movement joints: shrinkage joints, thermal expansion breaks and sliding bearings.
- Composite structural connections using grouted dowels and anchor bars into existing structures.
- Crane logistical organisation and regulatory traceability in the concreting log.
Reading methodology and sequencing logic on the construction site
To plan and complete a construction site without structural damage, the technical progression follows the physical life cycle of the concrete. The practitioner must first master the space and the overall kinematics before setting up the uprights. The study therefore begins with the design of expansion and shrinkage joints to anticipate thermal effects and autogenous shrinkage. The support infrastructure is then addressed: selection of props, compliance with load limits, verticality of prop lines and rigidified assembly of shoring towers for thick slabs or main beams.
- 1. Define breaks and supportsPosition through-structural joints, choose the orientation of elastomeric bearings and set out shrinkage strips according to the civil engineer's drawing.
- 2. Secure the load-bearing arrangementSet the propping pitch, brace load towers and check pin tightening before the concrete pump arrives.
- 3. Carry out pouring and release deformationsPhase pour volumes, record parameters in the concreting log and saw-cut early-age concrete within the prescribed working window.
- 4. Strike formwork and reprop under supervisionRelieve the formwork without suddenly releasing the slab, reinsert drying props storey by storey to avoid overloading the lower suspended slabs.
This sequence concludes with the interaction with the physical environment: reliable anchoring of reinforcement into existing masonry and rigorous management of crane slewing areas, guaranteeing compliance of the execution with the recognised rules of the trade enforceable under CP.
📘 Chapters in this section 10
Expansion joint: width, full-height continuity and treatment
Prevent facade failures by ensuring a perfect clear air gap from the foundation slab to the roof.
Joints, propping and structural phasingContraction joint: where to place it, when to saw, depth
Intervene during the right setting window to guide straight cracking without spalling the edges.
Joints, propping and structural phasingProps: adjusting, tightening and checking the row before pouring
Check the plumb, threaded travel and pin engagement of the outer tubes before clearing the pump.
Joints, propping and structural phasingRe-shoring and partial striking: storey-by-storey operation sequence
Ease the plywood without overloading green slabs using a controlled load-release cycle.
Joints, propping and structural phasingHeavy-duty shoring tower: assembly, bracing and acceptance
Assemble frames, base jacks and diagonal braces to support your heaviest elements without deflection.
Joints, propping and structural phasingPhasing the concreting of a large slab: dividing, strips and pour sequence
Divide your areas to limit internal tensile stresses and manage watertight construction joints.
Joints, propping and structural phasingNeoprene sliding bearing: role, flat installation and execution errors
Ensure pure translation of slabs without edge binding or premature crushing of the elastomer.
Joints, propping and structural phasingConnecting a new structure to the existing: bonded dowels, testing and tolerance
Drilling, dust extraction and structural resin: transfer shear forces without cracking the existing concrete.
Joints, propping and structural phasingConstruction site crane: reach, tip load and no-slew zones
Coordinate load charts, radius and blind spots to crane formwork panels with complete safety.
Joints, propping and structural phasingConcreting log: what to record to make the work defensible
Document pours to build an unassailable record for the site management.