Key takeaways
- Check the bearing length on the wall or beam before unhooking any lifting accessories.
- Set the prop lines before placing precast floor slabs to prevent any bending of the bottom flange.
- Prohibit any heavy storage on the precast floor slab as long as the topping concrete has not hardened.
- Comply with good practice to prevent collapse in accordance with the Swiss criminal code.
Bearing lengths, wedging and installation of temporary prop lines
During the temporary phase, the precast floor slab functions solely as self-supporting formwork reinforced with its stiffeners or bottom reinforcement. Standard SIA 262 requires strict adherence to bearing conditions to ensure force transfer and the anchorage of projecting reinforcement into the reinforced concrete load-bearing elements. Insufficient bearing length on a shear wall or beam creates a risk of direct shear of the concrete base or premature slippage during worker movement and concreting.
| Type of load-bearing support | Minimum gross bearing length | Interface device | Execution inspection |
|---|---|---|---|
| Shuttered reinforced concrete shear wall | 30 mm to 50 mm | Foam strip or elastomeric levelling strip | Visual alignment before crane release |
| Precast or cast-in-place beam | 50 mm to 70 mm | Direct laying on chamfer or resilient strip | Verification of steel lap length |
| Timber bearer on temporary propping | 70 mm to 100 mm | Timber joist or H20 type formwork beam | Bearing plane and laser level check |
| Load-bearing masonry | 50 mm to 80 mm | Bituminous felt or sliding strip | Levelling course tolerance and block crushing |
Temporary propping cannot wait until precast elements are lowered into place: it must imperatively be installed before cranage begins. Prop lines, fitted with timber ledgers or primary beams, form the rigid high points of the element. The permissible clear span of the thin concrete bottom flange without props is generally between 1 m 20 and 2 m 00 depending on the type of steel lattice girder used. Exceeding this centre-to-centre distance leads to excessive deflection, early transverse cracking and a risk of joint opening under the weight of workers.
At workstations and traffic routes, measures must be taken so that workers are not endangered by the collapse of building elements or falling objects and materials.
art. 17 OTConst
Erection sequence, concreting and prohibition of surcharges on green slabs
The behaviour of the structure during the 72 hours following the pouring of the infill concrete determines the durability of the structure. During these first three days, the slab concrete develops only partial strength. It acts as a heavy dead load added onto the props and the precast floor slab, without actively contributing to overall tensile or flexural strength. The installation sequence and movement of teams must be strictly phased to eliminate stress concentrations.
- Inspection of propping and levellingCheck the tightening of prop collars, the verticality of prop bodies and the elevation of ledgers with any camber required in accordance with the civil engineer's drawing.
- Orderly laying of precast floor slabs by cranePosition elements starting from the rigid end supports towards the centre of the bay. Never unhook slings before complete placement on the end supports and intermediate prop lines.
- Installation of tie reinforcementPlace transverse top reinforcement over supports, joint tie bars and upper mesh, avoiding concentrated stacking of rebar bundles in the middle of spans.
- Distribution of fresh concrete pourPour the compression slab evenly, starting discharge from the load-bearing supports towards the centre of the spans, without creating punctual heaps with the concrete skip or pump hose.
The management of construction site loads on a green slab formally excludes placing brick pallets, formwork panels, rebar racks or mortar skips on the unhardened zone. Concentrated stacking on concrete aged 24 to 48 hours punches through the precast floor slab base, breaks the mechanical bond between precast and cast-in-place concrete, and destabilises the storey prop lines underneath.
Checking of bearings and load transfer during the transitional phase
During the assembly phase and until the mechanical strength of the cast-in-place concrete is achieved, a precast floor slab does not act as a finished floor. It behaves as thin formwork, reinforced or prestressed, extremely sensitive to asymmetric loads. Compliance with bearing geometry on load-bearing walls and downstand beams determines the immediate stability of the structure. Standard SIA 262 sets out the requirements for concrete structures and requires verification of the adequacy of contact zones to prevent any localised crushing or premature slippage when releasing the crane load.
Load transmission occurs exclusively through contact zones and temporary propping lines. If the precast floor slab rests on masonry or a wall that is out of plumb or has spalled areas, effective bearing can be dangerously reduced. When the actual geometry of the support leaves a bearing smaller than the required tolerances, installing an edge prop line immediately against the facing becomes essential to relieve the concrete edge before any pour.
| Support type | Theoretical bearing length | Execution tolerance | Required propping measure |
|---|---|---|---|
| Shuttered reinforced concrete shear wall | 50 to 70 mm | ± 10 mm | Direct bearing permitted if flatness conforms |
| Clay brick masonry | 70 to 100 mm | ± 15 mm | Elastomeric felt strip and edge ledger recommended |
| Steel girder or precast concrete beam | 60 to 80 mm | ± 5 mm | Shims or mandatory edge prop line if bearing is bevelled |
| Existing wall with underpinning | 80 to 120 mm | ± 20 mm | Bolted steel ledger beneath bearing edge |
Bracing coordination, access routes and management of construction site loads
During the first three days following the pouring of the topping concrete, the composite precast floor slab-compression slab structure remains unable to take construction site operational surcharges. The propping system handles the entire load transfer to lower levels. Prop lines must be perfectly aligned vertically from one storey to the next to avoid punching through the underlying slabs, which have not yet reached full maturity under standard SIA 262.
Floor organisation demands strict discipline regarding movement and storage of heavy materials. Brick pallets, stored welded mesh or tool skips must under no circumstances be placed in the centre of temporarily propped bays. In accordance with OTConst art. 17, measures must be taken at workstations and traffic routes to prevent workers from being endangered by the collapse of building elements or falling materials.
- Check of vertical alignment schemeUsing a plumb line or laser level, check that each steel prop on level n strictly coincides with the prop head on level n-1 to ensure direct load transfer without subjecting the green slab to spurious bending.
- Installation of access routesPlace load-distributing timber planks perpendicularly to the precast floor slab ribs to guide the passage of workers and light concrete wheelbarrows, prohibiting any heavy point contact on zones with exposed stiffening reinforcement.
- Marking out and ban on temporary storageDemarcate central zones of newly laid precast floor slabs using warning chains or tape to prevent crane operators from placing concrete skips or rebar bundles outside rigid bearing zones.
- Verification of prop collar tightnessInspect wedges and screw jacks after the pour to identify props relieved of load by localised settlement or thermal deformations, and apply light re-tightening without jacking up the floor.
Management of laying deviations, abnormal deflections and execution disputes
During the temporary phase when the second-stage concrete has not reached its strength, the precast floor slab acts as self-supporting formwork that is particularly sensitive to geometrical defects. Deviations observed on construction sites mainly concern insufficient bearing length on walls or beams, unexpected deflection of the propping beam or an unauthorised construction site surcharge. When faced with these anomalies, concreting operations must be stopped before any attempt at improvised correction.
- Immediate recording and securing of the zoneHalt pouring or material storage. According to OTConst art. 17, measures must be taken at workstations and traffic routes so that workers are not endangered by the collapse of building elements. Cordon off the lower footprint below the affected elements.
- Survey of bearing non-conformitiesMeasure actual bearing length on each masonry, concrete or steel support. If the measured value is less than the tolerances set by execution drawings or standard SIA 262, notify the deviation in writing.
- Formal notice to site management and the civil engineerArt. 365 CO provides that if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the regular or prompt execution of the work, the contractor shall inform the client thereof. This step determines the preparation of bearing reinforcement measures by the engineering design office.
- Execution of an approved remedial systemImplement solutions validated by the engineer: installation of a steel angle beneath the bearing chemically anchored, addition of a flush permanent prop line until full hardening or reinforcement of top-layer rebar.
Any modification of the temporary static scheme requires an acceptance protocol countersigned by the civil engineer before authorising access to steel-fixing teams and pouring the slab.
Frequently asked questions
What should be done if the actual bearing length is less than 30 mm on a concrete wall?
Laying must be suspended immediately. A bearing length of less than 30 mm does not guarantee safety against slippage under fresh concrete loads. Record the dimension on the inspection record and request validation from the civil engineer. The engineer generally specifies a flush prop line placed tightly against the wall or the installation of a bolted steel angle to extend structural seating.
Can formwork panels or rebar pallets be stored on an unpoured precast floor slab?
No, this is strictly prohibited. Precast floor slabs during the transitional phase are designed only to support their self-weight, the weight of fresh concrete and a temporary operational load limited to workers and mobile skips. Placing a rebar pallet or heavy equipment creates a concentrated point load capable of crushing the precast floor slab or causing a prop line to buckle.
At what exact moment can the first prop line be relieved of load?
No removal of wedges or unloading of props must take place before the cast-in-place concrete has reached the mechanical strength specified by the civil engineer, in accordance with the rules of standard SIA 262. In construction site practice, this period corresponds to effective hardening verified by rebound hammer or companion test specimens, often set between 7 and 28 days depending on ambient temperature conditions.
How should precast floor slabs be stabilised when laying in high winds?
Lifting in strong winds exposes the precast floor slab to uncontrollable slewing forces. Elements once positioned must be immediately wedged and tied into their end bearings. Props fitted with retaining forks must be set beforehand to the exact laser height. As soon as the element is placed, temporary stiffeners or stabilising trestles must be installed to prevent any untimely lateral displacement.
Texts and standards cited
- OTConst art. 17protection against the collapse of building elements or falling objects and materials: at workstations and traffic routes, measures must be taken so that workers are not endangered.
- CO art. 365material and ground: the contractor is liable for the sound quality of the material he provides; if the material provided by the client or the ground designated by him is recognised as defective, or if another circumstance jeopardises the regular or punctual execution of the work, he immediately informs the client, under penalty of bearing the consequences (para. 3).
- SIA 262Standard for concrete structures, governing the design, dimensioning and execution of reinforced and precast concrete.