🧱 CFC 211.1Joints, propping and structural phasingChapter 9 of 10 in the section

Construction site crane: reach, tip load and no-slew zones

This chapter gives you the tools to size a crane layout on a structural work construction site. You will learn how to check the actual load chart against the heaviest precast elements, define no-oversail zones, and coordinate interference between multiple cranes to secure overall structural phasing.

Key takeaways

  • The heaviest and furthest load determines the choice of jib.
  • The maximum working load decreases drastically as the working radius increases.
  • No-oversail zones require reliable electronic airspace restriction.
  • Interference between cranes requires strict vertical offset and certified anti-collision systems.

Determining reach and tip load based on critical structural work loads

The site layout plan (PIC) is not simply about finding a stable spot for the crane mast. The position of the machine dictates the phasing of load-bearing reinforced concrete elements. A full 1,000-litre concrete skip weighs approximately 2.5 tonnes with its slings, while a long-span precast floor plate or precast staircase frequently exceeds 3 tonnes. The location of the batching plant or the truck unloading area must be aligned with the most unfavourable landing point.

Tip load
Residual lifting capacity of a crane at its maximum horizontal reach, measured at the end of its jib. It corresponds to the point where the permissible overturning moment on the steel structure and counterweight is under the greatest stress.

The load chart provided by the manufacturer defines the safe working load for every metre of reach. This curve drops exponentially as the trolley moves away from the mast. The site foreman and the site manager must list every heavy precast piece, identify its coordinates on the formwork plan, and check that the working radius of the chosen crane can support this gross weight plus lifting accessories.

Example of correlation between reach and lifting capacity (standard tower crane)
Working radius from slew centrePermissible gross capacityStandard load delivered to formwork
15 m8,000 kgHeavy formwork panels assembled in ganged sets or high-volume skip
30 m4,100 kgPrecast facade elements, prestressed concrete beams
45 m2,450 kgStandard 800-litre concrete skip with rigging accessories
55 m (jib tip)1,700 kgLight rebar cages, single man-portable formwork panels

The overall organisation must comply with the prevention principles set out by the Swiss legal framework. To prevent occupational accidents and occupational diseases, the employer shall take all measures shown by experience to be necessary, applicable according to the state of the art, and adapted to the given conditions, in accordance with art. 82 LAA. Providing a 10 to 15 percent lifting margin prevents trip-outs by the safe load indicator when stripping adhering wall formwork.

Managing no-oversail zones and multi-crane interference

The airspace of a construction site does not extend freely over neighbouring properties, public land, or site welfare facilities. Oversailing railway tracks, high-voltage lines, schools, or heavily used public roads is strictly regulated or prohibited with a suspended load. The Ordinance on Safety and Health Protection of Workers in Construction Work requires work stations and traffic routes to be secured against falling objects.

Interaction between several cranes on the same project requires strict technical coordination as early as the preparation of the site layout plan. Overlapping operating radii create a permanent collision hazard between jibs, counter-jibs, or hoist cables. When planning construction work, operations must be planned so that the risk of occupational accident, occupational disease, or harm to health is as low as possible, pursuant to art. 3 OTConst.

  1. Vertical clearance between slew planesMaintain a minimum safe vertical clearance between the lowest part of the higher crane (generally the jib tip or fully raised hook block) and the highest part of the lower crane (mast head or tower apex).
  2. Installation of an interconnected anti-collision systemEquip each crane with a dedicated radio link that exchanges slew angle, trolley position, and hook height in real time to automatically decelerate and then arrest converging movements.
  3. Definition of out-of-service weather-vaning priorityEnsure both machines can weather-vane freely out of service at the end of the shift without any jib striking the mast of the adjacent crane under the effect of prevailing winds.

The phasing of slabs and walls must adapt to these plant constraints. If a critical zone can only be oversaoled by the secondary crane with a lower tip load, massive elements must be divided into several pours or delivered at a specific time defined in the site safety plan.

Integration of the crane into the site layout and lift phasing

The site layout plan (PIC) translates lifting capacities into concrete reality on the ground. Mast positioning is not just a matter of convenience for clearance: it dictates concrete phasing, access to formwork storage areas, and skip rotation. If the chosen layout places the rebar unloading area or the skip cleaning station at an excessive radius, placing rates plummet. The site manager and site foreman must verify that each heavy load — twin-wall panels, full-height wall panels, full skips, or precast elements — has a direct path and documented residual capacity.

Crane layout constraints and impacts on reinforced concrete operations
PIC elementSlewing and load constraintDirect consequence on structural work phasing
Rebar fabrication area and reinforcement storagePositioning at intermediate radius (mid-range load area of chart).Supply of steel bundles without exhausting capacity at the jib tip.
Formwork storage area and panel formsRequires a lifting margin above dead weight to overcome bond release.Wall stripping dependent on concrete curing and clearance path.
Crane-and-skip concreting stationHigh gross weight (1,000-litre skip equals approximately 2.5 tonnes with rigging).Dictates slab pour cycle rates; prohibits any excessive radius.
Truck unloading platformsFull visual clearance and direct lifting from the delivery bay.Coordination of floor plate deliveries with concrete pour pauses.

Analysis of lifting cycles shows that a mismatch between usable reach and site spatial organisation creates structural downtime. When the concrete skip must be handled at the limit of capacity, the crane operator slows trolley travel and slewing movements to limit dynamic effects and load swing. This technical precaution, essential for mast stability, extends cycle times during slab pours.

Technical devices for interference, free slewing, and taking out of service

As soon as two or more tower cranes share an oversailing area, or a third-party building borders the plot, the employer must take the required measures. Pursuant to OPA, the employer shall take the measures and precautions that satisfy the provisions of the Ordinance, other applicable occupational safety regulations, and recognised safety and occupational medicine rules. On a hardware level, this entails installing reliable electronic anti-collision systems that act directly on travelling, traversing, and slewing controls.

  1. Configuring interference and no-oversail zonesTechnicians program the geometric coordinates of obstacles into the crane's PLC: CFF railway tracks, power lines, schools, or neighbouring roofs. The system automatically decelerates the drive mechanism and then cuts control inputs as the virtual boundary is approached, preventing the hook from trespassing.
  2. Radio coordination and operating priorityWhere jibs overlap at different elevations, a strict hierarchy is defined. The lower crane generally retains visual right-of-way, while the upper crane adapts its oversailing cycles. Crane operators and slingers communicate on a dedicated, secure radio channel.
  3. Daily out-of-service weather-vaning procedureAt the end of the shift or in winds exceeding operational limits, the slew brake must imperatively be released. The trolley is brought to the inner parking position (or the position specified by the manufacturer), and the hook block is raised to its highest point to avoid snagging overnight obstacles.

Strict control of the working envelope also protects personnel on the ground. According to OTConst, measures must be taken at workstations and traffic routes to ensure workers are not endangered by collapsing structural elements or falling objects and materials. Marking out circulation walkways away from repetitive lifting paths avoids crushing hazards when moving wall panels or rebar bundles to formwork zones.

Managing lifting deviations, faults, and oversail disputes during works

On a structural work construction site, a slewing conflict, an unexpected anti-collision fault, or an attempt to lift an unlisted load instantly halts concrete phasing. When the safe load indicator trips or a heavy load — full concrete skip, twin-wall, or high-bay formwork panel — exceeds safe capacity at the required reach, forcing the movement is out of the question. The crane operator and site foreman must halt the operation without attempting to bypass the machine's electronic safety systems.

  1. Lifting stoppage and securing the loadLand the load on the ground or bring it to a smaller radius that strictly complies with the load chart. If the cut-out is triggered by a no-oversail zone sensor, stabilise the load within the authorised perimeter of the construction site.
  2. Load reassessment and phasing adjustmentWeigh or recalculate the precise weight of the element with the civil engineer (dense reinforcement, residual wet concrete in the skip). Split the load, change the formwork method, or adjust wall casting sequences to bring the element closer to the crane mast.
  3. Technical inspection of interlocking systemsIn the event of a positioning drift between two interfering cranes or over a forbidden zone, lock out the machine concerned. Call out the appointed crane technician or crane electrician to recalibrate the slew-angle sensors and trolley limit switches.

Frequently asked questions

What should be done when a precast element exceeds the planned tip load?

Unloading the element at the critical radius must be refused immediately. Two technical options are available on the construction site: modify structural work phasing to bring a mobile unloading crane closer to the landing area, or review the reinforcement and detailing plan with the civil engineer to supply smaller split units compatible with the actual load chart.

How should one react to a sudden failure of the anti-collision system between two cranes?

Crane slewing within the overlap envelope must stop at once. Foremen switch operations temporarily to degraded manual mode, strictly assisted by ground spotters using dedicated radios on an exclusive channel, with absolute priority given to the lower crane. The crane electrician or official repair service must be called out without delay to service the faulty communication bus.

Wind prevents an out-of-service jib from weather-vaning freely; what should be done?

The crane operator must never leave the slew brake applied when leaving the cab. If the jib does not track freely in the wind due to brake binding or an unforeseen obstruction, call a crane technician immediately. Locking the slewing mechanism exposes the mast to destructive torsional stresses that can lead to collapse under gale-force gusts.

A neighbour reports recurring oversailing of their plot by the jib; how should this be settled?

Verify whether the oversailing occurs unloaded or under load. An unloaded jib passing over an adjacent plot during free weather-vaning is an accepted physical constraint, but moving loads over inhabited private property or a school remains strictly prohibited. The technician adjusts the software limits to restrict trolley travel.

Texts and standards cited

  • CPbreach of the recognised rules of construction: penalises anyone who knowingly endangers the life or limb of persons by contravening the rules of the art
  • OTConst art. 3planning of construction work so that the risk of occupational accident or harm to health is as low as possible