Neoprene sliding bearing: role, flat installation and execution errors

The elastomer sliding bearing allows delayed horizontal movements of the slab without shearing the head of the load-bearing wall. In this chapter, you will learn how to prepare a perfectly flat bearing surface, correctly orient the sliding faces, and seal the joint to prevent any rigid locking caused by concreting grout.

Key takeaways

  • The sliding bearing absorbs concrete shrinkage and thermal deformations without cracking the load-bearing element.
  • The bearing strip requires a clean surface, free of chippings and levelled without being out of plumb.
  • The orientation of composite plates requires positioning the sliding sheet according to the engineer's drawings.
  • Any laitance grout penetrating the joint prevents movement and destroys the bearing function.

Understanding the kinematic role of the elastomer to protect wall heads

A sliding bearing is a structural component placed between a rigid load-bearing element (reinforced concrete wall or padstone) and a floor slab or beam. Its primary function is to transfer permanent and imposed vertical loads while allowing relative horizontal displacements. These translations result from the hydraulic shrinkage of the concrete, creep under prestress or sustained load, and seasonal thermal expansion. If the slab is cast in direct contact with the top of the wall, shrinkage generates considerable secondary shear stress. The top of the wall then suffers spalling, diagonal shear cracks, or bearing edge failure.

Composite sliding bearing
Prefabricated device consisting of an elastomer (neoprene) base vulcanised or bonded to a polytetrafluoroethylene (PTFE) sliding plate, coupled with a mirror-polished stainless steel counter-plate, protected by a watertight foam seal.

The elastomer absorbs rotational movements at the bearing generated by span deflection, which evens out contact pressure and avoids stress concentrations on the front edge of the masonry or concrete wall. The polished stainless steel and PTFE pair ensures an extremely low coefficient of friction, guaranteeing freedom of axial translation for the slab.

The contractor remains responsible for the careful execution of this work in accordance with the civil engineer's drawings. Compliance with accepted codes of practice is mandatory on the construction site; federal law (art. 364 CO) stipulates that the contractor's liability is subject to the same rules as that of the employee.

Execution rules: substrate preparation, installation direction and laitance protection

  1. Levelling and cleaning the bearing surfaceThe top of the wall must be rigorously flat. Remove laitance runs, concrete splatter and gravel using a chisel or grinder. Thoroughly remove dust with a hand broom or compressed air. Any local roughness will puncture the neoprene and hinder kinematics.
  2. Positioning and adhering to the strip orientationUnroll or place the bearing strip according to the alignment defined on the engineer's drawings. Ensure the sliding face (sliding plate facing the stainless steel) is oriented in the direction of the expected movement. Set back clearly from the external line of the wall to avoid edge shear.
  3. Watertight sealing of joint edgesInstall an extruded polystyrene strip or closed-cell foam on both sides of the neoprene bearing, then apply a reinforced waterproof adhesive tape over the joints to prevent any leakage of liquid laitance under the formwork.
Systematic checkpoints during neoprene bearing installation
Identified defectImmediate consequenceCorrective action before pouring
Rough or uneven substratePuncturing of the elastomer and steel-concrete contactScabbling, levelling with fine mortar and flat grinding
Inversion of the bearing (upside down)Elastomer-concrete friction without sliding effectCheck manufacturer's instructions and correct stainless steel/PTFE face orientation
Discontinuous or displaced bearing stripStress concentration at the top of the wallRealign bearing with the layout axis on the drawing
Absence of edge sealingConcreting grout penetrating the sliding chamberInstall a closed-cell foam bead sealed with adhesive tape

The most common and destructive installation mistake remains the accidental grouting of the joint. If liquid cement laitance creeps along the edges or under the sliding plate during slab concrete vibration, it forms a rigid bridge. This bond hardens and instantly destroys the mechanical separation intended by the sliding bearing. At the first shrinkage movements, the slab pulls the wall along with it, cracking masonry corners and bearings.

On construction sites subject to tight production schedules, the organisation of the workstation must guarantee quality of execution without compromising safety. The Construction Works Ordinance requires the employer to appoint a competent person on each construction site responsible for occupational health and safety, who is authorised to issue instructions to workers (OTConst art. 5 al. 1).

Accidental mechanical locking: mechanisms that void the sliding bearing

The function of the sliding bearing, whether made of reinforced or non-reinforced elastomer, is to decouple the horizontal movements of a reinforced concrete slab from the underlying load-bearing wall or beam. This component absorbs reversible thermal expansion, plastic shrinkage, and deferred concrete creep. When a rigid obstacle restricts this kinematic freedom, the structure no longer functions according to its free bearing structural model. Shear and tensile stresses then concentrate immediately at the top of the wall or at the edge of the slab, causing severe spalling or even structural edge failure.

Common causes of kinematic obstruction and associated structural damage
Source of lockingLoad transfer mechanismObserved damage on the structure
Grout or laitance infiltrated into the interfaceRigid bridging between the upper pad and the lower baseHorizontal cracking below the edge and concrete spalling
Unprotected penetrating connecting rebarParasitic shear force preventing horizontal translationLocalised spalling of concrete cover around the rebar
Incompressible edge material or direct groutingEnd stop preventing free contraction of the slabDiagonal shear at the top of the load-bearing wall
Out-of-flatness installation with edge tiltingConcentration of compressive stresses along a narrow linePoint crushing of the elastomer and shear wall cracking

The most insidious problem occurs during the concreting of the upper slab. If the edge formwork or lateral compressible strip leaves a gap of a few millimetres, laitance flows directly down the side of the bearing strip. As it hardens, this fine mortar forms a non-deformable mineral wedge. The elastomer bearing is then short-circuited. When shrinkage begins, the concrete transmits a direct tensile force to the head of the wall, tearing off a whole corner of concrete.

Pre-concreting conformity checks and execution inspection

To guarantee the integrity of the sliding strip, the site foreman and the team leader must thoroughly inspect the bearing surface before placing the reinforcement. The receiving surface of the wall must be perfectly clean, free of dust and chippings, and levelled without hollows. A concrete burr under the strip creates a hard spot that punctures the neoprene under the dead load of the slab.

  1. Cleaning and inspection of the bearing surfaceRemove all traces of formwork release oil, dust or laitance from the bearing edge using a wire brush or compressed air. Check that the bearing surface is flat and horizontal.
  2. Positioning and securing the productUnroll the strip, adhering strictly to the alignment defined on the engineer's drawings. Hold the component in place using a compatible adhesive tape without puncturing the material.
  3. Installation of the compressible stripFit a laitance-tight closed-cell foam profile on the outer edge. This barrier absorbs lateral deformation and prevents fresh concrete from spilling over onto the underside.
  4. Visual inspection before pouringInspect for the total absence of foreign matter between the sliding sheet and the elastomer. Protect the upper surface until the reinforced concrete is poured immediately afterwards.

Liability management requires absolute rigour during this stage. Art. 365 CO stipulates that if the material supplied by the client or the plot designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, under pain of bearing the consequences. If the top of the wall has a levelness tolerance incompatible with the sliding bearing specified by the engineering firm, the contractor must report this levelling defect before permitting installation.

Once concreting is complete, monitoring the striking of formwork remains critical. Edge formwork panels must be removed without tearing the decoupling foam. Every joint must remain clean, free of any sawdust debris, nails or mortar, so that the translational mechanism functions upon initial loading and drying of the slab.

Management of bearing non-conformities and corrective measures on the construction site

On a structural work construction site, the late discovery of a poorly positioned, contaminated or mechanically bridged sliding bearing requires a methodical response before any final loading. When laitance penetrates the sliding interface or rogue grouting locks the translation of the slab, the floor can no longer expand freely: thermal shrinkage stresses are transferred entirely to the head of the wall, initiating spalling and diagonal shear cracks.

  1. Identification and stoppage of the pouring phaseIf the defect is visible before concreting, suspend the placement of the top reinforcement. Immediately clean or replace the damaged bearing pad.
  2. Formal notification to the civil engineerIf the concrete sets with an unintended rigid connection, record the defect in the site journal. In accordance with CO, the contractor shall inform the client of any circumstance compromising the proper execution of the work.
  3. Sawing or mechanical release of the jointAccording to the engineering firm's instructions, clear the bearing edge by diamond sawing the laitance heel or inserting an isolation profile to restore the required kinematic travel.

Repairing a sheared edge or injecting structural cracks generates costs disproportionate to the value of the original material. Remedial work under heavy propping entails costs in the order of several thousand francs, which can largely be avoided by rigorous control of the installation prior to pouring.

Frequently asked questions

How do you identify the installation direction of a reinforced sliding bearing?

The sliding face made of fluoropolymer or Teflon must be oriented strictly upwards, against the moving in-situ or precast concrete element. The intermediate steel plate or rough neoprene base rests directly on the clean, hardened concrete padstone. Inverting this direction locks the intended kinematics, degrades the pad under the rough friction of the substrate, and transfers secondary shear forces to the load-bearing wall.

What flatness tolerance does the padstone require before installation?

The bearing surface must be perfectly flat, horizontal, and free of friable laitance or gravel. Any localised irregularity beneath the elastomer strip causes local stress concentrations that puncture the bearing and lock sliding. Remediation is performed using non-shrink grouting mortar levelled with a straightedge, with systematic spirit level checks prior to placing any sliding strip.

What should be done if concrete has flowed against the edge of the bearing?

Any rigid contact between the slab and the wall negates the function of the bearing device. The hard bridge must be removed immediately before it cures completely, using a light chipping hammer or an angle grinder, without damaging the elastomer. A flexible, compressible watertight joint must then be inserted along the edge to prevent any renewal of contact during thermal deformations and under future imposed loads.

Can a sliding bearing be drilled to pass reinforcement through?

It is strictly forbidden to drill through a sliding bearing plate on the construction site without explicit approval from the civil engineer. Piercing the sliding sheet with a reinforcing bar or hanger creates a mechanical fixed point that prevents any horizontal translation. If a dowelled connection is required by the design calculations, specific sliding sleeves with expansion tubes must be installed on the specified axis.

Texts and standards cited

  • COmaterials and ground: the contractor is liable for the good quality of the materials he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, under pain of bearing the consequences (al. 3).